Analysis of causes and impact of variation order on educational building projects

Luqman Oyekunle Oyewobi (Quantity Surveying Department, Federal University of Technology, Minna, Nigeria)
Richard Jimoh (Building Department, Federal University of Technology, Minna, Nigeria)
Bashir Olanrewaju Ganiyu (Quantity Surveying Department, Federal University of Technology, Minna, Nigeria)
Abdullateef Adewale Shittu (Quantity Surveying Department, Federal University of Technology, Minna, Nigeria)

Journal of Facilities Management

ISSN: 1472-5967

Publication date: 3 May 2016

Abstract

Purpose

Construction process is complex and traditionally fragmented; thus, it is almost impossible to have a project completed without changes to the original plan or the construction process. The purpose of this study is to identify and examine the causes of variation orders, ascertain their effects and establish the cost and time performance implication as a result of variation orders.

Design/methodology/approach

This study obtained information from 90 construction stakeholders on 30 completed educational building projects to ascertain the causes and effects of variation orders on project delivery using questionnaire survey. In addition to this, a pro forma document was designed to obtain the project characteristics, cost and time data from these 30 completed educational building projects. Factor analysis was used to categorise the causes of variation orders, while severity index was used to examine their effects on project delivery. The hypothesised statement was tested using paired t-statistics to examine whether a statistically significant difference existed between variation orders, cost and time performance of the projects.

Findings

The study identified 13 main factors as causes of variation orders and the results revealed that the most frequent effects of variations were increase in construction costs, time, client dissatisfaction, increase construction project rework and demolition and project abandonment. The results also showed that variation orders had significant effects on both cost and scheduled performance of the educational building projects with average cost and time escalation of 33.95 and 29.45 per cent of the original project cost and time, respectively, for the entire projects studied, while average cost implication of variation orders is 23.79 per cent.

Practical implications

The findings in this study will be of assistance to government agencies and management of public works in higher institutions of learning in managing variations in construction projects. The study will also add to the current literature on the impact of variation orders on educational building projects in developing countries. Finally, it will create the much-needed awareness on the severity and implication of change or variation orders on project delivery.

Originality/value

The study identified and examined the causes of variation orders, ascertained their effects and established the cost and time effects of the causes of variation order on project performance. This will assist project initiators, contractors, consultants and other stakeholders to fully appreciate and understand the significant effects of variation orders on project performance.

Keywords

  • Nigeria
  • Construction industry
  • Projects
  • Change order
  • Educational building
  • Overrun

Citation

Oyewobi, L.O., Jimoh, R., Ganiyu, B.O. and Shittu, A.A. (2016), "Analysis of causes and impact of variation order on educational building projects", Journal of Facilities Management, Vol. 14 No. 2, pp. 139-164. https://doi.org/10.1108/JFM-01-2015-0001

Download as .RIS

Publisher

:

Emerald Group Publishing Limited

Copyright © 2016, Emerald Group Publishing Limited

Please note you do not have access to teaching notes

You may be able to access teaching notes by logging in via Shibboleth, Open Athens or with your Emerald account.
Login
If you think you should have access to this content, click the button to contact our support team.
Contact us

To read the full version of this content please select one of the options below

You may be able to access this content by logging in via Shibboleth, Open Athens or with your Emerald account.
Login
To rent this content from Deepdyve, please click the button.
Rent from Deepdyve
If you think you should have access to this content, click the button to contact our support team.
Contact us
Emerald Publishing
  • Opens in new window
  • Opens in new window
  • Opens in new window
  • Opens in new window
© 2021 Emerald Publishing Limited

Services

  • Authors Opens in new window
  • Editors Opens in new window
  • Librarians Opens in new window
  • Researchers Opens in new window
  • Reviewers Opens in new window

About

  • About Emerald Opens in new window
  • Working for Emerald Opens in new window
  • Contact us Opens in new window
  • Publication sitemap

Policies and information

  • Privacy notice
  • Site policies
  • Modern Slavery Act Opens in new window
  • Chair of Trustees governance statement Opens in new window
  • COVID-19 policy Opens in new window
Manage cookies

We’re listening — tell us what you think

  • Something didn’t work…

    Report bugs here

  • All feedback is valuable

    Please share your general feedback

  • Member of Emerald Engage?

    You can join in the discussion by joining the community or logging in here.
    You can also find out more about Emerald Engage.

Join us on our journey

  • Platform update page

    Visit emeraldpublishing.com/platformupdate to discover the latest news and updates

  • Questions & More Information

    Answers to the most commonly asked questions here