Article
Publication date: 6 January 2021

Cristina Toca Pérez and Dayana Bastos Costa

This paper proposes to apply the lean philosophy principle of minimizing or eliminating non-value adding activities combined with 4D building information modeling (BIM) simulations

Abstract

Purpose

This paper proposes to apply the lean philosophy principle of minimizing or eliminating non-value adding activities combined with 4D building information modeling (BIM) simulations to reduce transportation waste in construction production processes.

Design/methodology/approach

This study adopts design science research (DSR) because of its prescriptive character to produce innovative constructions (artifacts) to solve real-world problems. The artifact proposed is a set of constructs for evaluating the utility of 4D BIM simulations for transportation waste reduction. The authors performed two learning cycles using empirical studies in projects A, B and C. The construction process of cast-in-place (CIP) reinforcement concrete (RC) was selected to demonstrate and evaluate 4D BIM's utility. The empirical studies focused on understanding the current transportation waste, collecting actual performance data during job site visits and demonstrating the usage of 4D BIM.

Findings

In the first cycle, 4D BIM successfully allowed users to understand the CIP-RC process's transportation activities, which were modeled. In the second cycle, 4D BIM enabled better decision-making processes concerning the definitions of strategies for placing reusable formworks for CIP concrete walls by planning transportation activities.

Practical implications

In Cycle 2, three different scenarios were simulated to identify the most suitable formwork assembly planning, and the results were compared to the real situations identified during the job site visits. The scenario chosen demonstrated that the 4D BIM simulation yielded an 18.75% cycle time reduction. In addition, the simulation contributed to a decrease in transportation waste that was previously identified.

Originality/value

The original contribution of this paper is the use of 4D BIM simulation for managing non-value adding activities to reduce transportation waste. The utility of 4D BIM for the reduction of those conflicts considered three constructs: (1) the capacity to improve transportation activity efficiency, (2) the capacity to improve construction production efficiency and (3) the capacity to reduce transportation waste consequences.

Details

Engineering, Construction and Architectural Management, vol. 28 no. 8
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 21 September 2015

Heng Li, Greg Chan, Martin Skitmore and Ting Huang

Traditional construction planning relies upon the critical path method and bar charts. Both of these methods suffer from visualization and timing issues that could be addressed by…

1272

Abstract

Purpose

Traditional construction planning relies upon the critical path method and bar charts. Both of these methods suffer from visualization and timing issues that could be addressed by 4D technology specifically geared to meet the needs of the construction industry. The purpose of this paper is to propose a new construction planning approach based on simulation by using a game engine.

Design/methodology/approach

A 4D automatic simulation tool was developed and a case study was carried out. The proposed tool was used to simulate and optimize the plans for the installation of a temporary platform for piling in a civil construction project in Hong Kong. The tool simulated the result of the construction process with three variables: equipment, site layout and schedule. Through this, the construction team was able to repeatedly simulate a range of options.

Findings

The results indicate that the proposed approach can provide a user-friendly 4D simulation platform for the construction industry. The simulation can also identify the solution being sought by the construction team. The paper also identifies directions for further development of the 4D technology as an aid in construction planning and decision making.

Research limitations/implications

The tests on the tool are limited to a single case study and further research is needed to test the use of game engines for construction planning in different construction projects to verify its effectiveness. Future research could also explore the use of alternative game engines and compare their performance and results.

Originality/value

The authors proposed the use of game engine to simulate the construction process based on resources, working space and construction schedule. The developed tool can be used by end-users without simulation experience.

Details

Engineering, Construction and Architectural Management, vol. 22 no. 5
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 17 November 2023

Jinyu Zhang, Danni Shen, Yuxiang Yu, Defu Bao, Chao Li and Jiapei Qin

This study aims to develop a four-dimensional (4D) textile composite that self-forms upon thermal stimulation while eliminating thermomechanical programming steps by using fused…

Abstract

Purpose

This study aims to develop a four-dimensional (4D) textile composite that self-forms upon thermal stimulation while eliminating thermomechanical programming steps by using fused deposition modeling (FDM) 3D printing technology, and tries to refine the product development path for this composite.

