A Big Data and FMEA-based construction quality risk evaluation model considering project schedule for Shanghai apartment projects

Guofeng Ma (Tongji University, Shanghai, China)
Ming Wu (Tongji University, Shanghai, China)

International Journal of Quality & Reliability Management

ISSN: 0265-671X

Article publication date: 16 August 2019

857

Abstract

Purpose

The purpose of this paper is to mine information on the construction process of previous projects to develop a construction plan that meets both quality requirements and schedule constraints.

Design/methodology/approach

This paper uses a failure mode and effect analysis to evaluate the construction quality of 311 apartments in Shanghai. The authors also evaluate construction-scheduling control using the earned value management technique and implement an artificial neural network to correlate the results. The authors then develop a quality risk and schedule correlation model based on Big Data. The model can predict the relationship between the planned schedule and the project quality risk using multiple variables such as the number of layers, the schedule performance index and budget costs.

Findings

The methodology offers an innovative approach for assessment on the relationship between quality risk and project schedule. The authors have also built a multiple regression analysis model for comparative purposes with the model. The results show that the proposed model can better describe the relationship. The model can provide a quantitative quality risk value that changes with the planned schedule, as well as help project managers to understand the relationship between quality risk and project scheduling more accurately.

Research limitations/implications

The research approach only focuses on quality risk under the impact of scheduling. Future efforts might focus on developing a model that connects failure models with project schedules and costs in order to improve the effort of quality management.

Practical implications

The model based on Big Data in this paper is developed using real projects and reflects the relationship between project quality risk and scheduling in real environments. The created application provides support for project managers to develop and adjust quality plans and schedules, thereby reducing deviations in quality and scheduling objectives.

Originality/value

The authors make full use of historical project data from the perspective of both quality and schedule management, and provide a novel method to intelligently and objectively analyze the relationship between quality risk and scheduling.

Keywords

Acknowledgements

This research is supported by the National Natural Science Foundation of China (No. 71671128) and International Cooperation Program for Postgraduate of Tongji University (2019GJXSLT-009).

Citation

Ma, G. and Wu, M. (2020), "A Big Data and FMEA-based construction quality risk evaluation model considering project schedule for Shanghai apartment projects", International Journal of Quality & Reliability Management, Vol. 37 No. 1, pp. 18-33. https://doi.org/10.1108/IJQRM-11-2018-0318

Publisher

:

Emerald Publishing Limited

Copyright © 2019, Emerald Publishing Limited

Related articles