1 – 2 of 2Cong Wang, Henry Liu, Michael C.P. Sing and Jin Wu
Pre-construction of a project comprises stages that are pivotal for the procurement performance. It is defined as the duration from the project's initiation to construction…
Abstract
Purpose
Pre-construction of a project comprises stages that are pivotal for the procurement performance. It is defined as the duration from the project's initiation to construction. However, Private Public Partnerships (PPPs) have been subjected to a long pre-construction, thereby leading to an inefficient development process. Therefore, the purpose of this paper is to pay attention to the influencing factors elongating the pre-construction duration.
Design/methodology/approach
Based on data of 5,677 PPP projects between 2009 and 2021 in China, the authors adopt the Accelerated Failure Time (AFT) model in duration analysis to empirically analyze the following underlying dynamics determining the duration of PPP pre-construction stages: (1) policy uncertainty; (2) corruption; and (3) procurement method selection. To observe the influencing paths more specifically, the authors divided the pre-construction duration into the pre-tendering period and tendering period and regressed them separately.
Findings
The results indicate that the pre-construction duration is significantly prolonged with increased policy uncertainty and corruption degree as well as the use of tendering methods. Meanwhile, the above factors have a greater impact on the pre-tendering period than the tendering period.
Originality/value
The contribution of this study is twofold: (1) theoretically, this paper provides new evidence on the impact of PPP policy uncertainty, corruption and procurement method selection on the pre-construction duration. It complements empirical studies on the factors elongating the time efficiency of PPPs projects. (2) In practice, it provides a specific path for the government to improve the time efficiency of PPPs.
Details
Keywords
Simona Andreea Apostu and Bulent Akkaya
The migration of physicians is a global interest, causing imbalances between developed and developing countries. Romania is one of Europe's major providers of physicians, not…
Abstract
Purpose
The migration of physicians is a global interest, causing imbalances between developed and developing countries. Romania is one of Europe's major providers of physicians, not because there is a surplus, but because physicians are drawn to places with better living and working conditions. Medicine in Romania is increasingly highly advanced, and Romanian physicians are well appreciated all over the world. Despite being one of the countries with the most medical graduates in the world, Romania is suffering a doctor exodus. After joining the EU, the problem of physician migration became widespread, resulting in a deficient and inefficient healthcare system. Therefore, the purpose of this study is to estimate the losses registered by Romania because of physicians' decision to migrate.
Design/methodology/approach
These losses were calculated in two ways: utilizing the statistical life value and the amount of money invested in training a medical graduate.
Findings
According to the findings, the losses in 2018 were 104.16 million euros, approximately 0.12% of GDP.
Originality/value
The originality of this paper consists in data, being provided by the College of Physicians from Romania and the method used, this study being the only one that estimates the cost of Romanian physicians' migration. The paper adds to existing knowledge an empirical results regarding quantifying the value reflecting the departure of physicians, using value of statistical life and the amount of money invested in preparing a medical graduate.
Details