Design/methodology/approach

Polylactic acid (PLA) printing filaments were deposited on prestretched Lycra-knitted fabric using desktop-level FDM 3D printing technology to construct a three-layer structure of thermally responsive 4D textiles. Subsequently, the effects of different PLA thicknesses and Lycra knit fabric relative elongation on the permanent shape of thermally responsive 4D textiles were studied. Finally, a simulation program was written, and a case in this study demonstrates the usage of thermally responsive 4D textiles and the simulation program to design a wrist support product.

Findings

The constructed three-layer structure of PLA and Lycra knitted fabric can self-form under thermal stimulation. The material can also achieve reversible transformation between a permanent shape and multiple temporary shapes. Thinner PLA deposition and higher relative elongation of the Lycra-knitted fabric result in the greater curvature of the permanent shape of the thermally responsive 4D textile. The simulation program accurately predicted the permanent form of multiple basic shapes.

Originality/value

The proposed method enables 4D textiles to directly self-form upon thermal, which helps to improve the manufacturing efficiency of 4D textiles. The thermal responsiveness of the composite also contributes to building an intelligent human–material–environment interaction system.

Details

Rapid Prototyping Journal, vol. 30 no. 2
Type: Research Article
ISSN: 1355-2546

Keywords

Article
Publication date: 30 September 2014

Wei Zhou, David Heesom, Panagiotis Georgakis and Joseph H.M. Tah

The purpose of this paper is to clarify the CSCW in collaborative 4D modelling and its user interface (UI)/interaction designs for prototyping. Four-dimensional (4D) modelling…

Abstract

Purpose

The purpose of this paper is to clarify the CSCW in collaborative 4D modelling and its user interface (UI)/interaction designs for prototyping. Four-dimensional (4D) modelling technology has potentials to integrate geographically dispersed planners to achieve collaborative construction planning. However, applying this technology in teamwork remains a challenge in computer-supported collaborative work (CSCW).

Design/methodology/approach

The research adopted user-centred design (UCD) methodology to investigate a usable 4D collaboration prototype through analysis, design and usability testing. By applying CSCW theories, it first clarified the meaning of 4D CSCW to formulate design propositions as design target. By leveraging UCD theories, subsequently, the first-stage research sought an optimal standalone 4D modelling prototype following a parallel design approach. At the second stage, it further investigated into a collaborative 4D modelling prototype using an iterative design. It adopted collaborative task analysis into the UI/interaction design extension for a collaborative prototype based on results obtained from the first stage. The final usability testing was performed on the collaborative prototype to evaluate the designed CSCW and UI in a controlled geographically dispersed teamwork situation.

Findings

The test results and user feedback verified their usability. It also disclosed design weaknesses in collaborators’ awareness and smooth tasks’ transitions for further enhancement.

Originality/value

The combination of CSCW and UCD theories is practical for designing collaborative 4D modelling. It can also benefit designs for collaborative modelling in other dimensions like cost analysis, sustainable design, facility management, etc. in building information modelling.

Details

Construction Innovation, vol. 14 no. 4
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 9 December 2019

Aneetha Vilventhan and R. Rajadurai

The rapid development of the construction industry requires effective ways to monitor and control the project, and the use of 4D BIM is found to be very efficient. The purpose of…

Abstract

Purpose

The rapid development of the construction industry requires effective ways to monitor and control the project, and the use of 4D BIM is found to be very efficient. The purpose of this paper is to consider development, application and evaluation of 4D Bridge Information Modelling (BrIM) models for an ongoing bridge project.

Design/methodology/approach

An ethnographic action-based case study research methodology is adopted in this study. An ongoing bridge construction project in India is chosen and the 4D BrIM application is evaluated both quantitatively and qualitatively using planned percentage complete (PPC) measurements and semi-structured interviews, respectively.

Findings

The evaluation of the case study shows an increase in PPC values from 26.5 to 56.4 per cent after implementation of 4D BrIM in the project. The application of 4D BrIM in the construction phase benefits the project team in material delivery planning, project monitoring and control, construction schedule improvement, documentation and coordination.

Practical implications

The developed models are practically applied to the ongoing project and the positive benefits are observed. It is shown that 4D BrIM has the potential to improve the construction of bridge projects.

