Article
Publication date: 3 April 2024

Deraniyagalage Chanaka Karunarathna, H.A.H.P. Perera, B.A.K.S. Perera and P.A.P.V.D.S. Disaratna

Delays in utility shifting during road construction have broad ramifications. These delays not only lengthen the project's timeline but also raise expenses and cause problems with…

Abstract

Purpose

Delays in utility shifting during road construction have broad ramifications. These delays not only lengthen the project's timeline but also raise expenses and cause problems with resource allocation. Thus, this study investigates the influence of delay in utility shifting for extension of time claims in road construction projects (RCPs) in Sri Lanka.

Design/methodology/approach

The study used a quantitative approach with three rounds of Delphi surveys to gather empirical data. Further, the probability impact assessment was used to carefully analyse the data and appraise the information gathered.

Findings

The findings initially revealed 33 causes of delays in utility shifting for extension of time claims in RCPs in Sri Lanka. Ultimately, 11 severe causes were identified based on their high probability and impact, concluding with 45 strategies that were assigned to overcoming those most severe causes of delay.

Originality/value

This study will contribute to the industry and theory by providing solutions to handle utility-shifting delays with the linkage of preventing time extension claims for RCPs in Sri Lanka. Further, there is a dearth of literature in the research area, both locally and globally. Thus, the findings of this research will provide a benchmark for further detailed studies in other countries as well.

Details

Smart and Sustainable Built Environment, vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 2046-6099

Keywords

Article
Publication date: 13 July 2023

Haitham Alajmani, Salma Ahmed and Sameh Monir El-Sayegh

This paper aims to measure the severity, frequency and importance of the factors causing delays in the United Arab Emirates (UAE) construction industry following the Covid-19…

Abstract

Purpose

This paper aims to measure the severity, frequency and importance of the factors causing delays in the United Arab Emirates (UAE) construction industry following the Covid-19 pandemic onset. The study also measures the likelihood of the effects caused by these delays.

Design/methodology/approach

A mixed approach of both qualitative and quantitative. Literature review was conducted to extract 40 factors of delays and 10 effects of delays. A survey was then administered to construction professionals in the UAE to collect the perceptions on the severity and frequency of factors of the causes of delays using a Likert Scale of 1–5 where 1 represented very low and 5 represented very high. Similarly, the respondents were also asked to rate the likelihood of the occurrence of the effects of the delays based on a Likert scale of 1–5 as well. Furthermore, Spearman’s rank correlation was also conducted to compute the level of agreement between the different parties; owner, consultants and contractors.

Findings

The results revealed that the top five factors of delays include: award the project for the lowest bidder, delay in progress payment, change orders by the owner, poor subcontractor performance and inadequate planning and scheduling by the contractor. The findings of this study emphasize the financial challenges and economic crisis brought upon the construction industry due to the pandemic. Furthermore, the pandemic also shifted the perceptions of construction professionals, who are now more aware of the delays caused by awarding the project to the lowest bidder who would not have the required qualifications to conduct efficient planning and scheduling that are relevant in the case of extraordinary events such as Covid-19. Moreover, a high level of agreement between the consultants and contractors was observed, with a Spearman’s rank correlation of 0.804. Additionally, the most likely effects of delays concluded from this study were time overrun/extension and poor quality of work.

Originality/value

Literature review is very rich in the field of construction projects delays. However, there is very limited research on the impact of Covid-19 in the context of construction projects delays, and insights from construction professionals regarding this matter are particularly lacking in literature. Therefore, this paper bridges the gap in literature by providing perceptions of construction professionals on the impact of Covid-19 on the factors causing delays in the UAE construction industry. The findings of this research are expected to be an invaluable resource for future to help the construction industry heal faster when encountering similar epidemics or extraordinary events.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 21 November 2022

Babar Ali, Ajibade A. Aibinu and Vidal Paton-Cole

Delay and disruption claims involve a complex process that often result in disputes, unnecessary expenses and time loss on construction projects. This study aims to review and…

Abstract

Purpose

Delay and disruption claims involve a complex process that often result in disputes, unnecessary expenses and time loss on construction projects. This study aims to review and synthesize the contributions of previous research undertaken in this area and propose future directions for improving the process of delay and disruption claims.

Design/methodology/approach

This study adopted a holistic systematic review of literature following Preferred Reporting Items for Systematic Reviews and Meta-Analysis guidelines. A total of 230 articles were shortlisted related to delay and disruption claims in construction using Scopus and Web of Science databases.

