Case study
Publication date: 20 January 2017

Mark Jeffery, Derek Yung and Alex Gershbeyn

The case is based on a real $25 million project at a major U.S.-based computer manufacturer. For confidentiality reasons the company has been disguised as A&D High Tech. The…

Abstract

The case is based on a real $25 million project at a major U.S.-based computer manufacturer. For confidentiality reasons the company has been disguised as A&D High Tech. The Web-based online ordering system project is required by sales and marketing for the fall holiday season. If the project misses this window, the firm will lose substantial market share to competitors. The A&D High Tech case examines how to create and analyze a project plan in Microsoft Project. Specifically, data is given to build the project plan step-by-step and then analyze the plan using the Microsoft project management tool. In order to make the case manageable for students we reduced the size of the project, and corresponding number of resources, to approximately $1 million, but retained all of the features of the original project. The project plan that students construct from the data given in the case is fraught with risks, and students must apply risk management techniques to diagnose the plan. Ultimately, students must answer the management question: Will the project be completed for the holiday shopping season? This case is the first in a series; the second is the case entitled “A&D High Tech (B): Managing Scope Change.” The case can also be taught using other project management software tools, such as Primavera.

The case teaches students how to build a project plan in Microsoft Project (or other project management software tools). More important, the case teaches prospective executives how to analyze a project plan and identify risks of the plan, and define strategies to mitigate these risks. Students learn that in the planning stage of any project the risks are highest, but this is the best opportunity for proactive management intervention.

Details

Kellogg School of Management Cases, vol. no.
Type: Case Study
ISSN: 2474-6568
Published by: Kellogg School of Management

Keywords

Case study
Publication date: 20 January 2017

Mark Jeffery, Derek Yung and Alex Gershbeyn

The case is based on a real $25 million project at a major U.S.-based computer manufacturer. For confidentiality reasons the company has been disguised as A&D High Tech. The…

Abstract

The case is based on a real $25 million project at a major U.S.-based computer manufacturer. For confidentiality reasons the company has been disguised as A&D High Tech. The Web-based online ordering system project is required by sales and marketing for the fall holiday season. If the project misses this window, the firm will lose substantial market share to competitors. Part (B) takes place three months into the original project plan. The project manager has just been fired and the management challenge is to find out what is wrong with the project and recommend fixes. In addition, the scope of the project has changed: the VP of marketing has an additional promotional bundle requirement. A&D High Tech (A) examines how to create and analyze a project plan in Microsoft Project. In order to make the case manageable for students we reduced the size of the project, and corresponding number of resources, to approximately $1 million, but retained all of the features of the original project. Part (B) gives actual work done on each task three months into the project. Students must answer the management questions: Can the project be fixed and completed in time for the holiday season? Can the additional requirements be incorporated, and if so, what is the best approach? In order to answer these questions, earned value data can be extracted from Microsoft Project and analyzed. These data provide important insights into the root cause of problems with the project. The next step is to reduce the scope of the project and reassign resources. However, one must be aware that indiscriminately adding people can slow a project down, not speed it up. Finally, the additional promotional bundle requirement from the VP of marketing provides an important outsourcing management discussion. The case can also be taught using other project management software tools, such as Primavera.

The case teaches students how to analyze a project in trouble using Microsoft Project (or other project management software tool). More important, the case teaches prospective executives how to manage a project in trouble by first accurately diagnosing the problems, then reducing scope where necessary, and finally replanning the project with reallocated resources. In addition, students will learn the tradeoffs of outsourcing to highly specialized professionals vs. average contractors.

Details

Kellogg School of Management Cases, vol. no.
Type: Case Study
ISSN: 2474-6568
Published by: Kellogg School of Management

Keywords

Case study
Publication date: 20 January 2017

Mark Jeffery, Joseph F. Norton, Alex Gershbeyn and Derek Yung

The Ariba Implementation at MED-X case is designed to teach students how to analyze a program that is experiencing problems and recommend solutions. Specifically, the case…

Abstract

The Ariba Implementation at MED-X case is designed to teach students how to analyze a program that is experiencing problems and recommend solutions. Specifically, the case introduces students to earned value analysis and program oversight for an e-procurement technology program. The case centers on MED-X's need to quickly discover why the company's e-procurement implementation project was not going according to plan. Once a cause has been discovered, students will need to make a recommendation to fix the problem. Data for the simplified program, consisting of two concurrent projects, is given to students, who should in turn analyze the project using earned value analysis. The case is an easy introduction to program management and oversight for executives and MBA students, and teaches the essentials of earned value project management.

Students will learn how to control and act in oversight of large complex programs, as well as how to apply earned value metrics to analyze a simplified program consisting of two projects. Analyzing the project enables students to learn the strengths and pitfalls of the earned value approach. From a management decision perspective, the case gives students the tools to succinctly answer the questions: How much will the project cost? How long will it take? What is wrong with the project?

Details

Kellogg School of Management Cases, vol. no.
Type: Case Study
ISSN: 2474-6568
Published by: Kellogg School of Management

Keywords

Case study
Publication date: 20 January 2017

Mark Jeffery, Joseph F. Norton, Derek Yung and Alex Gershbeyn

The case concerns a real $25 million program consisting of nine concurrent projects to deliver and implement a custom-built in-store customer relationship management (CRM) system…

Abstract

The case concerns a real $25 million program consisting of nine concurrent projects to deliver and implement a custom-built in-store customer relationship management (CRM) system and a new point-of-sale system in 400 stores of a national retail chain. The name of the company has been disguised for confidentiality reasons. Once deployed, the new system should give Clothes ‘R’ Us a significant strategic advantage over competitors in the marketplace; it will increase in-store manager productivity, cut costs, and ultimately drive increased sales for the retail chain. The program is in crisis, however, because the product managers have just left to join a competitor. The explicit details of the program are given, including examples of best practice program governance and the real activity network diagram for the program. Detailed Excel spreadsheets are also provided with the actual earned value data for the program. Students analyze the spreadsheets and the data given in the case to diagnose the impact of the most recent risk event and past risk events that occurred in the program. Ultimately students must answer the essential executive questions: What is wrong with the program? How should it be fixed, and what is the impact in time and money to the program? In addition, qualitative warning signs are given throughout the case—these warning signs are red flags to executives for early proactive intervention in troubled projects.

The goal of the case is to teach complex program oversight. Students analyze actual earned value data for a real $25 million program consisting of nine concurrent programs and assess the impact of risk events as they occur in the program. A key takeaway of the case is that relatively simple tools (Excel spreadsheets and time tracking) combined with good project planning can be used to effectively control very complex projects. Students also learn the qualitative warning signs within programs that can serve as early indicators of problems.

Details

Kellogg School of Management Cases, vol. no.
Type: Case Study
ISSN: 2474-6568
Published by: Kellogg School of Management

Keywords

Access

Year

All dates (4)

Content type

1 – 4 of 4