Originality/value

Studies have contributed towards the development and implementation of 3D BrIM models for bridge projects. Limited efforts have been taken to analyse how 4D BrIM models help in the overall management of bridge projects. This study adds value to the existing literature through development, implementation and systematic qualitative and quantitative evaluation of 4D BrIM models.

Details

Built Environment Project and Asset Management, vol. 10 no. 3
Type: Research Article
ISSN: 2044-124X

Keywords

Article
Publication date: 19 October 2020

Aneetha Vilventhan, Sanu Razin and R. Rajadurai

The relocation of existing underground utilities in urban environments is complex because of the existence of multiple utility agencies being responsible for numerous utilities…

Abstract

Purpose

The relocation of existing underground utilities in urban environments is complex because of the existence of multiple utility agencies being responsible for numerous utilities and over constrained space and time to execute maintenance works. Unfamiliar location and insufficient records of maintenance data hamper the flow of work, causing unnecessary delays and conflicts. The aim of the paper is to explore 4 dimensional Building Information Modeling as a smart solution for the management of multiple utility data for a relocation project in an urban setting.

Design/methodology/approach

An empirical case-based research methodology is used to collect data and develop the BIM models. Two ongoing construction projects in an urban city are empirically studied, and 4D BIM models of identified utilities are developed to assist management and relocation of existing utilities.

Findings

The developed BIM models enabled the location of existing sub-surface utilities through 3D visualization and also enabled clash detection. The 4D simulation of BIM model enabled the tracking of actual progress of relocation works and thereby helped in taking necessary actions to minimize forthcoming delays. The evaluation of the developed model showed that the application of 4D BIM improved communication and coordination during utility relocation works.

Practical implications

4D BIM for utility infrastructure provides better management of utility information. They provide utility stakeholders an efficient way to coordinate, manage utility relocation processes through improved visualization and communication with a reduction in delays and conflicts.

Originality/value

Limited efforts were made using 3D BIM for sub-surface utility infrastructure in visualization and management of utility information. Efforts using 4D BIM in coordination and management of utility projects are left unexplored. This study adds value to the current literature through the application of 4D BIM for utility relocation projects.

Article
Publication date: 3 July 2009

Vacharapoom Benjaoran and Sdhabhon Bhokha

The 4D CAD model has been accepted for better conceptualizing and comprehending the sequences and spatial constraints in a construction schedule. The purpose of this paper is to…

1297

Abstract

Purpose

The 4D CAD model has been accepted for better conceptualizing and comprehending the sequences and spatial constraints in a construction schedule. The purpose of this paper is to identify the deficiencies of the visualization of the 4D CAD model and to propose improvements.

Design/methodology/approach

The presentation abilities of the existing 4D CAD model are analyzed and compared with the other conventional methods, namely Gantt chart, network diagram, and the calendar. Four aspects of the visualization are addressed, namely the overview of a schedule, the duration of an activity, the relationship of an activity, and the project progress tracking. The proposed improvements employed different visual properties of 3D CAD objects such as color, line weight, and line type to represent the different activities' performing statuses. A prototype of the 4D CAD model with enhanced visualization was developed on a construction project case.

Findings

The model evaluation showed that this development could enhance the visualization of the 4D CAD model and provide a more informative construction schedule.

Original/value

It is anticipated that the 4D CAD model with these enhancements can substitute for conventional presentation methods of construction schedules.

Details

Engineering, Construction and Architectural Management, vol. 16 no. 4
Type: Research Article
ISSN: 0969-9988

Keywords

Article
Publication date: 24 April 2007

A. Björnfot and R. Jongeling

The purpose of this paper is to suggest the application of the line‐of‐balance (LoB) scheduling technique in combination with a 4D CAD workspace model as a method to improve the…

1585

Abstract

Purpose

The purpose of this paper is to suggest the application of the line‐of‐balance (LoB) scheduling technique in combination with a 4D CAD workspace model as a method to improve the management of the flow of resources through locations in construction projects, defined as work flow. Current scheduling methods fail to consistently manage work flow, which can disrupt the construction process, leading to waste such as conflicts in time and space by construction crews.

