Ramifications of the COVID-19 pandemic on construction operations in developing countries: Malaysian experience

Yi Tong Kum (Department of Surveying, Universiti Tunku Abdul Rahman – Kampus Sungai Long, Kajang, Malaysia)
Jeffrey Boon Hui Yap (Department of Surveying, Universiti Tunku Abdul Rahman – Kampus Sungai Long, Kajang, Malaysia)
Yoke Lian Lew (Department of Surveying, Universiti Tunku Abdul Rahman – Kampus Sungai Long, Kajang, Malaysia)
Wah Peng Lee (Department of Surveying, Universiti Tunku Abdul Rahman – Kampus Sungai Long, Kajang, Malaysia)

Frontiers in Engineering and Built Environment

ISSN: 2634-2499

Article publication date: 28 May 2024

Issue publication date: 17 July 2024

3449

Abstract

Purpose

This study explored the ramifications of COVID-19 on construction operations in Malaysia.

Design/methodology/approach

Following a detailed literature review, 37 ramifications are identified and divided into nine aspects. A self-designed survey is then employed to seek the perceptions of construction practitioners around the Klang Valley region regarding the significance of the ramifications. A total of 203 valid responses are subjected to statistical analyses to prioritise the ramifications.

Findings

All the potential ramifications are perceived to be significant, with the five utmost critical ramifications being rescheduling the project timeline, compliance with government SOP, delay in the handover project, compulsory COVID-19 test for all workers and the extra cost incurred to provide COVID-19 test for workers.

Practical implications

This study highlights the ramifications of COVID-19 on construction operations and deliberately informs construction organizations regarding the shortcomings of recent construction management. Besides, the insights suggested that industry practitioners devise corresponding strategies for project sustainability in future similar crises.

Originality/value

The findings serve as a valuable reference and are benign to industry professionals and researchers from developing nations, especially nations that share similar characteristics to Malaysia.

Keywords

Citation

Kum, Y.T., Yap, J.B.H., Lew, Y.L. and Lee, W.P. (2024), "Ramifications of the COVID-19 pandemic on construction operations in developing countries: Malaysian experience", Frontiers in Engineering and Built Environment, Vol. 4 No. 3, pp. 196-214. https://doi.org/10.1108/FEBE-11-2023-0051

Publisher

:

Emerald Publishing Limited

Copyright © 2024, Yi Tong Kum, Jeffrey Boon Hui Yap, Yoke Lian Lew and Wah Peng Lee

License

Published in Frontiers in Engineering and Built Environment. Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode


Introduction

Construction is among the most significant patrons of the global economy, accounting for considerable total gross domestic production (GDP) in most nations (Alaloul et al., 2021). Therefore, countries, especially those in developing economies, have involved the construction industry in sustainable development. Unfortunately, the alarming health crisis of COVID-19 has set a predicament globally, creating chaos and devastating effects on all economic activities, including the construction sector. According to The World Bank (2020), the global economy has shrunk by about 5.2% due to the COVID-19 crisis, which is reported as the deepest recession since the Second World War. Furthermore, millions of people around the world are unemployed amid the COVID-19 fallout (Gamil and Alhagar, 2020).

Given the diversity of the construction sector, which encompasses constructing new buildings, renovating and maintaining existing buildings and other projects related to civil works such as roads, public utilities, maritime, transportation, energy and waste management facilities, construction is indeed playing a prominent role in revitalising the economy (Husien et al., 2021). Therefore, immediately reforming the industry is necessary, as the industry has suffered from myriad COVID-19 impacts that have interrupted construction operations. Nonetheless, it is suggested that gaining exhaustive insights into the ramifications of COVID-19 is the predominant step in enhancing construction management. Hence, this study aimed to provide an overview of the significant ramifications of COVID-19 on construction operations. Several studies investigated the early impacts of the COVID-19 pandemic on the construction industry, but little attempt has been made in developing countries, which perceive the construction business as one of the significant economic pillars. This leads to a shortage of information regarding the major threats of COVID-19 in developing built environments, thereby causing inappropriate remedies to be taken. Notably, the construction sector contributed approximately 4–10% annually to the GDP in developing nations such as Malaysia, Lebanon, Jordan and Cambodia (Alaloul et al., 2021; Alkilani et al., 2013; Awwad et al., 2016; Durdyev et al., 2017). Moreover, the containment measures of COVID-19 implied higher costs in developing countries, which commonly lack healthcare capacity and fiscal space, higher informality, shallower financial markets and poorer governance (Loayza and Pennings, 2020). In essence, the impacts of COVID-19 will be more severe and long-lasting in the developing world, especially without proper implementation of COVID-19 recovery strategies.