Findings

Six research themes were identified and critically reviewed including delay analysis, disruption analysis, claim management, contract administration, dispute resolution and delay and disruption information and records. The systematic review showed that there is a dearth of research on managing the wide-ranging information required for delay and disruption claims, ensuring the transparency and uniformity in delay and disruption claims’ information and adopting an end-user’s centred research approach for resolving the problems in the process of delay and disruption claims.

Practical implications

Complexities in delay and disruption claims are real-world problems faced by industry practitioners. The findings will help the research community and industry practitioners to prioritize their energies toward information management of delay and disruption claims.

Originality/value

This study contributes to the body of knowledge in delay and disruption claims by identifying the need for conducting more research on its information requirements and management. Subsequently, it provides an insight on the use of modern technologies such as drones, building information modeling, radio frequency identifiers, blockchain, Bigdata and machine learning, as tools for more structured and efficient attainment of required information in a transparent and consistent manner. It also recommends greater use of design science research approach for delay and disruption claims. This will help to ensure delay and disruption claims are the least complex and less dispute-prone process.

Details

Construction Innovation , vol. 24 no. 3
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 14 February 2024

Tiep Nguyen, Nicholas Chileshe, Duc Ty Ho, Viet Thanh Nguyen and Quang Phu Tran

Urban rail projects are typically large-scale transport infrastructure projects (megaprojects) which have many potential risks that can influence the strategic goals of owners…

Abstract

Purpose

Urban rail projects are typically large-scale transport infrastructure projects (megaprojects) which have many potential risks that can influence the strategic goals of owners. However, there is a paucity of studies which explore the impact of risks on both “urban rail” project time and cost together considering quantitative assessments. Therefore, this paper focuses on investigating critical risks and quantifying such risk impacts on urban railway project schedule and cost in practice.

Design/methodology/approach

A combination of qualitative and quantitative research methods comprising semi-interviews with five experts and a questionnaire survey of 132 professional respondents is used. The data were modeled using Monte Carlo Simulation to predict the probability of project schedule and cost.

Findings

The results show that 30 risk variables are categorized into seven main groups which have significant impacts on both project time and cost. Outstanding five risk variables were highlighted as follows: (1) project site clearance and land compensation; (2) design changes; (3) physical project resources; (4) contractors’ competencies and (5) project finance. Such findings were supported by Monte Carlo simulation which predicted in the worst case that the project may suffer 11.03 months’ delays and have cost overrun with a contingency of US$287.68 million.

Originality/value

This study expands our knowledge about time and cost contingency of urban metro railway implementation across developing economies and particularly within the context of Vietnam. Policymakers will not only gain an understanding about risk structure but will also recognize the significant impacts of critical risk through risk impact modeling and simulation. Such an approach provides insights into risk treatment priorities for planners so that they can proactively establish suitable strategies for risk mitigation in practice.

Details

Built Environment Project and Asset Management, vol. 14 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 13 July 2023

Adekunle Sabitu Oyegoke, Ben Williams Fisher, Saheed Ajayi, Temitope Seun Omotayo and Duga Ewuga

Supply chain disruptions have a significant impact on overall project delivery. This study aims to identify the supply chain disruptive factors and develop a framework to mitigate…

Abstract

Purpose

Supply chain disruptions have a significant impact on overall project delivery. This study aims to identify the supply chain disruptive factors and develop a framework to mitigate the disruptive effects on the supply chain. Covid-19 and Brexit disruption and their longevity effects in the short, medium and long term on the supply chain are relied upon to develop the framework.

Design/methodology/approach

The study adopted a mixed-method approach with a sequential explanatory design. The main disruptive factors were identified through a literature review, and key factors were selected through a focus group exercise. A questionnaire survey was carried out to sample opinions from the practitioners; 41 questionnaires were received and analysed using the relative importance index (RII) method for ranking the factors and percentage frequency distribution to determine the longevity effects. Five follow-up semi-structured interviews were conducted over the telephone and later transcribed.

Findings

The results of Covid-19 disruption indicate that material cost increase ranked first (RII: 0.863), logistics cost increase and supply chain interaction ranked second and third, respectively. They have long-term, medium-term and short-term longevity effects, respectively. The lowest-rated factors were communication (RII: 0.561), staff shortages (RII: 0.629) and impact on relationships (RII: 0.639). The three most ranked Brexit disruptive factors are supply chain interaction (RII: 0.775), material cost increase (RII: 0.766) and logistic and haulage delay (RII: 0.717). The first two factors have long-term effects, and the logistics and haulage delays have a medium-term impact. The mitigating solutions suggested in the framework are collaborative working, stronger resilience to external forces and better transparency and communication that will lead to good relationships among the supply chain members.

