1 – 10 of over 9000Richard Kadan, Temitope Seun Omotayo, Prince Boateng, Gabriel Nani and Mark Wilson
This study aimed to address a gap in subcontractor management by focusing on previously unexplored complexities surrounding subcontractor management in developing countries. While…
Abstract
Purpose
This study aimed to address a gap in subcontractor management by focusing on previously unexplored complexities surrounding subcontractor management in developing countries. While past studies concentrated on selection and relationships, this study delved into how effective subcontractor management impacts project success.
Design/methodology/approach
This study used the Bayesian Network analysis approach, through a meticulously developed questionnaire survey refined through a piloting stage involving experienced industry professionals. The survey was ultimately distributed among participants based in Accra, Ghana, resulting in a response rate of approximately 63%.
Findings
The research identified diverse components contributing to subcontractor disruptions, highlighted the necessity of a clear regulatory framework, emphasized the impact of financial and leadership assessments on performance, and underscored the crucial role of main contractors in Integrated Project and Labour Cost Management with Subcontractor Oversight and Coordination.
Originality/value
Previous studies have not considered the challenges subcontractors face in projects. This investigation bridges this gap from multiple perspectives, using Bayesian network analysis to enhance subcontractor management, thereby contributing to the successful completion of construction projects.
Details
Keywords
Zoubeir Lafhaj, Slim Rebai, Olfa Hamdi, Rateb Jabbar, Hamdi Ayech and Pascal Yim
This study aims to introduce and evaluate the COPULA framework, a construction project monitoring solution based on blockchain designed to address the inherent challenges of…
Abstract
Purpose
This study aims to introduce and evaluate the COPULA framework, a construction project monitoring solution based on blockchain designed to address the inherent challenges of construction project monitoring and management. This research aims to enhance efficiency, transparency and trust within the dynamic and collaborative environment of the construction industry by leveraging the decentralized, secure and immutable nature of blockchain technology.
Design/methodology/approach
This paper employs a comprehensive approach encompassing the formulation of the COPULA model, the development of a digital solution using the ethereum blockchain and extensive testing to assess performance in terms of execution cost, time, integrity, immutability and security. A case analysis is conducted to demonstrate the practical application and benefits of blockchain technology in real-world construction project monitoring scenarios.
Findings
The findings reveal that the COPULA framework effectively addresses critical issues such as centralization, privacy and security vulnerabilities in construction project management. It facilitates seamless data exchange among stakeholders, ensuring real-time transparency and the creation of a tamper-proof communication channel. The framework demonstrates the potential to significantly enhance project efficiency and foster trust among all parties involved.
Research limitations/implications
While the study provides promising insights into the application of blockchain technology in construction project monitoring, future research could explore the integration of COPULA with existing project management methodologies to broaden its applicability and impact. Further investigations into the solution’s scalability and adaptation to various construction project types and sizes are also suggested.
Originality/value
This research offers a comprehensive blockchain solution specifically tailored for the construction industry. Unlike prior studies focusing on theoretical aspects, this paper presents a practical, end-to-end solution encompassing model formulation, digital implementation, proof-of-concept testing and validation analysis. The COPULA framework marks a significant advancement in the digital transformation of construction project monitoring, providing a novel approach to overcoming longstanding industry challenges.
Details
Keywords
Hasith Chathuranga Victar and Anuradha Samarajeewa Waidyasekara
Construction and Demolition (C&D) Waste Management (WM) poses significant challenges in Sri Lanka, contributing to environmental degradation and resource depletion. To address…
Abstract
Purpose
Construction and Demolition (C&D) Waste Management (WM) poses significant challenges in Sri Lanka, contributing to environmental degradation and resource depletion. To address these issues, this study explores the application of Circular Economy (CE) strategies in minimising waste generation and optimising resource utilisation in Sri Lankan construction industry. The research focuses on the construction and building renovation and use and operate stages of the building project life cycle, recognising their significance in waste generation and resource consumption.
Design/methodology/approach
The research employed a qualitative approach, utilising the Delphi technique through three rounds of expert interviews. Seventeen experts were involved in the first round, followed by fifteen in the second round, and twelve in the final round. The collected data was analysed using manual content analysis methods.