To deepen the knowledge, this paper explored the ramifications of COVID-19 on construction operations in developing countries, providing Malaysia as a base of study. According to the Department of Statistics Malaysia (2023), the GDP of construction has been reduced by 44.3% during the COVID-19 crisis, which is among the hardest-hit sectors in Malaysia. Hence, this study is significant to uncover the significant impacts of COVID-19, which recently undermined construction operations, thereby assisting the construction stakeholders to develop appropriate and effective construction practices for the COVID-19 pandemic and future similar crises.

Literature review

Malaysian construction industry in COVID-19 crisis

COVID-19 is a contagious disease caused by the SARS-CoV-2 virus that originated in China. According to the Centers for Disease Control and Prevention (2022), the virus is highly transmittable through droplets and particles, which causes infected people to experience respiratory illness. Until 2020, this infectious disease had affected more than 200 countries and territories, with a minimum of 600 m confirmed cases and over six million deaths reported (Dao et al., 2020). To curb the contagious disease, WHO (2023) suggested several key preventive measures, such as practicing social distancing, avoiding 3C (crowded, confined and close contact) places, wearing a properly fitted face mask, getting vaccinated, regularly cleaning and sanitising hands and being self-isolated. In Malaysia, a nationwide lockdown is imposed to contain the spread of the COVID-19 disease. This policy has completely restricted the movement of the community, including banning all unessential businesses. However, this decision has caused the construction industry to incur losses of RM18.5 bn in the first three phases of the lockdown (King et al., 2021). Being one of the major productive sectors, it is indispensable to reopen the construction of building-related projects, notwithstanding that the contagious disease has not been eliminated. In this regard, the government suggested incorporating COVID-19 measures into the built environment to curb the transmission of disease whilst sustaining the construction work.

Unlike other sectors, the work from home (WFH) policy is quixotic in construction. Instead, construction work often demands close interactions and consistent supervision on site to ensure the construction operations are aligned with the client’s requirements (time, cost and quality) (Harari, 2020). Despite COVID-19 measures, mass infection is still enduring in the construction industry due to several critical challenges during implementation, such as ignorance and incompliance behaviours (Amoah and Simpeh, 2021). Moreover, Yap et al. (2022) revealed that conventional project delivery, which is labour-intensive, has an immense correlation with a high rate of incidence on site. For instance, the Ministry of Health (MoH) revealed that 11.56% of COVID-19 cases originated from construction sites. According to Malaysiakini (2020), Damanlela Construction Site Cluster is one of the biggest workplace-related clusters with a 56.9% high infectivity rate. Concerning the surge of COVID-19 cases, the Construction Industry Development Board (CIDB) responded that it is due to workers under subcontractors travelling across multiple sites to complete assigned tasks. Furthermore, the high transmission rate among the construction workforce is attributed to cramped worksite and crowded living conditions, which deter social distancing practices along with poor hygiene practices and the living environment (Chan, 2020). Amos et al. (2021) corroborated that the built environment expedited disease transmission, whilst the circumstances in developing countries were more damaging. Consequently, construction projects with severe mass infections will be temporarily suspended to contain the transmission on disease across the industry. As validated by Deep et al. (2022), workers’ H&S is a major constraint of project success. Indeed, over 90% of the construction projects around the globe are disrupted with protracted delays and disorganized cash flow due to the COVID-19 outbreak (Alsharef et al., 2021; Esa et al., 2020; Hatoum et al., 2021; Ogunnusi et al., 2020).

