1 – 10 of over 1000The purpose of this paper is to timely control of a construction collapse accident effectively during its development process by constructing a stage model and then aligning IT…
Abstract
Purpose
The purpose of this paper is to timely control of a construction collapse accident effectively during its development process by constructing a stage model and then aligning IT with each stage to help provide the information for decision making.
Design/methodology/approach
Through comprehensive literature review, this paper first identifies the various IT applications in on-site construction monitoring and analyzes the existed disaster/crisis stage models, also the stage models are compared with the causation models to illustrate the strengths. Then, a three-step methodology was conducted to develop and apply the conceptual framework, including the construction of the four-stage model; the establishment of the conceptual framework of information technology (IT) support for management of construction accidents (ITSMCA); and a building collapse accident used to illustrate the proposed framework.
Findings
The accident is divided into four stages, which are incubation stage, outbreak stage, spreading stage and final stage. The real-time staged information to support decision making, such as the contributing factors of on-site workers, materials, equipment and workplace, can be provided by emerging IT. Therefore, IT is aligned with the variations of contributing factors’ attributes in the four stages and ITSMCA is constructed to help accidents management.
Research limitations/implications
The focus of the framework presented in this paper is that the stage model is effective for it catches the variations of the attributes whose values can be provided by IT rather than research on the practical application of the IT system. The construction and application of the IT system will be the research focus in the future.
Originality/value
This paper presents a stage model of a building collapse accident and gives a comprehensive conceptual framework of ITSMCA, which align the IT with different stages of the collapse accident. The ITSMCA proposes a feasible ideology and practical method for real-time management of the collapse accident during the process.
Details
Keywords
Andrew Ebekozien, Wellington Didibhuku Thwala, Clinton Ohis Aigbavboa and Mohamad Shaharudin Samsurijan
Studies showed that construction digitalisation could prevent or mitigate accidents rate on sites. Digitalisation applications may prevent or mitigate building project collapse…
Abstract
Purpose
Studies showed that construction digitalisation could prevent or mitigate accidents rate on sites. Digitalisation applications may prevent or mitigate building project collapse (BPC) but with some encumbrances, especially in developing countries. There is a paucity of research on digital technologies application to prevent or mitigate BPC in Nigeria. Thus, the research aims to explore the perceived barriers that may hinder digital technologies from preventing or mitigating building collapse and recommend measures to improve technology applications during development.
Design/methodology/approach
The study is exploratory because of the unexplored approach. The researchers collected data from knowledgeable participants in digitalisation and building collapse in Nigeria. The research employed a phenomenology approach and analysed collected data via a thematic approach. The study achieved saturation at the 29th interviewee.
Findings
Findings show that lax construction digitalisation implementation, absence of regulatory framework, lax policy, unsafe fieldworkers' behaviours, absence of basic infrastructure, government attitude, hesitation to implement and high technology budget, especially in developing countries, are threats to curbing building collapse menace via digitalisation. The study identified technologies relevant to preventing or mitigating building collapse. Also, it proffered measures to prevent or mitigate building collapse via improved digital technology applications during development.
Originality/value
This research contributes to the construction digitalisation literature, especially in developing countries, and investigates the perceived barriers that may hinder digital technologies usage in preventing or mitigating building collapse in Nigeria.
Details
Keywords
Andrew Ebekozien, Clinton Aigbavboa and Mohamad Shaharudin Samsurijan
Housing provision and the neighbourhood's safety are significant social sustainability concerns. If structural issues are not well checked, housing provision and the…
Abstract
Purpose
Housing provision and the neighbourhood's safety are significant social sustainability concerns. If structural issues are not well checked, housing provision and the neighbourhood's safety may become threatened, especially in Lagos State, Nigeria. Thus, this study aims to investigate the perceived root cause of collapsed buildings at the construction stage using two case studies, its effect on social sustainability aspects and suggested measures to mitigate future happening and enhance achieving social sustainability aspects goals.
Design/methodology/approach
The researchers collected data from Nigeria's built environment experts and eyewitnesses/employees of selected cases of collapsed buildings. The study adopted a phenomenology type of qualitative research design and analysed collated data via thematic analysis and achieved saturation. The analysed data created three themes.