Findings
The research findings revealed fifteen C&D WM issues in the construction and building renovation stage in Sri Lanka, along with suitable strategies to overcome each of them. Similarly, eight C&D WM issues were identified for the use and operate stage of the building, and corresponding strategies were provided to address each issue. By adopting CE strategies such as modular design and material reuse, construction projects can optimise the project's timeline, cost, and quality factors. These strategies enable efficient resource allocation, reduce waste generation, and contribute to the overall sustainability of the project. The impact of CE strategies on mitigating these issues within the project management iron triangle was also discussed.
Originality/value
This paper entails delving into how construction, building renovation, and operation stages of a building's life cycle intersect with CE strategies, which profoundly influence operational efficiency and long-term sustainability. By incorporating principles such as energy efficiency, water conservation, and circular product design, the paper illuminates how these strategies facilitate decreased energy usage, enhanced resource management, and diminished waste production throughout the building's lifespan.
Details
Keywords
Handan Kunkcu, Kerim Koc and Asli Pelin Gurgun
Work–family conflict is one of the most challenging stressors for construction industry professionals to cope with emotional problems. This study aims to propose a model linking…
Abstract
Purpose
Work–family conflict is one of the most challenging stressors for construction industry professionals to cope with emotional problems. This study aims to propose a model linking work–family conflict and high-quality relationships among project team members and explore mediating effects of life and job satisfactions.
Design/methodology/approach
A theoretical framework was established based on the spillover theory and social exchange theory. Data were obtained by a questionnaire survey conducted with 328 respondents working in construction projects. Structural equation modeling (SEM) was used to test interrelationships among work–family conflict, job satisfaction, life satisfaction and high-quality relationship.
Findings
The results indicate that work–family conflict is negatively associated with both job and life satisfactions of construction professionals. In addition, there were direct and positive relationships between satisfaction domains and high-quality relationship capacity. The findings further support that job satisfaction plays a mediating role between work–family conflict and high-quality relationship among construction professionals, while life satisfaction does not mediate the relationship.
Originality/value
The effects of interrole conflicts on the context of satisfaction have been investigated previously; however, there is a lack of knowledge regarding its influence on high-quality relationship among project team members. This study extends the body of knowledge on high-quality relationships among project team members to understand how conflict and satisfaction factors influence interpersonal relationships in construction project management.
Details
Keywords
Yuanwen Han, Jiang Shen, Xuwei Zhu, Bang An and Xueying Bao
This study aims to develop an interface management risk interaction modeling and analysis methodology applicable to complex systems in high-speed rail construction projects…
Abstract
Purpose
This study aims to develop an interface management risk interaction modeling and analysis methodology applicable to complex systems in high-speed rail construction projects, reveal the interaction mechanism of interface management risk and provide theoretical support for project managers to develop appropriate interface management risk response strategies.
Design/methodology/approach
This paper introduces the association rule mining technique to improve the complex network modeling method. Taking China as an example, based on the stakeholder perspective, the risk factors and significant accident types of interface management of high-speed rail construction projects are systematically identified, and a database is established. Then, the Apriori algorithm is used to mine and analyze the strong association rules among the factors in the database, construct the complex network, and analyze its topological characteristics to reveal the interaction mechanism of the interface management risk of high-speed rail construction projects.
Findings
The results show that the network is both scale-free and small-world, implying that construction accidents are not random events but rather the result of strong interactions between numerous interface management risks. Contractors, technical interfaces, mechanical equipment, and environmental factors are the primary direct causal factors of accidents, while owners and designers are essential indirect causal factors. The global importance of stakeholders such as owners, designers, and supervisors rises significantly after considering the indirect correlations between factors. This theoretically explains the need to consider the interactions between interface management risks.
Originality/value
The interaction mechanism between interface management risks is unclear, which is an essential factor influencing the decision of risk response measures. This study proposes a new methodology for analyzing interface management risk response strategies that incorporate quantitative analysis methods and considers the interaction of interface management risks.
Details
Keywords
Francis Nuako, Frank Ato Ghansah and Thomas Adusei
It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been…
Abstract
Purpose
It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been advancements in the management of building projects throughout time but cost overruns remain a key concern in the construction sector internationally, particularly in emerging economies such as Ghana. This study aims to answer the question, “What are the critical success factors (CSFs) that can assist reduce cost overruns in public sector infrastructure projects in the Ghanaian construction industry?”