Conspicuously, immediate recovery strategies are demanded to improve construction management for the contagious built environment. According to Sospeter et al. (2022), every post-disaster environment delivers unique intricacies and dynamics that inspire transformed management to be implemented for project sustainability and success. Hence, a comprehensive study of the relevant ramifications of COVID-19 shall be prioritized to devise coping strategies that can effectively rehabilitate the industry. In line with this, a literature review is widely conducted to include various aspects of the ramifications of COVID-19. As summarized in Table 1, a total of 37 ramifications are identified and divided into nine aspects: overarching time, financial, human resources, resource availability and accessibility, health and safety prevention, regulatory compliance, contractual issues and the psychological health of employees.

Ramifications of COVID-19 on construction operations

Generally, the ramifications of COVID-19 vary from contract to contract and nation to nation; however, induced significant effects on construction operations. Time is perceived as one of the most prevalent impacts in most countries, like Malaysia, the USA, India, Kuwait and Nigeria (Gamil and Alhagar, 2020; Hatoum et al., 2021). Esa et al. (2020) from Malaysia, who conducted interview sessions with eight contractors listed on the Construction Industry Development Board (CIDB), asserted that the lockdown policy imposed to contain the spread of COVID-19 unexpectedly caused project delays, late delivery of building materials and rearrangement of the project schedule.

Financial is another noteworthy impact of COVID-19, which gathered considerable attention in the global construction industry. In the USA, Alsharef et al. (2021) revealed that the COVID-19 crisis has induced unappealing financial impacts such as deferred payment due to cash flow problems, suspension of ongoing projects and delay in commencement of projects, the extra cost to secure necessary personal protective equipment (PPE) and an upsurge in material costs. Moreover, Kaklauskas et al. (2021) observed that investment in construction-related projects has been reduced by 13–30% due to the unpredictable context of the pandemic.

Notably, human resources are valuable in the construction industry, given its labour-intensive nature. Nonetheless, Stiles et al. (2021) elucidated that the preventive measures implemented to contain the spread of disease affected the reduction of the workforce, low productivity and restriction of nonessential site visits in the UK construction industry. Indeed, Esa et al. (2020) corroborated that productivity has slid down by approximately 20% during the COVID-19 fallout. Moreover, Ogunnusi et al. (2020) revealed that the UK construction industry is facing a shortage in construction material supply, tools and equipment since the border between Indonesia and China is inaccessible to restrict the spread of COVID-19 disease. Likewise, the labour shortage issue is encountered in Malaysia due to the fact that foreign workers have returned to their respective countries, whilst the government has stipulated a more rigorous ordinance to restrict the entry of foreign workers during the pandemic (Zamani et al., 2021).

To combat the infectious disease, corresponding H&S preventions are alertly introduced as standard operating procedures (SOPs) in most nations, such as distancing practices, one task for one worker policies, site surveillance and providing COVID-19 H&S education to the workers (Iqbal et al., 2021). By conducting quality interviews with 23 construction experts, Umar (2021) discovered that regular health checks, providing screening tests and promoting H&S practices among workers are encouraged in Gulf Cooperation Council (GCC) countries. However, some industry professionals treated regulatory compliance as having a detrimental impact in terms of management and control of labour (King et al., 2021). This may give rise to the unclear SOP guidelines announced by the authority, which often lead to interruptions to construction operations. Given their unexpected nature, most construction professionals in the US construction industry have suffered plenty of significant contractual issues. For instance, issues and interruptions in contractual terms and increases in disputes, litigation and claims due to nonperformance and delay (Alsharef et al., 2021). Industry experts raised a discussion over the legal interpretation of the implications of the COVID-19 outbreak on construction projects (Husien et al., 2021). A notable question emerged: Can the contractor include COVID-19 as a “force majeure”, which represents an unforeseeable event to be exempt from compensation whilst granting the construction projects an extension of time (Biswas et al., 2021; Ogunnusi et al., 2020)? Since none of the construction parties would like to endure the losses resulting from the pandemic, conflict arises when there is a disagreement regarding the claim and interpretation of certain legal terms.

