Article
Publication date: 18 June 2021

Adedotun Ojo, Olusola Ogunsina and Deji R. Ogunsemi

The purpose of the work presented here is to assess the cost management practices of civil engineering organisations in Nigeria, with an overall aim of developing a generic cost…

Abstract

Purpose

The purpose of the work presented here is to assess the cost management practices of civil engineering organisations in Nigeria, with an overall aim of developing a generic cost management process map. The first objective is to compare existing frameworks theoretically to highlight their strengths and weaknesses. The second objective is to use the findings of the first objective to assess or benchmark the developed process map obtained from the multiple cases. The third objective is to compare the generic process map with the traditional building cost management process map to evaluate the strengths and shortcomings of the generic process map, which resulted in conclusions and recommendations made at the end of the research.

Design/methodology/approach

Data for the work was collected via semi-structured interviews, review of literature and official documents of the civil engineering organisations visited. To achieve the stated objectives, comparative analysis technique was used to compare existing frameworks on cost management to obtain the basis to benchmark the generic process map. The single case narrative technique was used to present each case; and the cross-case synthesis technique was used to present the multiple cases on each cost management process examined. Then, process maps were deployed to represent the homogeneous sets of civil engineering organisations, out of which the generic process map was developed. Comparative analysis was again deployed to compare the generic process map with the traditional building process map of cost management practice to evaluate the findings.

Findings

It was found out that the generic civil engineering process map is not as detailed and effective as the building process map in providing best value for money, accurate early cost estimates, accurate cost certainty and post-contract cost control.

Originality/value

This research study provides an industrial impetus to push for the involvement of more quantity surveyors (QS) as cost management process owners in the procurement of civil engineering projects in Nigeria, hence encouraging government’s efforts in the enforcement of more accurate project cost estimates and promoting the QS’s project-specific advice on capital, operational, maintenance and life cycle costs.

Details

Journal of Financial Management of Property and Construction , vol. 27 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 1 December 2020

Ahmed Yousry Akal and Amr Metwally El-Kholy

This work affords a practical checklist that specifies the civil engineering trades-related hazards and offers a safety indicator to identify the safety level of a construction…

Abstract

Purpose

This work affords a practical checklist that specifies the civil engineering trades-related hazards and offers a safety indicator to identify the safety level of a construction project concerning the hazards of the civil engineering trades.

Design/methodology/approach

The methodology depends on reviewing the archival works, visiting the construction sites, utilizing the direct observation and preliminary hazard analysis methods and conducting semistructured interviews to pinpoint and validate the checklist of the civil engineering trades-related hazards. Additionally, a questionnaire-based survey with the rank sum weight technique has been employed to assemble and analyze the data required to build the safety indicator.

Findings

Relying upon the used methodology, 70 hazards under the trades of general environment, earth, demolition, excavation, concrete, dewatering, waterproofing insulation and scaffolding have been pinpointed and validated. This is in addition to the safety level indicator of the civil engineering trades-related hazards (SLICETH), which indicates high viability during its validation in five national and international projects.

Originality/value

The value of this work lies in its ability to tackle the gap existing in the safety management knowledge regarding the notion of the hazards of the civil engineering trades and their influences on the safety performance of the construction projects. As a result, it offers a complete knowledge to the academics and the practitioners for confronting the negative impacts of the civil engineering trades-related hazards. Consequently, it helps in enhancing the safety performance level in the sites of the construction projects.

Details

Journal of Advances in Management Research, vol. 18 no. 3
Type: Research Article
ISSN: 0972-7981

Keywords

Article
Publication date: 22 March 2024

Ramgy Pararajasingam, Anuradha Samarajeewa Waidyasekara and Hasith Chathuranga Victar

Construction material management plays a significant role in achieving successful project delivery of a construction project. However, ineffective material management is a…

Abstract

Purpose

Construction material management plays a significant role in achieving successful project delivery of a construction project. However, ineffective material management is a critical issue in the construction industry, especially in developing economies, of which Sri Lanka is not an exception. Therefore, this study aims to focus on exploring the causes of ineffective material management practices in civil engineering construction projects in Sri Lanka and their impact on successful project delivery.

Design/methodology/approach

Furthermore, the literature findings were validated through the preliminary survey. Subsequently, a quantitative research approach was adopted to pursue the research aim. Questionnaire responses were obtained from 215 construction professionals in civil engineering projects who were selected using the judgemental and snowball sampling techniques. Collected data were analysed through Statistical Package for the Social Sciences (SPSS) V26 and Microsoft Excel 2016.

