The moderating effect of project risk mitigation strategies on the relationship between delay factors and construction project performance

Suhaiza Zailani (Faculty of Business and Accountancy, University of Malaya, Kuala Lumpur, Malaysia)
Hazrina Aziz Md. Ariffin (Faculty of Business and Accountancy, University of Malaya, Kuala Lumpur, Malaysia)
Mohammad Iranmanesh (Malaysia University of Science and Technology, Petaling Jaya, Malaysia)
Soroush Moeinzadeh (School of Management, University Sains Malaysia, Penang, Malaysia)
Masoomeh Iranmanesh (Department of Art and Architecture, Islamic Azad University Kerman Branch, Kerman, Iran)

Journal of Science and Technology Policy Management

ISSN: 2053-4620

Article publication date: 3 October 2016

2004

Abstract

Purpose

This paper aims to explore the relationship between delay factors and construction project performance with respect to project risk mitigation strategies as moderators.

Design/methodology/approach

Random sampling was used to select the sample of the study. Data were gathered through a survey of 204 Malaysian construction companies. The data were analysed using the partial least squares technique.

Findings

The results indicate that environmental, resource and coordination issues negatively affect construction project performance. Project visibility and flexibility can mitigate the negative effects of both resource and coordination issues on project performance. Furthermore, supplier development can mitigate the negative effects of coordination issues.

Practical implications

The findings of the study will be useful for construction firms to complete construction projects timely, within a scheduled budget and with only minor defects if adopted.

Originality/value

This study is among the first to empirically test the moderating role of risk mitigation strategies on the relationship between delay factors and project performance in the construction industry.

Keywords

Citation

Zailani, S., Ariffin, H.A.M., Iranmanesh, M., Moeinzadeh, S. and Iranmanesh, M. (2016), "The moderating effect of project risk mitigation strategies on the relationship between delay factors and construction project performance", Journal of Science and Technology Policy Management, Vol. 7 No. 3, pp. 346-368. https://doi.org/10.1108/JSTPM-12-2015-0041

Publisher

:

Emerald Group Publishing Limited

Copyright © 2016, Emerald Group Publishing Limited

Related articles