Meanwhile, studies have conceded that the psychological health of employees is another paramount aspect to be concerned about during the COVID-19 pandemic. Findings from Lingard et al. (2021) reported that the construction workforce is suffering mental anguish due to several reasons. Heeding the call of “teleworking”, industry personnel are socially isolated, which causes them to have minimal interaction with family members, friends and colleagues (Hallin, 2020). As such, negative emotions derived from job burnout have no way to be expressed, thus leading to psychological distress. Financial distress has been reported as a critical factor in poor mental health due to the pandemic (Dawel et al., 2020). Construction employees are afraid to be laid off, furloughed or have their salaries cut off, which will cause them to suffer from income loss. Indeed, more than 50% of the construction workforce has experienced elevated mental distress, depression, anxiety and stress from financial concerns due to the deadly disease (Newby et al., 2020). Certainly, construction practitioners with poor psychological health will thus disrupt the overall construction operations.

Despite myriad studies deliberating about the impacts of COVID-19, limited studies have focused on the context of a developing world in which the construction business plays a vital role in national economic growth. In bridging the knowledge gap, this study explored the ramifications of COVID-19 on construction operations, providing Malaysia as the base of the study. The findings are expected to present an overview of the construction issues in recent years, thereby supporting the project team to reform the industry.

Research methodology

The exploratory direction is embraced due to the scarcity of knowledge about the COVID-19 fallout. This study relied on a quantitative approach to uncover the most prominent ramifications of COVID-19 on construction operations. According to Naoum (2019), this technique is well-suited to establish reliable theories from the results. To recognize the prevailing impacts plaguing the building industry, a thorough literature review is initiated to examine a preliminary list. Pertinent studies regarding the construction industry during the COVID-19 outbreak were discovered using relevant keywords to search in research databases such as Google Scholar, Web of Science and Scopus. To capture the perceptions of the targeted respondents on the significance of ramifications, a questionnaire survey is engaged as the research instrument, given its benefit of gathering a satisfactory amount of responses in a limited time (Yap and Lee, 2019). The survey contained two parts. The first part is engaged to gather the background information of the respondents, whilst the second part accesses the viewpoints of respondents on the ramifications of COVID-19. For each ramification, the respondents are asked to rate the significance level based on a five-point Likert scale (with 1 = extremely insignificant, 2 = insignificant, 3 = neutral, 4 = significant and 5 = extremely significant).

Sampling and data collection

To ascertain the comprehensibility and appropriateness of the questionnaire, a pilot survey is first distributed to 30 experienced construction industry practitioners. Without necessary modifications, the questionnaire is further administered to targeted respondents through convenience, snowball and judgemental sampling techniques. Convenience sampling is engaged as the primary technique, which is convenient as it has limited prescribed characteristics (Etikan and Bala, 2017). The data collection process will be immediately suspended once sufficient responses are returned. Snowball sampling is embraced to accelerate the data collection process through a networking approach as well as to avoid missing out on any potential respondents, whilst judgemental sampling is considered to access respondents with the best information on COVID-19, such as the H&S officer (Fellow and Liu, 2015; Kumar, 2011). Moreover, the researchers were able to gather the opinions of the construction personnel in managerial positions who seemed to provide comprehensive data. Notably, the former sampling methods have been widely used for construction engineering and management-related survey research (Yap et al., 2020), whilst the latter technique is suitable for describing the unknown knowledge of a phenomenon, like the COVID-19 crisis (Kumar, 2011). The sampling frame entails industry practitioners in the Klang Valley area, which is the central region with the highest gross output impelled by rapid construction activities in Malaysia (Department of Statistics Malaysia Official Portal, 2015). The targeted respondents encompassed the primary construction stakeholders, including the developer, consultant and contractor, to obtain a balanced view of perceptions. Despite the fact that the sample size was determined to be approximately 385, a total of 625 e-surveys designed by Google From were distributed to ensure sufficient responses were collected. Using the platforms of LinkedIn and email, a total of 203 completed surveys were returned in a period of two and a half months. Overall, the response rate of 32.48% is beyond the common rate of survey (30%) for gaining feedback from construction personnel (Yap et al., 2019). Although it is a self-voluntary participation survey, follow-up reminders are issued to nonrespondents to raise the response rate. It is also worth noting that ethics clearance are obtained from the university to conduct this meaningful survey.

