Search results

1 – 10 of over 118000
Article
Publication date: 1 March 1996

DAVID G. PROVERBS, PAUL O. OLOMOLAIYE and FRANK C. HARRIS

The results of a model based survey of contractors' planning engineers in France and the UK suggest that planned completion times for constructing an identical high‐rise in situ…

Abstract

The results of a model based survey of contractors' planning engineers in France and the UK suggest that planned completion times for constructing an identical high‐rise in situ concrete framed structure are significantly and dramatically lower in France than in the UK. Average planned construction periods in France were 13 weeks, some 9 weeks faster than the UK average of 22 weeks. Since planned construction periods reflect past experience, French contractors apparently achieve superior levels of production performance whilst at the same time working fewer hours per week, utilizing directly employed workers and employing fewer supervisors. If such planned completion times are truly representative, the findings indicate comparatively poor UK contractor performance, and signify future problems for the British builder in the emerging European marketplace. The causes of such poor performance are complicated, but based on indicative French best practices: production is enhanced when scheduled overtime is avoided, a directly employed and mainly skilled workforce is engaged, and a maximum working time of 40 hours per week is the norm rather than the exception.

Details

Engineering, Construction and Architectural Management, vol. 3 no. 3
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 1 February 2002

HONG XIAO and DAVID PROVERBS

International comparisons of contractor performance allow contractors in different countries to distinguish their own strengths and weaknesses and improve their competitiveness…

Abstract

International comparisons of contractor performance allow contractors in different countries to distinguish their own strengths and weaknesses and improve their competitiveness accordingly. Based on a survey of contractors in Japan, the UK and the US, contractor time performance is evaluated and compared. It is found that Japanese contractors achieve shorter construction times and higher levels of time certainty than their UK and US counterparts. Furthermore, anticipated delays are far shorter in Japan and levels of client satisfaction are significantly higher than in the US and UK. The superior performance of Japanese contractors may be attributed to their working practices which were characterized by the use of a larger workforce on site, detailed planning, close working relationships with their subcontractors, and an overriding focus on time certainty.

Details

Engineering, Construction and Architectural Management, vol. 9 no. 2
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 3 July 2009

Ahmed Attar, Mohamed Amine Boudjakdji, Nadia Bhuiyan, Khaled Grine, Said Kenai and Ali Aoubed

The purpose of this paper is to show how the time frame for the execution of a construction project in Algeria is rarely respected because of organizational problems and…

Abstract

Purpose

The purpose of this paper is to show how the time frame for the execution of a construction project in Algeria is rarely respected because of organizational problems and uncertainties encountered while the execution is underway.

Design/methodology/approach

A case study on the construction of a metro station is used as a pilot project to show the effectiveness of replacing traditional construction processes by more innovative procedures. Concurrent engineering (CE) is applied to optimize the execution time of the underground structure. A numerical simulation is integrated into the construction process in order to update design parameters with real site conditions observed during the construction process.

Findings

The results show that the implementation of CE is efficient in reducing the completion time, with an 18 per cent reduction observed in this case study. A cost reduction of 20 per cent on the steel frame support and a total cost reduction of 3 per cent were obtained.

Research limitations/implications

The study demonstrates that the application of CE methods can be quite valuable in large, complex construction projects. Vulgarizing it as “the solution” to adjust time frame delay, control quality and cost, might be an issue for local construction enterprises in Algeria.

Originality/value

Using the concept of CE by overlapping different activities involved in a construction project and making use of simulation tools in the process at different stages of the execution have resulted in modifying the excavation method and hence reducing the completion times.

Details

Engineering, Construction and Architectural Management, vol. 16 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 11 April 2021

Mohamed Kasbar, Sheryl Staub-French, Angelique Pilon, Erik Poirier, Zahra Teshnizi and Thomas Froese

The purpose of this paper is to improve the understanding of the impact of mass timber construction methods on construction performance through the successful delivery of the…

Abstract

Purpose

The purpose of this paper is to improve the understanding of the impact of mass timber construction methods on construction performance through the successful delivery of the first-of-a-kind tall wood building, Brock Commons Tallwood House (Tallwood House). This paper is one of a set of papers examining the project; companion papers describe innovations used during the mass timber design and construction processes.

Design/methodology/approach

A mixed-method, longitudinal case study approach was used in this research project to investigate and document the Tallwood House project. Quantitative data were collected to perform the following analysis: hook time, the variability of productivity and schedule reliability. Members of the research team observed construction progress, meetings and decision-making, conducted periodic interviews and reviewed project artifacts.

Findings

The research presented in this paper is the culmination of a longitudinal study aimed at studying the innovation process on a project where radical innovations of structural systems were developed. Prefabrication, combined with the use of a virtual design and construction (VDC) model for planning and fabrication and early collaboration with trades, construction managers and consultants, increased the labor productivity of the on-site erection of the mass timber structural components and envelope panels and expedited the construction schedule.

Originality/value

This paper details an in-depth investigation into the construction productivity for a unique building project and lessons learned. The case study chosen is the construction of Tallwood House at the University of British Columbia. Tallwood House was the tallest mass-timber hybrid building in the world at the time of its construction.