Findings
Results reveal that inadequate heavy equipment and personnel incapacitated relevant government agencies are responsible for handling emergency and rescue during building projects collapse. Preliminary findings show developers' greed and systematic failures as the root cause of Nigeria's building project collapse (BPC). It categorised the root causes into three groups (developer's related-cause, design team related-cause and government entities related-cause). The study suggested measures to mitigate future happening. The emerged measures were grouped into a penalty, regulatory, byelaw act, technical and safety measures.
Originality/value
This study contributes to curbing the threat to social sustainability of housing provision in cities. It reveals the underlying perceived root cause of collapsed buildings in Nigeria's building industry. Also, it suggested feasible measures to mitigate BPC. These measures may be modified and adopted by other developing countries facing similar challenges.
Details
Keywords
In order to succeed in an action under the Equal Pay Act 1970, should the woman and the man be employed by the same employer on like work at the same time or would the woman still…
Abstract
In order to succeed in an action under the Equal Pay Act 1970, should the woman and the man be employed by the same employer on like work at the same time or would the woman still be covered by the Act if she were employed on like work in succession to the man? This is the question which had to be solved in Macarthys Ltd v. Smith. Unfortunately it was not. Their Lordships interpreted the relevant section in different ways and since Article 119 of the Treaty of Rome was also subject to different interpretations, the case has been referred to the European Court of Justice.
Ahmed Yousry Akal and Amr Metwally El-Kholy
This work affords a practical checklist that specifies the civil engineering trades-related hazards and offers a safety indicator to identify the safety level of a construction…
Abstract
Purpose
This work affords a practical checklist that specifies the civil engineering trades-related hazards and offers a safety indicator to identify the safety level of a construction project concerning the hazards of the civil engineering trades.
Design/methodology/approach
The methodology depends on reviewing the archival works, visiting the construction sites, utilizing the direct observation and preliminary hazard analysis methods and conducting semistructured interviews to pinpoint and validate the checklist of the civil engineering trades-related hazards. Additionally, a questionnaire-based survey with the rank sum weight technique has been employed to assemble and analyze the data required to build the safety indicator.
Findings
Relying upon the used methodology, 70 hazards under the trades of general environment, earth, demolition, excavation, concrete, dewatering, waterproofing insulation and scaffolding have been pinpointed and validated. This is in addition to the safety level indicator of the civil engineering trades-related hazards (SLICETH), which indicates high viability during its validation in five national and international projects.
Originality/value
The value of this work lies in its ability to tackle the gap existing in the safety management knowledge regarding the notion of the hazards of the civil engineering trades and their influences on the safety performance of the construction projects. As a result, it offers a complete knowledge to the academics and the practitioners for confronting the negative impacts of the civil engineering trades-related hazards. Consequently, it helps in enhancing the safety performance level in the sites of the construction projects.
Details
Keywords
Franck Taillandier, Cédric Baudrit, Claudio Carvajal, Benjamin Delhomme and Bruno Beullac
Civil engineering structures are regularly confronted with failures that can lead to catastrophic consequences. It is important, after a failure, to be able to identify the origin…
Abstract
Purpose
Civil engineering structures are regularly confronted with failures that can lead to catastrophic consequences. It is important, after a failure, to be able to identify the origin and the sequence of factors that led to it. This failure analysis by experts, called forensic engineering investigation, generally leads to the drafting of an expert report. These reports do not inform on the processes that guided the experts to a conclusion and the uncertainties involved. This paper aims to propose a new methodological approach to formalize the opinions of experts in forensic engineering.
Design/methodology/approach
The research consists in combining abstract argumentation with the theory of imprecise probabilities to take into account epistemic and stochastic uncertainties to support forensic engineering investigation.
Findings
A model and a tool to support forensic analysis are presented. An application on the collapse of the Brumadinho dam highlights the interest of the chosen approach.
Originality/value
This work is the first use of the abstract argument framework in civil engineering, and so in forensic engineering. Furthermore, it provides an innovative model based on imprecise probability for AAF.
Details
Keywords
MEMBERS should note that a steadily increasing number of large companies are taking practical steps to help with the creation and expansion of small firms, especially in areas of…
Abstract
MEMBERS should note that a steadily increasing number of large companies are taking practical steps to help with the creation and expansion of small firms, especially in areas of industrial decline and rising unemployment. Some companies go it alone, others band together to form joint schemes.