The calculation of sample size is as follow:

Assumption:

P=50%
Z value=1.96(95% confidence level)
E=5%
n=0.5(10.5)1.9620.052
=(0.5)(0.5)(3.8416)0.0025
=384.16385

In the equation, P indicates the characteristics of the targeted respondents in this study and is recommended to be 50% of the population. According to Bartlett et al. (2001), researchers are suggested to engage 50% as the estimated value of P to maximize the variance and allow the largest sample size to be included. From the equation, the Z – value describes the confidence level in the accuracy of the results produced by the survey findings. As for this study, the typical confidence level for management research involved is 95% with a Z-value of 1.96 (Bartlett et al., 2001). Besides, the E value, which revealed the risk level able to be liable, is assumed to be 5%.

Statistical analysis approach

Statistical Package for Social Sciences (SPSS) Version 26 software is used to perform quantitative data analysis. Descriptive statistics for the demographic information of respondents are obtained, whereby the relative ranking of the ramifications is determined based on the mean scores by considering the viewpoints of the respondent groups. Ramifications achieved with a higher mean value will therefore be regarded as more significant. If two or more yields achieve the identical mean value, the yield with a lower SD will be prioritized with a higher ranking (Yap et al., 2020). To further evaluate the collected data, a nonparametric ANOVA test known as Kruskal–Wallis is applied to ascertain if there are any statistically significant differences between the three respondent groups. Variables obtained with a significance value (p-value) above 0.05 denoted that the respondents in all groups shared similar viewpoints on the ramifications, whilst p-values below 0.05 showed significant differences in perceptions among the respondent group (Shafiq and Afzal, 2020). However, the Shapiro–Wilk test is suggested to study the normality of the data, indicating the suitability of the Kruskal–Wallis test (Yap and Sim, 2011).

Analysis and discussion of results

Demographic profile of respondents

Table 2 provided detailed information regarding the background of respondents, broadly including representatives from developers (47), consultants (37) and contractor (119) firms. A majority (60%) had at least ten years of working experience in this sector, whilst at least 44% of the participants held a manager position or above in their respective organizations. In this context, the respondents are considered adequate to make informed judgements (Yap and Cheah, 2020). In addition, over 90% of the respondents are qualified with bachelor’s or higher degrees. Thus highlighting that the skilled professionals are providing valid and noteworthy responses.

Questionnaire reliability

In this study, Cronbach’s alpha coefficient parameter is employed to measure the reliability of the five-point Likert scale used in the survey. As a result, an alpha value of 0.965 is obtained, which represents satisfied internal consistency between the variables, and the measurement scale has attained a good measure of the yields (Deng et al., 2018; Doloi, 2009).

Ranking of ramifications

Table 3 presents the mean, standard deviation and p-value of each variable according to the sample groups (developer, consultant and contractor). The ranking is assigned to each variable in ascending order based on the mean scores. Notably, all the ramifications of COVID-19 have obtained a significant mean value beyond 3.50. “Rescheduling project timeline” obtained the highest mean (4.36), which is therefore regarded as the most significant impact of COVID-19 on construction, whilst “Compliance of government SOP” is in second place with a mean value of 4.35. “Delay in handover project”, which achieved a mean score of 4.34, is ranked as the third most critical ramification of COVID-19 on construction operations. Besides, “Compulsory COVID-19 test for all workers” is rated fourth place among all the ramifications measured (mean = 4.32), whilst “Extra cost in providing COVID-19 test for workers” is ranked fifth with a mean value of 4.28.

Meanwhile, the results of the Shapiro–Wilk test indicate that the data is not normally distributed with a p-value <0.05; therefore, the Kruskal–Wallis ANOVA test is further engaged to study the significance difference in the perceptions of respondent groups. Consequently, the Kruskal–Wallis ANOVA test provided that only the extra cost incurred to provide COVID-19 tests for workers (ranked more important by contractors), providing health and safety education for all workers (ranked more important by contractors) and the additional cost in providing COVID-19 PPE (ranked more by contractors) had statistically significant differences between the three respondent groups (Table 2).