Article
Publication date: 18 June 2019

Yuan Fang and S. Thomas Ng

Precast construction has become increasingly popular in the construction industry. Nonetheless, the logistics of construction materials has been a neglected topic, and this…

Abstract

Purpose

Precast construction has become increasingly popular in the construction industry. Nonetheless, the logistics of construction materials has been a neglected topic, and this neglect has resulted in delays and cost overruns. Careful planning that considers all of the factors affecting construction logistics can ensure project success. The purpose of this paper is to examine the potential for using genetic algorithms (GAs) to derive logistics plans for materials production, supply and consumption.

Design/methodology/approach

The proposed GA model is based on the logistics of precast components from the supplier’s production yard, to the intermediate warehouse and then to the construction site. Using an activity-based costing (ABC) approach, the model not only considers the project schedule, but also takes into account the production and delivery schedule and storage of materials.

Findings

The results show that GAs are suitable for solving time-cost trade-off problems. The optimization process helps to identify the activity start time during construction and the delivery frequency that will result in the minimal cost. What-if scenarios can be introduced to examine the effects of changes in construction logistics on project outcomes.

Originality/value

This paper presents a method for using GAs and an ABC approach to support construction logistics planning decisions. It will help construction planners and materials suppliers to establish material consumption and delivery schedules, rather than relying on subjective judgment.

Details

Engineering, Construction and Architectural Management, vol. 26 no. 10
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 1 January 1998

ALEXANDER LAUFER, AVIAD SHAPIRA and ITZHAK GOREN

The need to provide immediate housing solutions for hundreds of thousands of people in the early 1990's faced the Israeli construction industry with an unprecedented challenge: to…

Abstract

The need to provide immediate housing solutions for hundreds of thousands of people in the early 1990's faced the Israeli construction industry with an unprecedented challenge: to multiply overnight its output and drastically cut construction time. It also created a unique opportunity to observe a national‐level experiment of great magnitude aimed at meeting that challenge. The present paper reports on a study that examined how construction companies managed to cut housing construction time to half of what had been accepted earlier as a normal pace. This was achieved by implementing an approach that concurrently and integratively treats environment, technology and management determinants, creating a synergetic effect. The present paper introduces and demonstrates the integrative approach to schedule compression, and highlights the role of the environment.

Details

Engineering, Construction and Architectural Management, vol. 5 no. 1
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 30 July 2020

Mohamed Saad Bajjou and Anas Chafi

This research seeks to evaluate the impact of applying lean construction principles on the performance of reinforcement operations using a discrete-event simulation (DES) approach.

1318

Abstract

Purpose

This research seeks to evaluate the impact of applying lean construction principles on the performance of reinforcement operations using a discrete-event simulation (DES) approach.

Design/methodology/approach

Process mapping of reinforcements operations was first established through field observation and interviews with construction managers involved in the selected project. Subsequently, quantitative data were gathered and then used to identify the best probabilistic density functions for each activity duration based on the fit-quality tests. Upon testing the validity of the real-world model, a lean simulation model was developed, using ARENA software, to investigate the impact of lean construction principles on the performance of such processes.

Findings

Lean principles are effective in enhancing the performance of the selected construction process. Output performance measurements for real-world model and lean model revealed that lean construction principles led to 41% improvement in process productivity, 14% enhancement in process efficiency and 17% reduction in cycle time.

Research limitations/implications

The statistical findings only represent the process under study (reinforcement process) and cannot be generalized to other construction activities. In order to draw generalizable conclusions, future works are needed to extend this study to different project sizes and more complex construction processes (e.g. bricklaying process and concrete pouring operations). Moreover, there are other factors such as labor skills, rework and uncertainty, site conditions that require further analyses for leaner construction projects.

Originality/value

The methodology and the techniques presented in this work can be used for decision making by analyzing various lean construction scenarios and evaluating their impacts on performance outcomes of any construction process prior to real-world implementation.

Details

International Journal of Productivity and Performance Management, vol. 70 no. 2
Type: Research Article
ISSN: 1741-0401

Keywords

Article
Publication date: 9 June 2020

Qian Chen, Bryan T. Adey, Carl Haas and Daniel M. Hall

Building information modelling (BIM) and radio frequency identification (RFID) technologies have been extensively explored to improve supply chain visibility and coordination of…

1648

Abstract

Purpose

Building information modelling (BIM) and radio frequency identification (RFID) technologies have been extensively explored to improve supply chain visibility and coordination of material flow processes, particularly in the pursuit of Industry 4.0. It remains challenging, however, to effectively use these technologies to enable the precise and reliable coordination of material flow processes. This paper aims to propose a new workflow designed to include the use of detailed look-ahead plans when using BIM and RFID technologies, which can accurately track and match both the dynamic site needs and supply status of materials.

