Assessment of early warning signs in hospital projects' front-end phase

Anne Strand Alfredsen Larsen (Aalesund Hospital, Møre and Romsdal Hospital Trust, Aalesund, Norway) (Department of Mechanical and Industrial Engineering, Faculty of Engineering, NTNU, Trondheim, Norway)
Anniken Th Karlsen (Department of ICT and Natural Sciences, Faculty of Information Technology and Electrical Engineering, NTNU, Aalesund, Norway)
Jo-Åsmund Lund (Department of Oncology, Aalesund Hospital, Møre and Romsdal Hospital Trust, Aalesund, Norway) (Department of Health Sciences, Faculty of Medicine and Health Sciences, NTNU, Aalesund, Norway)
Bjørn Sørskot Andersen (Department of Mechanical and Industrial Engineering, Faculty of Engineering, NTNU, Trondheim, Norway)

International Journal of Managing Projects in Business

ISSN: 1753-8378

Article publication date: 17 January 2022

Issue publication date: 18 March 2022

446

Abstract

Purpose

The front-end phase plays an important role in achieving project success, and establishment of performance measurement systems considering project challenges or pitfalls is a way of keeping track of this phase. Early warning signs, a type of proactive performance indicators, may serve as means for improving decision-making and project processes aiming for short- and long-term project success. In this paper, the authors present findings from a study on early warning signs (EWS) in hospital projects' front-end. A preliminary systematisation of identified signs as a contribution to front-end improvement is provided.

Design/methodology/approach

The paper is based on a mixed methods approach, using a sequential, exploratory research design comprising document studies, interviews and a survey.

Findings

The authors identified 62 challenges for hospital projects' front-end performance and further established four categories of EWS as follows: (1) structure and tools, (2) context and frame factors, (3) management and (4) relational factors and properties. This mirrors the presence of hard and soft issues from previous studies. There is need for clarifying terminology and raising consciousness on EWS. Processual approaches to identify EWS are considered more useful than subsequent established indicators.

Originality/value

The findings from this paper provide insight into EWS in hospital projects' front-end phase. This adds to the general understanding of EWS and contributes to more knowledge on the front-end phase in general.

Keywords

Acknowledgements

Funding: This research is partly funded by the Research Council of Norway through the Public sector PhD-scheme, grant no. 272377.

We have no known conflict of interest to disclose.

Citation

Larsen, A.S.A., Karlsen, A.T., Lund, J.-Å. and Andersen, B.S. (2022), "Assessment of early warning signs in hospital projects' front-end phase", International Journal of Managing Projects in Business, Vol. 15 No. 2, pp. 299-323. https://doi.org/10.1108/IJMPB-06-2021-0156