Findings

Moreover, the study revealed that material price fluctuation, shortage of material in the market, delay in material procurement, inadequate planning and delays in material delivery are the most frequent causes of ineffective material management in civil engineering projects. In addition, it was evidenced that most ineffective material management practices cause both time and cost overruns in civil engineering construction projects. Most respondents emphasized inadequate planning, inadequate qualified and experienced staff, lack of supervision and lack of leadership as the causes for both time and cost overruns.

Originality/value

The study was concluded by proposing strategies for effective material management. Education/training/enlightenment of staff in charge of materials management, use of software like Microsoft Project, Primavera and similar software to eliminate manual errors in material management, and providing clear specifications to suppliers were the most agreed strategies for effective material management in civil engineering construction projects.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 11 August 2023

Guus Keusters, Frédérique Batelaan, Froukje SleeswijkVisser, Erik-Jan Houwing and Hans Bakker

The increasing complexity of civil engineering projects necessitates focusing on new competencies of project participants. Based on the research on team performance and design…

1001

Abstract

Purpose

The increasing complexity of civil engineering projects necessitates focusing on new competencies of project participants. Based on the research on team performance and design processes that are more closely linked to the relevance of the project context, it is hypothesised that empathic abilities could play an important role in the performance of civil engineering projects. Therefore, this study aims to investigate whether performance can be improved by focusing on empathic abilities during the integrated design phase.

Design/methodology/approach

Semi-structured in-depth interviews with experts were conducted to explore the relevance of empathic abilities and their interaction with performance in a real-life infrastructure project. The project team’s empathy level was measured by means of a survey using Davis’ Interpersonal Reactivity Index method. Finally, differences between expected and measured levels of empathy were analysed.

Findings

The results provide insights into how empathic abilities interact with performance. The measurement indicates that, on average, professionals in the civil engineering industry score relatively low on empathy. In addition, differences were identified between the expected distribution and the measured empathy levels of the team, implying a potential for improvement, in particular by increasing the empathic abilities of the project management and increasing gender diversity.

Originality/value

To the best of the authors’ knowledge, this study is the first to investigate a relationship between empathy and the performance of civil engineering projects. The results provide initial insights into the empathic ability of civil engineering project teams and the potential of empathy to improve performance. Furthermore, from an empathy perspective, this study advocates increasing the gender diversity of project teams to improve performance.

Details

Journal of Engineering, Design and Technology , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1726-0531

Keywords

Article
Publication date: 6 February 2020

Bart Lenderink, Johannes I.M. Halman, Hans Boes and Hans Voordijk

Stimulating innovation in projects can contribute to achieving policy goals, addressing societal challenges and meeting objectives within programs and projects. Despite their…

Abstract

Purpose

Stimulating innovation in projects can contribute to achieving policy goals, addressing societal challenges and meeting objectives within programs and projects. Despite their potential, innovations are rarely included in tender assignments and evaluated in the award of civil engineering projects. One explanation for this is the perceived difficulty in triggering and objectively assessing innovations in the awarding of projects. The aim of this paper is to develop, implement and evaluated a method to encourage and assess innovations in the awarding of bridge construction projects to address this problem.

Design/methodology/approach

A design science research (DSR) approach is used to develop, implement and evaluate a method to trigger and assess innovations in tenders for bridge projects. DSR approaches are used to develop “well-tested, well-understood and well documented innovative generic designs, dealing with authentic field problems or opportunities” (van Aken et al., 2016).

Findings

The findings show that the application of the developed method in a bridge project led to the inclusion of a broad range of innovations in the tender offers. Despite the broad support for the defined criteria, there were some differences in the way the criteria were interpreted by the public procurement team and by the tenderers. Despite these differences, no legal claims were filed in court.

Practical implications

Further development and wider adoption of the method is likely to have a positive impact on the application of innovations in bridge projects. With some adjustments, the method would also be appropriate for other civil engineering and construction projects.

Originality/value

This paper contributes to the discussion on how the terms innovation and innovativeness can be operationalized and used in the literature and practice. The developed method provides definitions for assessing the degree as well as the level of innovations in tenders for bridge projects. Further, it provides a way to rank innovations and determine the additional value of the offered innovations in terms of a notional reduction in tender price. Finally, it provides insights into how to encourage innovations through public procurement in civil engineering projects.