Design/methodology/approach

LoB and 4D CAD are applied to a case study of multi‐story timber housing project involving the construction of 95 apartments in five six‐storey buildings. Based on the case study results, the benefits and limitations of the combined use of both methods are discussed.

Findings

The majority of the problems experienced during the actual construction process quickly become evident from an analysis of a relatively simple LoB diagram. Furthermore, the 4D CAD workspace model provides additional insights in the scheduling of construction activities, such as workspace availability, the spatial context of workspaces and partial overlap of workspaces.

Practical implications

Virtual design and construction methods based on principles from lean construction can contribute significantly to the value of the product and the elimination of waste in any construction project.

Originality/value

The paper refers to the guiding principles from lean construction in relation to virtual design and construction methods, such as simulations with 4D CAD. Additional research and studies of practical applications are suggested to facilitate the combination of principles from lean construction with virtual design and construction methods.

Details

Construction Innovation, vol. 7 no. 2
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 23 January 2023

Bruno Falcón Silveira and Dayana Bastos Costa

Several studies have addressed the use of four-dimensional (4D) building information modeling (BIM) for construction management. However, the automation of the processes for…

Abstract

Purpose

Several studies have addressed the use of four-dimensional (4D) building information modeling (BIM) for construction management. However, the automation of the processes for generating 4D models and their integrated use with Location-Based Planning and the Last Planner® System is not well discussed. Therefore, this paper aims to develop a method for automating the generation and use of 4D BIM models integrated with Location-Based Planning and Last Planner® System supporting project control cycles.

Design/methodology/approach

The research strategy adopted was Design Science Research. The automated method for using the 4D models was developed and refined in two residential building projects in Brazil, along with 31 meetings and involving 11 direct users. The assessment of the proposed method focuses on four constructs: the impact of process automation, the impact on the identification and assessment of site progress and the planning process, ease of adoption and utility of the proposed method.

Findings

The results of this paper indicated increased adherence between planned and executed through an automated method for using the 4D models. The established routines enabled automating the link between the planning levels and the three-dimensional (3D) model, providing a more agile and updated data source and achieving 92.8% of user satisfaction regarding the deadline and frequency of delivery of the 4D model reports. Moreover, this study identified the relationships between the processes of the method proposed and Digital Models.

Originality/value

The primary scientific value achieved in this study is creating a method for automating processes and simplifying steps for the generation and use of 4D BIM models in the production planning and control cycles during the construction phase.

Details

Construction Innovation , vol. ahead-of-print no. ahead-of-print
Type: Research Article
ISSN: 1471-4175

Keywords

Article
Publication date: 3 March 2020

Faris Elghaish and Sepehr Abrishami

The integration of building information modelling (BIM) and integrated project delivery (IPD) is highly recommended for better project delivery. Although there is a methodology…

1398

Abstract

Purpose

The integration of building information modelling (BIM) and integrated project delivery (IPD) is highly recommended for better project delivery. Although there is a methodology for this integration, the BIM requires some improvements to foster the adoption of IPD. The purpose of this paper is to present an innovative way to support 4D BIM automation/optimisation within the IPD approach. Similar to structural and architectural design libraries, this research proposes a planning library to enable automating the formulation of schedule, as well as embedding the multi-objective optimisation into the 4D BIM.

Design/methodology/approach

The literature review was used to highlight the existing attempts to support the automation process for 4D BIM and the multi-objective schedule optimisation for construction projects. A case study was done to validate the developed framework and measure its applicability.

Findings

The results show that there is a cost-saving of 22.86 per cent because of using the proposed automated multi-objective optimisation. The case study shows the significance of integrating activity-based costing into 4D BIM to configure the hierarchy level of overhead activities with the IPD approach; therefore, the maximum level of contribution in managing the IPD project is 33.33 per cent by the trade package level and the minimum contribution is around 8.33 per cent by the project level.

Originality/value

This research presents a new philosophy to develop the 4D BIM model – planning and scheduling – a BIM library of the project activities is developed to enable the automation of the creation of the project schedule with respect to the 3D BIM design sequence. The optimisation of the project duration is considered to be automated within the creation process by using the proposed genetic algorithm model.

1 – 10 of 776