Managing supply chain risks and delays in construction project

Yulia Panova (Department of E-Commerce, Luoyang Normal University, Luoyang, China) (Department of Logistics and Supply Chain Management, National Research University Higher School of Economics, St Petersburg, Russia)
Per Hilletofth (Department of Industrial Engineering and Management, School of Engineering, Jönköping University, Jönköping, Sweden) (Department of Industrial Engineering and Management, University of Gävle, Gävle, Sweden)

Industrial Management & Data Systems

ISSN: 0263-5577

Article publication date: 10 August 2018

Issue publication date: 28 September 2018

3393

Abstract

Purpose

The purpose of this paper is to investigate models and methods for managing supply chain risks and delays in construction projects.

Design/methodology/approach

The study mainly employs quantitative analysis in order to identify disruptions in construction supply chains. It also uses paradigms of simulation modeling, which are suitable for risk assessment and management. Both qualitative and quantitative data were collected through a literature review and details of specific construction projects, respectively. A dynamic modeling method was used, and the model was provided with an event-based simulation. Simulation modeling was used to measure the performance of the system.

Findings

The study shows the benefits of applying the dynamic modeling method to a construction project. Using event-based simulation, it was found that construction delays influence both the magnitude and the probability of disruption. This method contributes to the existing theoretical foundations of risk management practices, since it also considers the time factor. This method supplements the Monte Carlo statistical simulation method, which has no time representation. Using empirical analysis, the study proposes increasing the safety stock of construction materials at the distribution center, so as to mitigate risks in the construction supply chain.

Research limitations/implications

The research considers a single case of a hypothetical construction project. The simulation models represent a simple supply chain with only one supplier. The calculations are based on the current economic scenario, which will of course change over time.

Practical implications

The outcomes of the study show that the introduction of a safety stock of construction materials at the distribution center can prevent supply chain disruption. Since the consideration of risks at all stages of construction supply chain is essential to investors, entrepreneurs and regulatory bodies, the adoption of new approaches for their management during strategic planning of the investment projects is essential.

Originality/value

This dynamic modeling method is used in combination with the Monte Carlo simulation, thus, providing an explicit cause-and-effect dependency over time, as well as a distributed value of outcomes.

Keywords

Citation

Panova, Y. and Hilletofth, P. (2018), "Managing supply chain risks and delays in construction project", Industrial Management & Data Systems, Vol. 118 No. 7, pp. 1413-1431. https://doi.org/10.1108/IMDS-09-2017-0422

Publisher

:

Emerald Publishing Limited

Copyright © 2018, Emerald Publishing Limited