Search results
1 – 10 of over 2000Kesavan Manoharan, Pujitha Dissanayake, Chintha Pathirana, Dharsana Deegahawature and Renuka Silva
Sources highlight that insufficient skills of site supervisors considerably influence the progress of many construction projects in numerous countries. This study intends to…
Abstract
Purpose
Sources highlight that insufficient skills of site supervisors considerably influence the progress of many construction projects in numerous countries. This study intends to identify the crucial supervisory competencies that influence the effectiveness of building project operations in the context of developing countries.
Design/methodology/approach
The crucial construction site supervisory competencies were qualitatively identified through a comprehensive literature survey and a series of expert interviews with the use of thematic analysis approaches. A questionnaire survey was then carried out among 154 building project firms to quantify the impacts of the competencies on the effectiveness of project tasks with the use of the relative importance index approach. Additionally, industry-consultative meetings were held using problem-focused communication strategies to scrutinise the necessary actions.
Findings
Overall, 22 cognitive elements and 24 skills/abilities of supervisors were determined as being critical according to their impact values, where the site supervisors cognitive domains in construction planning and construction materials were determined as the top-ranking competencies in the list, with their manual skills/abilities in labour management and labour performance evaluation. Accordingly, a group of key competency outcomes were produced for the considerations in developing new site supervisory training components. Relevant statistical analysis results and the industry consultative outcomes substantiated the validity and dependability of the overall results.
Research limitations/implications
Although the study's focus was to site supervision procedures used in Sri Lankan building construction projects, the overall findings/outcomes might be put to the test in related situations in other emerging industries in other countries.
Originality/value
The study has constructed a base that shows how the significant site supervisory competencies influence the effectiveness of building construction operations, contributing to making a big difference in the methods of reskilling/upskilling in the industry associated with construction labour, supervision, efficiency management and productivity enhancement.
Details
Keywords
Kesavan Manoharan, Pujitha Dissanayake, Chintha Pathirana, Dharsana Deegahawature and Renuka Silva
Labour efficiency is the key component for the long-term sustainability of construction firms. Recent studies show that modernising organisational/managerial processes is…
Abstract
Purpose
Labour efficiency is the key component for the long-term sustainability of construction firms. Recent studies show that modernising organisational/managerial processes is necessary to raise labour efficiency in many emerging nations. Construction supervision is a crucial element in organisational/managerial practices, which provide blood circulation to the project operations by directing labour. Accordingly, this study aims to quantify the impacts of crucial organisational/managerial elements on the efficiency of labour in building construction projects based on the viewpoint of construction supervisors.
Findings
A total of 28 factors were determined as critical, where lack of labour motivation, poor labour training facilities, poor performance evaluation practices, no labour rewarding mechanism and poor communication/cooperation between parties were judged to be the top five key issues in the list. The validity and reliability of the study findings were ensured through statistical tests and the experts' discussion outcomes. In view of the evolving challenges facing the industry, the results indicate that the organisational policies of construction enterprises in place addressing financial procedures, communication strategies, resource management and performance management practices must be enhanced.
Research limitations/implications
The study findings will make a substantial contribution to reducing the disparity between organisation/management policies and labour practices towards changing how the sector operates to increase labour efficiency in construction projects.
Originality/value
This study contributes to addressing the knowledge gap in the industry associated with the organisational protocols, especially to understand/predict how such elements are significant, how much they influence the efficiency of construction practices and what steps can be made to limit their effects on labour efficiency in construction. These could be crucial in modernising organisational policies and procedures for construction management.
Details
Keywords
Kesavan Manoharan, Pujitha Dissanayake, Chintha Pathirana, Dharsana Deegahawature and Renuka Silva
Past studies highlight a wide range of labour-related problems resulting in productivity loss in the construction industry of many developing countries. This study aims to…
Abstract
Purpose
Past studies highlight a wide range of labour-related problems resulting in productivity loss in the construction industry of many developing countries. This study aims to quantify the impacts of labour-related factors on the productivity of construction operations in Sri Lankan building projects based on the viewpoint of engineers and construction managers for upgrading management/organisational policies and practices.
Design/methodology/approach
Qualitative and quantitative approaches were used to identify the critical factors. Further, a series of industry consultative discussions were conducted through problem-based communication approaches to analyse the actions required.
Findings
A total of 21 factors were determined as critical, where skills shortage, labourers’ thinking abilities, work experience, knowledge in construction works and discipline were leading in the list. The statistical tests and the experts’ discussion outcomes ensured the validity and reliability of the study findings.
Research limitations/implications
The study outcomes will contribute to finding out better ways for directing labour in the industry practices and revising organisational policies towards achieving higher productivity levels in construction operations. Though the study findings are limited to the Sri Lankan context, some findings may be tested in other developing countries in similar scenarios.