Research limitations/implications

The scope of the study was limited to the UK construction industry; however, the pandemic effect on supply chain can serve as critical learning curve in other developed and developing countries.

Practical implications

The study will help the government and construction firms to understand the focal areas of importance in solving the supply chain disruption problems based on the effects of Brexit and Covid-19. The research would be useful in ensuring the proactive involvement of the government and contracting firms in their preparedness for similar events in the future. The results could be interpreted for critical learning in other developed/developing countries.

Originality/value

Identifying and ranking the supply chain disruptive factors affecting the small‐ and medium‐sized enterprises (SMEs) in the UK construction industry has been the focal point of this study. The study also proposes a simple but effective framework comprising the highly ranked factors, their longevity effects and mitigating measures. This will help the SMEs manage future/similar external events affecting the supply chain.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 29 December 2023

Dara Sruthilaya, Aneetha Vilventhan and P.R.C. Gopal

The purpose of this paper is to identify and analyze the interdependence of project complexity factors (PCFs) in metro rail projects using the Decision-Making Trial and Evaluation…

Abstract

Purpose

The purpose of this paper is to identify and analyze the interdependence of project complexity factors (PCFs) in metro rail projects using the Decision-Making Trial and Evaluation Laboratory (DEMATEL). The study provides qualitative and quantitative analysis of project complexities factors and their relationships. The results of the study facilitate effective project planning, proactive risk management and informed decision-making by stakeholders.

Design/methodology/approach

This study employs a case-based method for identifying PCFs and a DEMATEL method for analyzing the interdependence of complexity factors in metro rail projects. Initially, PCFs were identified through an extensive literature review. To validate and refine these factors, semi-structured interviews were conducted with thirty experienced professionals, each having 5–20 years of experience in roles such as project management, engineering, and planning. Further, elevated and underground metro rail projects were purposefully selected as cases, for identifying the similarities and differences in PCFs. A questionnaire survey was conducted with various technical experts in metro rail projects. These experts rated the impact of PCFs on a five-point Likert scale, for the evaluation of the interdependence of PCFs. The DEMATEL technique was used to analyze the interdependencies of the PCFs.

Findings

Metro rail projects are influenced by project complexity, which significantly impacts their performance. The analysis reveals that “design problems with existing structures,” “change in design or construction” and “land acquisition” are the key factors contributing to project complexity.

Originality/value

The study of project complexity in metro rail projects is limited because most of the studies have studies on examining complexity in mega projects. The existing literature lacks adequate attention in identifying project complexity and its effects on metro rail project performance. This research aims to bridge this gap by examining project complexity and interdependencies in metro rail projects.

Details

Built Environment Project and Asset Management, vol. 14 no. 2
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 18 September 2023

Mohammad Mayouf and Ciaran Gilligan

In construction projects, underpayments can be recognised as one of the significant drawbacks that impact the success of a project. Research into underpayments is considered…

Abstract

Purpose

In construction projects, underpayments can be recognised as one of the significant drawbacks that impact the success of a project. Research into underpayments is considered ambiguous and provides a limited reflection of the issue, which makes it complicated to trace how it originates in the first place. This study aims to examine the causes that lead to underpayments and develop a holistic synthesis of underpayments for subcontractors in the lifecycle of a construction project.

Design/methodology/approach

An open-ended and closed-ended questionnaire was used to collect the data using purposeful sampling with 28 construction stakeholders who ranged from main contractors, subcontractors and others (Small medium enterprises SMEs, Consultancies, Clients etc.). Data collected was analysed to trace drivers and the impact of underpayment and suggested mitigation strategies to be identified whilst viewing the perspectives of a main contractor and subcontractor.

Findings

The findings show that the most prominent driver for underpayments is variation disputes followed by cash flow. The research also suggests mitigation strategies such as collaborative working, more robust budget control and early identification of risks as potential remedies to overcome the underpayment issue. The research concludes with a framework that elicits the complexity underlying underpayments for subcontractors in construction projects.

Originality/value

The research evolves the understanding that underpayment is a complex phenomenon, relying heavily on the data/information exchange mechanism between the main contractor and subcontractors. This research provokes the need to understand underpayment further so it can be mitigated.