Details

Construction Innovation , vol. 20 no. 2
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 27 January 2022

Guus Keusters, Hans Bakker and Erik-Jan Houwing

Civil engineering projects around the world have been underperforming for a long time. While the complexity of these projects will continue to increase, there is an urgent need to…

Abstract

Purpose

Civil engineering projects around the world have been underperforming for a long time. While the complexity of these projects will continue to increase, there is an urgent need to perform better. Although the integrated design process is critical for project success, the literature lacks studies describing the link to project performance. Therefore, this study aims to investigate the dominant variables that affect the integrated design process and consequently project performance.

Design/methodology/approach

A multiple case study was conducted to determine the dominant variables that affect the integrated design process and project performance. The research included four projects. Semi-structured interviews were the main source of data.

Findings

The cases indicated that the extent to which an integrated approach is achieved in the design process is essential for project performance. This applies to the integration of stakeholders’ interests as well as the integration of disciplines. Above all, it was concluded that the project team participants’ competencies for integration are a dominant factor for project performance, as the integrated design process has changed from a technical challenge to an integrative one.

Originality/value

This study provides insights into the dominant variable of the integrated design process that affects project performance, which is underexposed in the literature. The study results reveal the importance of competencies related to integration and adoption of the design problem context, which are not yet included in civil engineering design methods. In this respect, empathy is introduced as a new and critical competence for the civil engineering industry, which needs further research.

Details

Journal of Engineering, Design and Technology , vol. 22 no. 2
Type: Research Article
ISSN: 1726-0531

Keywords

Article
Publication date: 14 January 2014

Palaneeswaran Ekambaram, Peter E.D. Love, Mohan M. Kumaraswamy and Thomas S.T. Ng

Rework is an endemic problem in construction projects and has been identified as being a significant factor contributing cost and schedule overruns. Causal ascription is necessary…

1090

Abstract

Purpose

Rework is an endemic problem in construction projects and has been identified as being a significant factor contributing cost and schedule overruns. Causal ascription is necessary to obtain knowledge about the underlying nature of rework so that appropriate prevention mechanisms can be put in place. The paper aims to discuss these issues.

Design/methodology/approach

Using a supervised questionnaire survey and case-study interviews, data from 112 building and engineering projects about the sources and causes of rework in projects were obtained. A multivariate exploration was conducted to examine the underlying relationships between rework variables.

Findings

The analysis revealed that there was a significant difference between rework causes for building and civil engineering projects. The set of associations explored in the analyses will be useful to develop a generic causal model to examine the quantitative impact of rework on project performance so that appropriate prevention strategies can be identified and developed.

Research limitations/implications

The limitations include: small data set (112 projects), which include 75 from building and 37 from civil engineering projects.

Practical implications

Meaningful insights into the rework occurrences in construction projects will pave pathways for rational mitigation and effective management measures.

Originality/value

To date there has been limited empirical research that has sought to determine the causal ascription of rework, particularly in Hong Kong.

Details

Engineering, Construction and Architectural Management, vol. 21 no. 1
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 6 July 2015

Andrew Whyte and James Donaldson

The use of digital-models to communicate civil-engineering design continues to generate debate; this pilot-work reviews technology uptake towards data repurposing and assesses…

Abstract

Purpose

The use of digital-models to communicate civil-engineering design continues to generate debate; this pilot-work reviews technology uptake towards data repurposing and assesses digital (vs traditional) design-preparation timelines and fees for infrastructure. The paper aims to discuss these issues.

Design/methodology/approach

Extending (building-information-modelling) literature, distribution-impact is investigated across: quality-management, technical-applications and contractual-liability. Project case-study scenarios were developed and validated with resultant modelling-application timeline/fees examined, in conjunction with qualitative semi-structured interviews with 11 prominent stakeholder companies.

Findings

Results generated to explore digital-model data-distribution/usage identify: an 8 per cent time/efficiency improvement at the design-phase, and a noteworthy cost-saving of 0.7 per cent overall. Fragmented opinion regarding modelling utilisation exists across supply-chains, with concerns over liability, quality-management and, the lack of Australian-Standard contract-clause(s) dealing directly with digital-model document hierarchy/clarification/reuse.