Originality/value
The study findings show why the identified factors are critical, how those influence construction practices and what actions need to be considered for addressing the industry’s productivity-related challenges. These can play a key role in upgrading the construction management practices and organisational policies to the near-future stages.
Details
Keywords
Kesavan Manoharan, Pujitha Dissanayake, Chintha Pathirana, Dharsana Deegahawature and Renuka Silva
Site supervision features largely influence the productivity status of construction operational processes. This study aims to use a case study containing mixed methods to test the…
Abstract
Purpose
Site supervision features largely influence the productivity status of construction operational processes. This study aims to use a case study containing mixed methods to test the site supervisory traits in applying mathematical theories to construction operations for directing supervisory capabilities under various operational characteristics.
Design/methodology/approach
A total of 62 construction site supervisors were trained as part of a new apprenticeship programme. Through literature reviews and expert consultations, grading criteria were designed with various degrees of descriptions and score ratings. The supervisory attributes were evaluated under seven competency element characteristics mapped with the relevant learning domains.
Findings
The results demonstrate a detailed sectional view of performance ratings of supervisors under different characteristics of competency factors with the validity, reliability, applicability and generalisability assurance of the research findings using relevant statistical tests and expert evaluations.
Research limitations/implications
Though the research applications were engaged directly with the construction industry in the Sri Lankan setting, other developing countries and emerging industries can also employ equivalent tactics to attain similar outcomes in their industry-based operations.
Originality/value
The research findings have led to producing a new guide that makes significant impacts on deciding the capability levels in construction supervisory attributes while executing problem-solving applications in construction planning and operational processes. Accordingly, the findings push to open a gate to intake advanced cognitive attributes towards addressing the industry's knowledge gap on how the problem-solving-based apprenticeship protocols need to be linked with the supervision features.
Details
Keywords
Robert Larsson and Martin Rudberg
This paper aims to study the effects of different weather conditions on typical concrete work tasks’ productivity. Weather is one important factor that has a negative impact on…
Abstract
Purpose
This paper aims to study the effects of different weather conditions on typical concrete work tasks’ productivity. Weather is one important factor that has a negative impact on construction productivity. Knowledge about how weather affects construction works is therefore important for the construction industry, e.g. during planning and execution of construction projects.
Design/methodology/approach
A questionnaire survey method is used involving means to perform pairwise comparisons of different weather factors according to the analytical hierarchical process (AHP). The survey also contains means to enable assessment of the loss in productivity for typical work tasks exposed to different weather types. The survey targets practitioners involved in Swedish concrete construction projects, and the results are compared with previous research findings.
Findings
The survey covers responses from 232 practitioners with long experience of concrete construction. The pairwise comparisons reveal that practitioners rank precipitation as the most important followed by wind and temperature. The loss in productivity varies significantly (from 0 to 100%) depending on the type of work and the type of weather factor considered. The results partly confirm findings reported in previous research but also reveal a more complex relationship between weather and productivity indicating several underlying influencing factors such as type of work, type of weather (e.g. rain or snow) and the intensity of each weather factor.
Originality/value
This paper presents new data about how 232 practitioners assess the effects of weather on construction productivity involving novel means to perform objective rankings such as the AHP methodology.
Details
Keywords
The future construction site will be pervasive, context aware and embedded with intelligence. The purpose of this paper is to explore and define the concept of the digital skin of…
Abstract
Purpose
The future construction site will be pervasive, context aware and embedded with intelligence. The purpose of this paper is to explore and define the concept of the digital skin of the future smart construction site.
Design/methodology/approach
The paper provides a systematic and hierarchical classification of 114 articles from both industry and academia on the digital skin concept and evaluates them. The hierarchical classification is based on application areas relevant to construction, such as augmented reality, building information model-based visualisation, labour tracking, supply chain tracking, safety management, mobile equipment tracking and schedule and progress monitoring. Evaluations of the research papers were conducted based on three pillars: validation of technological feasibility, onsite application and user acceptance testing.
Findings
Technologies learned about in the literature review enabled the envisaging of the pervasive construction site of the future. The paper presents scenarios for the future context-aware construction site, including the construction worker, construction procurement management and future real-time safety management systems.
Originality/value
Based on the gaps identified by the review in the body of knowledge and on a broader analysis of technology diffusion, the paper highlights the research challenges to be overcome in the advent of digital skin. The paper recommends that researchers follow a coherent process for smart technology design, development and implementation in order to achieve this vision for the construction industry.
Details
Keywords
Oluseyi Julius Adebowale and Justus Ngala Agumba
Despite the significance of the construction industry to the nation's economic growth, there is empirical evidence that the sector is lagging behind other industries in terms of…
Abstract
Purpose
Despite the significance of the construction industry to the nation's economic growth, there is empirical evidence that the sector is lagging behind other industries in terms of productivity growth. The need for improvements inspired the industry's stakeholders to consider using emerging technologies that support the enhancement. This research aims to report augmented reality applications essential for contractors' productivity improvement.