Mahsa Pouraliakbarimamaghani, Mohammad Mohammadi and Abolfazl Mirzazadeh
When designing an optimization model for use in a mass casualty event response, it is common to encounter the heavy and considerable demand of injured patients and inadequate…
Abstract
Purpose
When designing an optimization model for use in a mass casualty event response, it is common to encounter the heavy and considerable demand of injured patients and inadequate resources and personnel to provide patients with care. The purpose of this study is to create a model that is more practical in the real world. So the concept of “predicting the resource and personnel shortages” has been used in this research. Their model helps to predict the resource and personnel shortages during a mass casualty event. In this paper, to deal with the shortages, some temporary emergency operation centers near the hospitals have been created, and extra patients have been allocated to the operation center nearest to the hospitals with the purpose of improving the performance of the hospitals, reducing congestion in the hospitals and considering the welfare of the applicants.
Design/methodology/approach
The authors research will focus on where to locate health-care facilities and how to allocate the patients to multiple hospitals to take into view that in some cases of emergency situations, the patients may exceed the resource and personnel capacity of hospitals to provide conventional standards of care.
Findings
In view of the fact that the problem is high degree of complexity, two multi-objective meta-heuristic algorithms, including non-dominated sorting genetic algorithm (NSGA-II) and non-dominated ranking genetic algorithm (NRGA), were proposed to solve the model where their performances were compared in terms of four multi-objective metrics including maximum spread index (MSI), spacing (S), number of Pareto solution (NPS) and CPU run-time values. For comparison purpose, paired t-test was used. The results of 15 numerical examples showed that there is no significant difference based on MSI, S and NPS metrics, and NRGA significantly works better than NSGA-II in terms of CPU time, and the technique for the order of preference by similarity to ideal solution results showed that NRGA is a better procedure than NSGA-II.
Research limitations/implications
The planning horizon and time variable have not been considered in the model, for example, the length of patients’ hospitalization at hospitals.
Practical implications
Presenting an effective strategy to respond to a mass casualty event (natural and man-made) is the main goal of the authors’ research.
Social implications
This paper strategy is used in all of the health-care centers, such as hospitals, clinics and emergency centers when dealing with disasters and encountering with the heavy and considerable demands of injured patients and inadequate resources and personnel to provide patients with care.
Originality/value
This paper attempts to shed light onto the formulation and the solution of a three-objective optimization model. The first part of the objective function attempts to maximize the covered population of injured patients, the second objective minimizes the distance between hospitals and temporary emergency operation centers and the third objective minimizes the distance between the warehouses and temporary centers.
Details
Keywords
Lijia Shao, Shengyu Guo, Yimeng Dong, Hongying Niu and Pan Zhang
The construction collapse is one of the most serious accidents since it has several attributes (e.g. accident type and consequence) and its occurrence involves various kinds of…
Abstract
Purpose
The construction collapse is one of the most serious accidents since it has several attributes (e.g. accident type and consequence) and its occurrence involves various kinds of causal factors (e.g. human factors). The impact of causal factors on construction collapse accidents and the interrelationships among causal factors remain poorly explored. Thus, the purpose of this paper is to use association rule mining (ARM) for cause analysis of construction collapse accidents.
Design/methodology/approach
An accident analytic framework is developed to determine the accident attributes and causal factors, and then ARM is introduced as the method for data mining. The data are from 620 historical accident records on government websites of China from 2010 to 2020. Through the generated association rules, the impact of causal factors and the interrelationships among causal factors are explored.
Findings
Collapse accident is easily caused by human factors, material and machine condition and management factors. Furthermore, the results show a close interrelationship between many causal factors and construction scheme and organization. The earthwork collapse is greatly related to environmental condition and the scaffolding collapse is greatly related to material and machine condition.
Practical implications
This study found relevant knowledge about the key causes for different types of construction collapses. Besides, several suggestions are further provided for construction units to prevent construction collapse accidents.
Originality/value
This study uses data mining methods to extract knowledge about the causes of collapse accidents. The impact of causal factors on various types of construction collapse accidents and the interrelationships among causal factors are explained from historical accident data.