Design/methodology/approach

The new workflow is designed according to lean theory and is modeled using business process modeling notation. To digitally support the workflow, an integrated BIM-RFID database system is constructed that links information on material demands with look-ahead plans. The new workflow is then used to manage material flows in the erection of an office building with prefabricated columns. The performance of the new workflow is compared with that of a traditional workflow, using discrete event simulations. The input for the simulations was derived from expert opinion in semi-structured interviews.

Findings

The new workflow enables contractors to better observe on-site status and differences between the actual and planned material requirements, as well as to alert suppliers if necessary. The simulation results indicate that the new workflow has the potential to reduce the duration of the material flow processes by 16.1% compared with the traditional workflow.

Research limitations/implications

The new workflow is illustrated using a real-world-like situation with input data based on expert opinion. Although the workflow shows potential, it should be tested on a real-world site.

Practical implications

The new workflow allows project participants to combine detailed near-term look-ahead plans with BIM and RFID technologies to better manage material flow processes. It is particularly useful for the management of engineer-to-order components considering the dynamic site progress.

Originality/value

The research improves on existing research focused on using BIM and RFID technologies to improve material flow processes by showing how the workflow can be adapted to use detailed look-ahead plans. It reinforces data-driven construction material management practices through improved visibility and reliability in planning and control of material flow processes.

Article
Publication date: 24 January 2022

Samin Mahdavian, Ming Lu and Estacio Pereira

Previous research regarding shaping factors and major causes behind accidents in the construction field is reviewed. In particular, a hypothetical model is established to…

Abstract

Purpose

Previous research regarding shaping factors and major causes behind accidents in the construction field is reviewed. In particular, a hypothetical model is established to correlate activity time, cost and safety in the context of construction activity acceleration planning. Two demonstration cases are presented to illustrate the proposed theoretical model in the context of critical activity expedition planning. Further, a third case uses a 100-activity project to perform the global level total project time and cost analysis, identifying specific activity acceleration plans that would materialize the shortened total project time at the lowest total project cost.

Design/methodology/approach

This research proposes a safety-centric application framework to guide construction acceleration planning at both activity and project levels while taking sufficient preventive measures against safety hazards and accidents. As planning construction acceleration by factoring in safety constraints inevitably drives up cost, it is imperative to control increases in activity costs at the local level in connection with schedule acceleration planning while at the same time not compromising on safety. This research also addresses this critical question through performing global level total project time and cost analysis.

Findings

An application framework is proposed for guiding a planner through identifying accident shaping factors, obeying schedule acceleration rules and accounting for safety-related costs in attempts to mitigate hazardous situations on-site at both activity level (local) and project level (global), resulting in (1) minimizing the increase of total project cost in schedule acceleration while at the same time not compromising on safety at individual activities; (2) producing specific execution plans on each individual activity in terms of the amount of time to crash and the associated activity cost.

Originality/value

This study is original in developing theories and methods for evaluating the impact of safety constraints upon construction time and cost in activity acceleration planning and project time-cost analysis. The research fills a gap in knowledge in terms of how to factor in sufficient safety constraints while achieving project time and cost objectives on construction acceleration planning at both activity and project levels.

Details

Engineering, Construction and Architectural Management, vol. 30 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 30 March 2021

Alireza Ahmadian Fard Fini, Mojtaba Maghrebi, Perry John Forsythe and Travis Steven Waller

Measuring onsite productivity has been a substance of debate in the construction industry, mainly due to concerns about accuracy, repeatability and unbiasedness. Such…

Abstract

Purpose

Measuring onsite productivity has been a substance of debate in the construction industry, mainly due to concerns about accuracy, repeatability and unbiasedness. Such characteristics are central to demonstrate construction speed that can be achieved through adopting new prefabricated systems. Existing productivity measurement methods, however, cannot cost-effectively provide solid and replicable evidence of prefabrication benefits. This research proposes a low-cost automated method for measuring onsite installation productivity of prefabricated systems.

Design/methodology/approach

Firstly, the captured ultra-wide footages are undistorted by extracting the curvature contours and performing a developed meta-heuristic algorithm to straighten these contours. Then a preprocessing algorithm is developed that could automatically detect and remove the noises caused by vibrations and movements. Because this study aims to accurately measure the productivity the noise free images are double checked in a specific time window to make sure that even a tiny error, which have not been detected in the previous steps, will not been amplified through the process. In the next step, the existing side view provided by the camera is converted to a top view by using a spatial transformation method. Finally, the processed images are compared with the site drawings in order to detect the construction process over time and report the measured productivity.

Findings

The developed algorithms perform nearly real-time productivity computations through exact matching of actual installation process and digital design layout. The accuracy and noninterpretive use of the proposed method is demonstrated in construction of a multistorey cross-laminated timber building.

Originality/value

This study uses footages of an already installed surveillance camera where the camera's features are unknown and then image processing algorithms are deployed to retrieve accurate installation quantities and cycle times. The algorithms are almost generalized and versatile to be adjusted to measure installation productivity of other prefabricated building systems.

Details

Engineering, Construction and Architectural Management, vol. 29 no. 2
Type: Research Article
ISSN: 0969-9988

Keywords

1 – 10 of over 118000