Design/methodology/approach
This study used a quantitative survey method. The questionnaire was pre-tested by interviewing 15 contractors to ascertain the validity of the content. Factor analysis and multiple regression were adopted to analyze the data.
Findings
This study discovered that the critical factors that can reduce cost overruns in construction projects in Ghana are directly linked to five themes: early contractor involvement in the project planning stage, adequate funding, good project team relations, competent managers/supervisors and project participant incentives/bonuses. This study identifies indestructible, empirically measurable important success criteria for reducing cost overruns in public building projects in Ghana.
Practical implications
When well thought through from the project initiation stage to completion, these critical successes can also be used to deal with damaging economic effects such as allocative inefficiency of scarce resources, further delays, contractual disputes, claims and litigation, project failure and total abandonment.
Originality/value
The uniqueness of this research resides in the fact that it is, to the best of the authors’ knowledge, a first-of-its-kind investigation of the CSFs for reducing cost overruns in public building projects in developing countries.
Details
Keywords
N. Aishah Abdul-Rahman, Rahimi A. Rahman and Ahmad Rizal Alias
This study aims to develop an interrelation model between critical parameters for assessing the construction readiness (CR) of abandoned housing projects, using Malaysia as a case…
Abstract
Purpose
This study aims to develop an interrelation model between critical parameters for assessing the construction readiness (CR) of abandoned housing projects, using Malaysia as a case study. To achieve that aim, the study objectives are to (1) identify critical parameters for assessing the CR of abandoned housing projects; (2) develop underlying constructs to categorize interrelated critical parameters and (3) assess the influence of the underlying constructs on the CR of abandoned housing projects.
Design/methodology/approach
This study identifies potential parameters for assessing the CR of abandoned housing projects by reviewing existing literature and interviewing industry professionals. Then, the list was used to develop a questionnaire survey. The collected survey data were analyzed using normalized mean analysis to identify the critical parameters. Exploratory factor analysis (EFA) was used to develop underlying constructs to categorize interrelated critical parameters. Finally, the influence of the underlying constructs on the CR of abandoned housing projects was examined through partial least squares structural equation modeling (PLS-SEM).
Findings
The analyses suggest that 21 critical parameters are affecting the CR of abandoned housing projects. The critical parameters can be categorized into four underlying constructs: construction site evaluation, management verification, uncertainties mitigation and document approval. Finally, the analyses confirmed that all four constructs affect the CR of abandoned housing projects.
Originality/value
This study is a pioneering effort to quantitatively analyze the parameters for assessing the CR of abandoned housing projects. The findings significantly benefit researchers and industry professionals by providing a list of critical parameters associated with the CR of abandoned housing projects.
Details
Keywords
Mohamed Marzouk and Dina Hamdala
The aggressive competition in the real estate market forces real estate developers to tackle the challenge of selecting the best project construction phasing alternative. The real…
Abstract
Purpose
The aggressive competition in the real estate market forces real estate developers to tackle the challenge of selecting the best project construction phasing alternative. The real estate industry is characterized by high costs, high profit and high risks. The schedules of real estate projects are also characterized by having large number of repetitive activities that are executed over a long duration. The repetitiveness, long duration of execution, the high amounts of money involved and the high risk made it desirable to leverage the impact of changes in phasing plans on net present value of amounts incurred and received over the long execution and selling duration. This also changes the project progress, and delivery time as well as their respective impact on customer degree of satisfaction. This research addresses the problem of selecting the best phasing alternative for real estate development projects while maximizing customer satisfaction and project profit.
Design/methodology/approach
The research proposes a model that generates all construction phasing alternatives and performs decision-making to rank all possible phasing alternatives. The proposed model consists of five modules: (1) Phasing Sequencing module, (2) Customer Satisfaction module, (3) Cash-In calculation module, (4) Cost Estimation module and (5) Decision-making module. A case study was presented to demonstrate the practicality of the model.
Findings
The proposed model satisfies the real estate market's need for proper construction phasing plans evaluation and selection against the project's main success criteria, customer satisfaction and project profit. The proposed model generates all construction phasing alternatives and performs multi-criteria decision making to rank all possible phasing alternatives. It quantifies the score of the two previously mentioned criteria and ranks all solutions according to their overall score.
