Mayssa Kalach (Department of Civil and Environmental Engineering, American University of Beirut, Beirut, Lebanon)
Mohamed-Asem Abdul-Malak (Department of Civil and Environmental Engineering, American University of Beirut, Beirut, Lebanon)
Issam Srour (Department of Civil and Environmental Engineering, American University of Beirut, Beirut, Lebanon)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 17 July 2020

Issue publication date: 28 April 2021

275

Abstract

Purpose

The purpose of this paper is to analyse the impact of schedule compression under alternative project delivery methods (APDMs) on the design information release (DIR). The objectives are to understand the dynamics and the respective implications of the DIR under alternative design-construction (DC) modes (e.g. fast-track).

Design/methodology/approach

The methodology of work includes: (1) identifying the relevant factors that may impact the release of design deliverables under APDMs, (2) representing the selected APDMs with corresponding DC sequencing modes and (3) conceptualizing the possible alternative dynamics of the released deliverables.

Findings

The findings reveal that in contrast to the traditional one-time packaging of design deliverables, multiple DIR – with less certainty on their scope, timing, frequency and coordination quality – are released under alternative DC modes. This uncertainty mainly emanates from the deduced impact of the identified factors (e.g. DC overlapping intensity and degree of pressure by the builder) on the design deliverables dynamics.

Practical implications

This study can be of benefit to Architecture/Engineering (A/E) professionals as well as to project owners in better planning for their roles and responsibilities under each of the identified modes, as it helps raising their awareness on new issues brought about by APDMs. For instance, the presented analysis indirectly informs designers, design review professionals and project owners about a potentially increased liability exposure emanating from the reduced certainty on the DIR's coordination quality. Moreover, it informs design managers about the need for a design team's re-formation and/or re-structuring (i.e. of the involved staff) in order to accommodate for the hypothesized DIR dynamics.

Originality/value

This work offers a novel study that theorizes the impact of time-reduction-related factors, under alternative DC modes, on the release of design deliverables.

Keywords

Acknowledgements

The authors would like to acknowledge the generous endowed doctoral research funding granted by the Maroun Semaan Faculty of Engineering and Architecture at the American University of Beirut in support of this research. Special gratitude is also extended to the industry practitioners for their valuable input and commitment throughout the validation interviews.

Citation

Kalach, M., Abdul-Malak, M.-A. and Srour, I. (2021), "Design information release under alternative design-construction modes", Engineering, Construction and Architectural Management, Vol. 28 No. 4, pp. 969-993. https://doi.org/10.1108/ECAM-02-2020-0080

Publisher

:

Emerald Publishing Limited

Copyright © 2020, Emerald Publishing Limited

Related articles