Discussion

The following discussion expounds on the five most critical ramifications of COVID-19 on construction operations. Scheduling is an important factor in determining project success. A good schedule allows a project to run smoothly and optimize the use of construction resources financially and operationally according to predetermined needs (Zakia and Febrianti, 2021). In the case of Malaysia, the government has enforced a national quarantine policy to restrict the movement of citizens in response to the COVID-19 outbreak. However, this policy put the construction businesses at a standstill for at least three months. Therefore, building activities that had been planned earlier are postponed, and the practitioners need to reschedule the project timeline (Gamil and Alhagar, 2020). When budget and time are limited for project completion, the project planner must carefully amend the work breakdown to avoid this inferior situation. Apparently, all unfulfilled construction tasks are being stressed in the remaining days to meet the date of completion as agreed by the parties initially. In line with these reasons, industry personnel claimed that the rearrangement of project schedules is the utmost ramification of the COVID-19 pandemic.

The government has decided to allow the reoperation of construction after the Cabinet realized that less than 40% of the budget allocated for the building sector in 2021 had been exploited to date (New Straits Times, 2021). Conditionally, all construction operations are implied by the strict SOP as specified by the Malaysian Ministry of Health. The enforcement of strict SOP in the construction sector is to ensure site safety, and it will be more practical to impose targeted lockdowns if any construction sites find an increasing number of infection cases. As highlighted by Esa et al. (2020), industry professionals treated this impact of COVID-19 as significant due to the tremendous effects of not adhering to the prescribed SOP. To limit the spread of disease, responsible authorities have conducted random investigations to confirm strict compliance with SOP is being adhered to on construction sites. Failing to comply with the stipulated SOP, the related practitioners will immediately get fined or warned. More imperatively, construction sites with immense disregard for SOP will be ordered to close until further notice. Around July 2021, 188 of the 810 operating jobsites investigated were forced to shut down due to non-compliance with SOP (PropertyGuru, 2021). In this situation, the construction projects will be further delayed, making no profits or more jeopardizing and the contractors will have to make compensation for noncompletion of work.

Before the COVID-19 fallout, a finding mentioned the notorious delay characteristic of the construction industry (Umar, 2021). Undoubtedly, the industry is facing a more advanced challenge of delay, which is aggravated by the pandemic. When projects are delayed, the party can either accelerate the building process or request an extension on time that is beyond the agreed completion date. However, none of these can be exempt from cost implications. Perhaps the additional expenses can be covered by the contingency sum, but most of the contingency allowances are unrealistic, especially when there are a plethora of prohibitive costs associated with COVID-19. Since the pandemic is an unexpected event, there is no extra contingency cost allocated in advance. Notably, whether the responsibilities will be borne by the contractors or equally distributed to all related parties is uncertain in this crisis. Relevant profound effects can be disputes and claims, arbitration and litigation and total abandonment (Alfakhri et al., 2018). Expected disagreement shall result in dispute resolution; in addition, it is not free of charge. Additionally, the construction stakeholders will risk their public image when the project has a delayed handover. Precisely, none of these extended impacts is appealing for industry personnel; therefore, the delay in handover of the project has been rated as one of the top five ramifications of COVID-19.

COVID-19-infected people have different sicknesses. In this regard, even medical experts cannot determine if a person is infected by a contagious disease based on common symptoms such as fever and cough. With an upward trend of COVID-19 cases, the population around the globe has a high dependency on polymerase chain reaction (PCR) tests to help detect if a person has been exposed to the SARS-COV-2 virus before the COVID-19 rapid test kit was introduced. In Malaysia, the COVID-19 test was aimed at controlling the high infectivity rate when the vaccination programme had not been launched. Furthermore, all field workers needed to get screened before the resumption of work to ensure site safety (Esa et al., 2020). The Malaysian construction industry is still very labour-intensive but there are limited slots provided for the health screening test, and the speed of getting results is relatively slow (Star Property, 2020). With these, a massive queue of foreign workers is found at a clinic to take the screening test with no compliance to distancing practice. This may turn into a terrible infection cluster if anyone from the crowd is detected positive for COVID-19. The surge in such high demand for COVID-19 tests was due to practitioners rushing to reshape their construction activities at the same time after a long haul of lockdown. As highlighted by Simpeh and Amoah (2021), screening is the only way to identify COVID-19 disease. Therefore, industry personnel must ensure all workers are screened before resuming building work.