Details

Journal of Financial Management of Property and Construction , vol. 29 no. 1
Type: Research Article
ISSN: 1366-4387

Keywords

Article
Publication date: 25 March 2024

Francis Nuako, Frank Ato Ghansah and Thomas Adusei

It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been…

Abstract

Purpose

It is widely accepted that one criterion for determining if a construction project is successful is whether it is completed within the expected budget. There have been advancements in the management of building projects throughout time but cost overruns remain a key concern in the construction sector internationally, particularly in emerging economies such as Ghana. This study aims to answer the question, “What are the critical success factors (CSFs) that can assist reduce cost overruns in public sector infrastructure projects in the Ghanaian construction industry?”

Design/methodology/approach

This study used a quantitative survey method. The questionnaire was pre-tested by interviewing 15 contractors to ascertain the validity of the content. Factor analysis and multiple regression were adopted to analyze the data.

Findings

This study discovered that the critical factors that can reduce cost overruns in construction projects in Ghana are directly linked to five themes: early contractor involvement in the project planning stage, adequate funding, good project team relations, competent managers/supervisors and project participant incentives/bonuses. This study identifies indestructible, empirically measurable important success criteria for reducing cost overruns in public building projects in Ghana.

Practical implications

When well thought through from the project initiation stage to completion, these critical successes can also be used to deal with damaging economic effects such as allocative inefficiency of scarce resources, further delays, contractual disputes, claims and litigation, project failure and total abandonment.

Originality/value

The uniqueness of this research resides in the fact that it is, to the best of the authors’ knowledge, a first-of-its-kind investigation of the CSFs for reducing cost overruns in public building projects in developing countries.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Open Access
Article
Publication date: 10 April 2023

An Thi Binh Duong, Tho Pham, Huy Truong Quang, Thinh Gia Hoang, Scott McDonald, Thu-Hang Hoang and Hai Thanh Pham

The present study is performed to identify the propagation mechanism of the ripple effect as well as examine the simultaneous impact of risks on supply chain (SC) performance.

2704

Abstract

Purpose

The present study is performed to identify the propagation mechanism of the ripple effect as well as examine the simultaneous impact of risks on supply chain (SC) performance.

Design/methodology/approach

A theoretical framework with many hypotheses regarding the relationships between SC risk types and performance is established. The data are collected from a large-scale survey supported by a project of the Japanese government to promote sustainable socioeconomic development for the Association of Southeast Asian Nations (ASEAN) region, with the participation of 207 firms. Structural equation modeling (SEM) is used to test the hypotheses of the theoretical framework.

Findings

It is indicated that human-made risk causes operational risk, while natural risk causes both supply risk and operational risk. Furthermore, the impacts of human-made risk and natural risk on performance are amplified through operational risk.

Research limitations/implications

This study is one of the first attempts that identifies the propagation mechanism of the ripple effect and examines the simultaneous impact of risks on performance in construction SCs.

Originality/value

Although many studies on risk management in construction SCs have been carried out, they mainly focus on risk identification or quantification of risk impact. It is observed that research on the ripple effect of disruptions has been very scarce.

Details

Engineering, Construction and Architectural Management, vol. 31 no. 13
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 4 April 2024

Richard Kadan, Temitope Seun Omotayo, Prince Boateng, Gabriel Nani and Mark Wilson

This study aimed to address a gap in subcontractor management by focusing on previously unexplored complexities surrounding subcontractor management in developing countries. While…

Abstract

Purpose

This study aimed to address a gap in subcontractor management by focusing on previously unexplored complexities surrounding subcontractor management in developing countries. While past studies concentrated on selection and relationships, this study delved into how effective subcontractor management impacts project success.

Design/methodology/approach

This study used the Bayesian Network analysis approach, through a meticulously developed questionnaire survey refined through a piloting stage involving experienced industry professionals. The survey was ultimately distributed among participants based in Accra, Ghana, resulting in a response rate of approximately 63%.

Findings

The research identified diverse components contributing to subcontractor disruptions, highlighted the necessity of a clear regulatory framework, emphasized the impact of financial and leadership assessments on performance, and underscored the crucial role of main contractors in Integrated Project and Labour Cost Management with Subcontractor Oversight and Coordination.

Originality/value

Previous studies have not considered the challenges subcontractors face in projects. This investigation bridges this gap from multiple perspectives, using Bayesian network analysis to enhance subcontractor management, thereby contributing to the successful completion of construction projects.

Details

Journal of Financial Management of Property and Construction , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1366-4387

Keywords