Research limitations/implications
The research proposes a model that assist real estate market's need for proper construction phasing plans evaluation and selection against the project's main success criteria, customer satisfaction and project profit. The proposed model can be used to conclude general guidelines and common successful practices to be used by real estate developers when deciding the construction phasing plan. In this study the model is based on business models where all the project units are sold, rental cases are not considered. Also, the budget limitations that might exist when phasing is not considered in the model computations.
Originality/value
The model can be used as a complete platform that can hold all real estate project data, process revenues and cost information for estimating profit, plotting cash flow profiles, quantifying the degree of customer satisfaction attributable to each phasing alternative and providing recommendation showing the best one. The model can be used to conclude general guidelines and common successful practices to be used by real estate developers when tackling the challenge of selecting construction phasing plans.
Details
Keywords
Agana Parameswaran, K.A.T.O. Ranadewa and Akila Pramodh Rathnasinghe
The proliferation of lean principles in the construction industry is offset by the enduring uncertainty among industry stakeholders regarding their respective roles in lean…
Abstract
Purpose
The proliferation of lean principles in the construction industry is offset by the enduring uncertainty among industry stakeholders regarding their respective roles in lean implementation. This uncertainty is further compounded by the scarcity of empirical investigations in this area. Consequently, this study undertakes the task of bridging this knowledge gap by identifying the critical roles of lean learners and their indispensable contributions to achieving successful lean implementation.
Design/methodology/approach
A qualitative exploratory approach informed by an interpretivism perspective was adopted. The case study strategy was employed to gather data from three contracting organisations that had implemented lean practices. Empirical data was collected through in-depth semi-structured interviews with fifteen industry experts and complemented by document reviews. To analyse the data, a code-based content analysis approach was employed using NVivo software, while Power BI software was utilised to develop a comprehensive force-directed graph visualisation.
Findings
The research findings substantiated nine lean learners and unveiled a set of seventy-three roles associated with them. The force-directed graph facilitated the identification of lean learners and their connections to the emerged roles. Notably, the graph highlighted the pivotal role played by project managers and internal lean trainers in ensuring the success of lean implementation, surpassing the contributions of other lean learners.
Originality/value
The implications of findings extend to industry professionals seeking to establish a robust lean learning framework to expedite lean implementation within the construction sector. This study not only provides a comprehensive definition of lean learners’ roles but also transcends specific construction types, making it a significant catalyst for global impact.
Details
Keywords
Kenneth Lawani, Farhad Sadeghineko, Michael Tong and Mehmethan Bayraktar
The purpose of this study is to explore the suggestions that construction processes could be considerably improved by integrating building information modelling (BIM) with 3D…
Abstract
Purpose
The purpose of this study is to explore the suggestions that construction processes could be considerably improved by integrating building information modelling (BIM) with 3D laser scanning technologies. This case study integrated 3D laser point cloud scans with BIM to explore the effects of BIM adoption on ongoing construction project, whilst evaluating the utility of 3D laser scanning technology for producing structural 3D models by converting point cloud data (PCD) into BIM.
Design/methodology/approach
The primary data acquisition adopted the use of Trimble X7 laser scanning process, which is a set of data points in the scanned space that represent the scanned structure. The implementation of BIM with the 3D PCD to explore the precision and effectiveness of the construction processes as well as the as-built condition of a structure was precisely captured using the 3D laser scanning technology to recreate accurate and exact 3D models capable of being used to find and fix problems during construction.
Findings
The findings indicate that the integration of BIM and 3D laser scanning technology has the tendency to mitigate issues such as building rework, improved project completion times, reduced project cost, enhanced interdisciplinary communication, cooperation and collaboration amongst the project duty holders, which ultimately enhances the overall efficiency of the construction project.
Research limitations/implications
The acquisition of data using 3D laser scanner is usually conducted from the ground. Therefore, certain aspects of the building could potentially disturb data acquisition; for example, the gable and sections of eaves (fascia and soffit) could be left in a blind spot. Data acquisition using 3D laser scanner technology takes time, and the processing of the vast amount of data acquired is laborious, and if not carefully analysed, could result in errors in generated models. Furthermore, because this was an ongoing construction project, material stockpiling and planned construction works obstructed and delayed the seamless capture of scanned data points.
Originality/value
These findings highlight the significance of integrating BIM and 3D laser scanning technology in the construction process and emphasise the value of advanced data collection methods for effectively managing construction projects and streamlined workflows.