Research limitations/implications

Representing a small-scale/snapshot industrial-study, findings suggest that (model-distribution) must emphasise checking-procedures within quality-systems and, seek precedence clarification for dimensioned documentation. Similarly, training in specific file-formatting (digital-model-addenda) techniques, CAD-file/hard-copy continuity, and digital-visualisation software, can better regulate model dissemination/reuse. Time/cost savings through digital-model data-distribution in civil-engineering contracts are available to enhance provision of society’s infrastructure.

Originality/value

This work extends knowledge of 3D-model distribution for roads/earthworks/drainage, and presents empirical evidence that (alongside appropriate consideration of general-conditions-of-contract and specific training to address revision-document continuity), industry may achieve tangible benefits from digital-model data as a means to communicate civil-engineering design.

Details

Built Environment Project and Asset Management, vol. 5 no. 3
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 2 January 2018

Chandra Mouli Vemury, Oliver Heidrich, Neil Thorpe and Tracey Crosbie

The purpose of this paper is to present pedagogical approaches developed and implemented to deliver sustainable design education (SDE) to second-year undergraduate students on…

Abstract

Purpose

The purpose of this paper is to present pedagogical approaches developed and implemented to deliver sustainable design education (SDE) to second-year undergraduate students on civil engineering programmes in the (then) School of Civil Engineering and Geosciences at Newcastle University. In doing so, the work presented offers an example of how to help students understand the contested and contingent nature of sustainability.

Design/methodology/approach

The research presented takes an action-based approach to the development of a teaching and assessment model centered on problem- and project-based learning in a real-world context.

Findings

Because of the use of a design brief, which addresses a practical infrastructure problem encountered by regional communities, the academic team were able to make arguments related to the three pillars of sustainability more accessible to the students. This suggests that pedagogical instruments based on problem- and project-based learning strategies are effective in delivering SDE.

Practical implications

The successful delivery of SDE requires commitment from the senior management teams leading individual departments as well as commitments embedded in the high-level strategies of Higher Education institutions. It was also found that some students need extra support from the teaching staff if their engagement through SDE is to be successful. This has practical implications for the amount of contact time built into undergraduate and postgraduate degree programmes.

Originality/value

The teaching and assessment model presented in this paper addresses various substantive and normative issues associated with SDE making it relevant and transferable to courses other than civil engineering.

Details

International Journal of Sustainability in Higher Education, vol. 19 no. 1
Type: Research Article
ISSN: 1467-6370

Keywords

Article
Publication date: 24 August 2012

J. Goggins

The purpose of this paper is to focus on a number of initiatives in civil engineering undergraduate programmes at the National University of Ireland, Galway (NUIG) that allow…

Abstract

Purpose

The purpose of this paper is to focus on a number of initiatives in civil engineering undergraduate programmes at the National University of Ireland, Galway (NUIG) that allow students to complete engineering projects in the community, enabling them to learn by doing.

Design/methodology/approach

A formal commitment to civic engagement was undertaken by the NUIG in 2001 with the establishment of the Community Knowledge Initiative (CKI) to work on mainstreaming civic engagement (service learning) within the curriculum across the institution. Today, the majority of undergraduate and postgraduate degree programmes in the College of Engineering and Informatics at NUIG have embedded service learning into their curriculum. These initiatives allow students to work with and in local communities, international communities and multi‐disciplinary groups as part of their academic courses. The paper investigates and shows that community‐based projects can enhance student learning and engagement in a number of ways. At NUIG, these projects are framed by a research orientation, commitments to civic engagement and building university‐community partnerships, city‐university partnerships and partnerships with other official agencies, so that community users can provide real learning problems and contexts for students and researchers and benefit from the results.

Findings

It was found that the students got a sense of pride and satisfaction out of the knowledge that their work may be helping communities and that learning is not just to get marks to pass the exam! The projects can increase the students’ sense of ownership of their own learning. Learners are more motivated when they can see the usefulness of what they are learning and when they can use that information to do something that has an impact on others.

Research limitations/implications

The work represents work done in one institution affecting a region in a country. This can be extended to include more institutions and other regions. This paper presents evidence from the aforementioned projects that by creating service‐based learning the students’ energy in learning can have a positive impact on the community.

Practical implications

The energy and enthusiasm of learners can be better utilised (and increased) by setting assignments as real community‐based projects.

Originality/value

This lies in the design of projects and assessment involving education providers and public for the benefit of learners and the society at large.