The Ministry of Infrastructure and Port Development (MIDP) urged all industry employers to provide PCR tests for their workers to restrain the spread of disease. However, the cost of screening tests will not be abated by the authorities. Instead, the owners need to bear the cost of hundreds of construction employees in a company that is ill-afforded since the disease has unexpectedly plagued the industry. In this regards, construction practitioners revealed the prohibitive cost of complying with COVID-19 guidelines is unplanned (Simpeh et al., 2021). During the pandemic, the estimated cost per PCR test is between RM 250 and RM350, which requires a minimum of three hours to get the result. Such costs will sum to a considerable amount of high expenses when the employers will have to be liable for all workers whilst facing financial distress from mobilization costs and profit losses since the initiation of the lockdown. In this vein, the construction practitioner will treat these as significant ramifications of COVID-19 in a beleaguered industry.

It is worth mentioning that all variables that are rated more important by contractors have labour-related impacts. As highlighted by Niroshana et al. (2022), managing the workforce is one of the most critical challenges in the COVID-19 era. Given that the contractors have an extensive number of workforces to sort out; it is unsurprising that the aforesaid ramifications, which involved high prohibitive costs, are ranked more significant by the contractor group.

Implications

Practical implications

By presenting an overview of the contemporary construction issues of COVID-19, this study reflected the severity of the COVID-19 crisis in dampening the construction industry. The outcome of the study highlighted that the most significant ramifications are majorly concerned with time, cost, H&S prevention and regulatory compliance. These implied that the construction practitioners would be more attentive in these aspects during unforeseen circumstances, particularly in a future similar crisis. For instance, the discussion suggested that industry practitioners should always reserve extra contingency funds to cover unexpected costs like purchasing COVID-19 PPE to contain the spread of the disease. Due to the extended impact of project delays, a backup schedule shall be prepared in advance to avoid further deferment. Also, there is a need to review the standard form of contract by elaborating on the contractual terms of “force majeure” or adding on extra conditions to outline the responsibilities of parties during unforeseen circumstances. Additionally, the identified ramifications of COVID-19 can guide the construction stakeholders, including the client, suppliers, governments, consultants, contractor, etc. in confronting future similar crises by advancing the project delivery system whilst allocating sufficient resources.

Theoretical implications

This study provides a theoretical base for the significant ramifications of COVID-19 on project delivery, according to the experiences of the primary construction stakeholders. It is noteworthy that the sample size in this study is a paucity of similar studies that touch on the impacts of COVID-19. Moreover, this empirical study concerning developing countries is new to the construction management literature. The findings of this study suggest the most significant issues of COVID-19, which can serve as a guide for future studies intended to propose response strategies for unexpected events in the construction industry. Meanwhile, this paper highlighted that immediate studies are necessary to review the current project delivery system whilst developing a recovery plan to reform the industry from recession.

Conclusion

In recent years, the industry has been distressingly trapped in the COVID-19 crisis. Myriad consequences dreadfully dragged down construction progress, which is inextricably intertwined with the national economy. Hence, it is urgent to propose effective, sustainable and fulfilling responses to alleviate the impact of COVID-19 whilst sustaining construction operations. Nonetheless, it is suggested to well acknowledge the COVID-19 impacts to develop corresponding strategies. Previous studies focused on the early impacts of COVID-19 in the industry, but few have delved into the developing context. In bridging the knowledge gap, this study explored the ramifications of COVID-19 on construction operations in the Malaysian construction industry. A detailed review of the literature determined a list of potential ramifications, consisting of 37 variables, which are then divided into nine aspects. Following this, a questionnaire survey will be constructed and distributed to the construction practitioners to examine the significance of the ramifications of COVID-19. The participants have included 47 developers, 37 consultants and 119 contractors from the Klang Valley region. Prioritised using mean scores, the five most critical ramifications are rescheduling the project timeline, compliance with government SOP, delay in handover of the project, compulsory COVID-19 test for all workers and extra cost incurred to provide COVID-19 tests for workers. Besides, the result of the Kruskal–Wallis test indicated that the respondent groups have different views on several variables, including the extra cost incurred to provide COVID-19 tests for workers provide H&S education for all workers and provide COVID-19 PPE.