Design/methodology/approach
This study systematically reviewed academic journals. The selection of journal articles entailed searching Scopus and Web of Science databases. Relevant articles for reviews were identified and screened. Content analysis was used to classify key applications into six categories. The research results were limited to journal articles published between 2010 and 2021.
Findings
Augmented reality can improve construction productivity through its applications in assembly, training and education, monitoring and controlling, interdisciplinary function, health and safety and design information.
Originality/value
The research provides a direction for contractors on key augmented reality applications they can leverage to improve their organisations' productivity.
Details
Keywords
This paper aims to provide top-level design and basic platform for intelligent application in China high-speed railway.
Abstract
Purpose
This paper aims to provide top-level design and basic platform for intelligent application in China high-speed railway.
Design/methodology/approach
Based on the analysis for the future development trends of world railway, combined with the actual development needs in China high-speed railway, The definition and scientific connotation of intelligent high-speed railway (IHSR) are given at first, and then the system architecture of IHSR are outlined, including 1 basic platform, 3 business sectors, 10 business fields, and 18 innovative applications. At last, a basic platform with cloud edge integration for IHSR is designed.
Findings
The rationality, feasibility and implementability of the system architecture of IHSR have been verified on and applied to the Beijing–Zhangjiakou high-speed railway, providing important support for the construction and operation of the world’s first IHSR.
Originality/value
This paper systematically gives the definition and connotation of the IHSR and put forward the system architecture of IHSR for first time. It will play the most important role in the design, construction and operation of IHSR.
Details
Keywords
Pablo Ballesteros-Pérez, Maria Luisa del Campo-Hitschfeld, Manuel Alejandro González-Naranjo and Mari Carmen González-Cruz
Construction projects usually suffer delays, and the causes of these delays and its cost overruns have been widely discussed, the weather being one of the most recurrent. The…
Abstract
Purpose
Construction projects usually suffer delays, and the causes of these delays and its cost overruns have been widely discussed, the weather being one of the most recurrent. The purpose of this paper is to analyze the influence of climate on standard construction work activities through a case study.
Design/methodology/approach
By studying the extent at which some weather variables impede outdoor work from being effectively executed, new maps and tables for planning for delays are presented. In addition, a real case regarding the construction of several bridges in southern Chile is analyzed.
Findings
Few studies have thoroughly addressed the influences of major climatic agents on the most common outdoor construction activities. The method detailed here provides a first approximation for construction planners to assess to what extent construction productivity will be influenced by the climate.
Research limitations/implications
Although this study was performed in Chile, the simplified method proposed is entirely transferable to any other country, however, other weather or combinations of weather variables could be needed in other environments or countries.
Practical implications
The implications will help reducing the negative social, economic and environmental outcomes that usually emerge from project delays.
Originality/value
Climatic data were processed using extremely simple calculations to create a series of quantitative maps and tables that would be useful for any construction planner to decide the best moment of the year to start a project and, if possible, where to build it.
Details
Keywords
Kailun Feng, Shiwei Chen, Weizhuo Lu, Shuo Wang, Bin Yang, Chengshuang Sun and Yaowu Wang
Simulation-based optimisation (SO) is a popular optimisation approach for building and civil engineering construction planning. However, in the framework of SO, the simulation is…
Abstract
Purpose
Simulation-based optimisation (SO) is a popular optimisation approach for building and civil engineering construction planning. However, in the framework of SO, the simulation is continuously invoked during the optimisation trajectory, which increases the computational loads to levels unrealistic for timely construction decisions. Modification on the optimisation settings such as reducing searching ability is a popular method to address this challenge, but the quality measurement of the obtained optimal decisions, also termed as optimisation quality, is also reduced by this setting. Therefore, this study aims to develop an optimisation approach for construction planning that reduces the high computational loads of SO and provides reliable optimisation quality simultaneously.
Design/methodology/approach
This study proposes the optimisation approach by modifying the SO framework through establishing an embedded connection between simulation and optimisation technologies. This approach reduces the computational loads and ensures the optimisation quality associated with the conventional SO approach by accurately learning the knowledge from construction simulations using embedded ensemble learning algorithms, which automatically provides efficient and reliable fitness evaluations for optimisation iterations.
Findings
A large-scale project application shows that the proposed approach was able to reduce computational loads of SO by approximately 90%. Meanwhile, the proposed approach outperformed SO in terms of optimisation quality when the optimisation has limited searching ability.
Originality/value
The core contribution of this research is to provide an innovative method that improves efficiency and ensures effectiveness, simultaneously, of the well-known SO approach in construction applications. The proposed method is an alternative approach to SO that can run on standard computing platforms and support nearly real-time construction on-site decision-making.
Details