Analysing delay causes and effects in Ghanaian state housing construction projects

Charles Teye Amoatey (GIMPA Business School, Ghana Institute of Management and Public Administration, Accra, Ghana)
Yaa Asabea Ameyaw (GIMPA Business School, Ghana Institute of Management and Public Administration, Accra, Ghana)
Ebenezer Adaku (GIMPA Business School, Ghana Institute of Management and Public Administration, Accra, Ghana)
Samuel Famiyeh (GIMPA Business School, Ghana Institute of Management and Public Administration, Accra, Ghana)

International Journal of Managing Projects in Business

ISSN: 1753-8378

Article publication date: 5 January 2015

4285

Abstract

Purpose

The purpose of this paper is to assess the causes and effects of delays in public sector housing projects in Ghana.

Design/methodology/approach

A purposive sampling approach was used in selecting the respondents for the study. These were experts working on various state housing construction projects in Ghana.

Findings

Results from the study showed that the critical factors that contribute to project delays in Ghana are; delay in payment to contractor/supplier, inflation/price fluctuation, price increases in materials, inadequate funds from sponsors/clients, variation orders and poor financial/capital market. The critical effects of delays are cost overrun, time overrun, litigation, lack of continuity by client and arbitration.

Research limitations/implications

This paper is limited to causes and effects of project delays in Ghana based on data collected from only one state institution. Due to geographic constraints the researchers were unable to sample state institutions across Ghana involved in various housing projects.

Practical implications

This paper has documented the critical state housing construction project delay factors in Ghana. The results will help project managers and policymakers appreciate the effects of these delays on project outcomes.

Social implications

Measures aimed at reducing cost of housing projects in Ghana can translate into significant benefits to the poor and support achievement of government objective of providing affordable housing to low income citizens.

Originality/value

This research focussed on the key factors and best practices that lead to the success of state housing projects within the Ghanaian context.

Keywords

Citation

Amoatey, C.T., Ameyaw, Y.A., Adaku, E. and Famiyeh, S. (2015), "Analysing delay causes and effects in Ghanaian state housing construction projects", International Journal of Managing Projects in Business, Vol. 8 No. 1, pp. 198-214. https://doi.org/10.1108/IJMPB-04-2014-0035

Publisher

:

Emerald Group Publishing Limited

Copyright © 2015, Emerald Group Publishing Limited

Related articles