Limitations and future studies

A limitation of this study has been discovered to be that the data collection instrument used does not open up gateways to generate further explanations from the participants. Furthermore, the adoption of a five-point Likert scale has lacked reliability and validity, which does not provide more refined responses from the respondents (Dolnicar, 2021). As compared to mixed-method research, a mono-method research design is unable to provide a comprehensive outcome. Therefore, future studies have suggested including qualitative interviews or case studies to extract related information and knowledge from other developing countries in the Asia and Africa regions, which will be useful to corroborate the outcome of this study.

Ramifications of COVID-19

No.RamificationsReferences
Time
T1Delay in handover projectAdhikari and Poudyal (2021), Shibani (2020), Esa et al. (2020), Gamil and Alhagar (2020), Ogunnusi et al. (2020), Alsharef et al. (2021), Umar (2021), Zamani et al. (2021), Ebekozien et al. (2021), Hatoum et al. (2021), Kaushal (2021), Majumder and Biswas (2021), Pamidimukkala and Kermanshachi (2021)
T2Delay in material supplyEsa et al. (2020), Gamil and Alhagar (2020), Alsharef et al. (2021), Biswas et al. (2021), Hatoum et al. (2021), King et al. (2021), Umar (2021), Zamani et al. (2021)
T3Rescheduling project timelineEsa et al. (2020), Gamil and Alhagar (2020), Ebekozien et al. (2021), Hatoum et al. (2021), Kaushal (2021)
T4Delay in inspections and securing permitsAlsharef et al. (2021), Hatoum et al. (2021), Kaushal (2021)
Financial
F1Additional cost in providing personal protective equipment (PPE)Adhikari and Poudyal (2021), Esa et al. (2020), Alsharef et al. (2021), King et al. (2021)
F2Provide COVID-19 test for workersEsa et al. (2020), King et al. (2021), Zamani et al. (2021)
F3Cost in appointing COVID-19 health supervisorEsa et al. (2020)
F4Cost in providing transportation for workersEsa et al. (2020), King et al. (2021)
F5Cash flow problem/late paymentOgunnusi et al. (2020), Osuizugbo (2020), Alsharef et al. (2021), Biswas et al. (2021), Ebekozien et al. (2021), Hatoum et al. (2021), King et al. (2021), Majumder and Biswas (2021), Pamidimukkala and Kermanshachi (2021), Zamani et al. (2021)
F6Increase in material costOsuizugbo (2020), Alsharef et al. (2021), Ebekozien et al. (2021), Hatoum et al. (2021), Majumder and Biswas (2021), Zamani et al. (2021)
F7Suspension of projects/reduced number of planned projectsGamil and Alhagar (2020), Osuizugbo (2020), Alsharef et al. (2021), Ebekozien et al. (2021), Hatoum et al. (2021), Majumder and Biswas (2021), Zamani et al. (2021)
Human resources
H1Reallocation of human resourceEsa et al. (2020), Gamil and Alhagar (2020), Hatoum et al. (2021), Iqbal et al. (2021), Stiles et al. (2021)
H2Low productivityEsa et al. (2020), Ogunnusi et al. (2020), Alsharef et al. (2021), Kaushal (2021), Stiles et al. (2021)
H3Termination of workersEsa et al. (2020), Gamil and Alhagar (2020), Biswas et al. (2021), Ebekozien et al. (2021), Hatoum et al. (2021), Husien et al. (2021), Majumder and Biswas (2021), Umar (2021)
H4Work from home challengesGamil and Alhagar (2020), Alsharef et al. (2021), Lingard et al. (2021), Pamidimukkala and Kermanshachi (2021)
H5Limited access to construction siteIqbal et al. (2021), Stiles et al. (2021)
Resource availability and accessibility
R1Material shortageAdhikari and Poudyal (2021), Ogunnusi et al. (2020), Osuizugbo (2020), Shibani (2020), Esa et al. (2020), Gamil and Alhagar (2020), Alsharef et al. (2021), Umar (2021), Zamani et al. (2021), Biswas et al. (2021), Choi and Staley (2021), Ebekozien et al. (2021), Hatoum et al. (2021), Husien et al. (2021), Majumder and Biswas (2021)
R2Tools and equipment unavailableEsa et al. (2020), Ogunnusi et al. (2020), Choi and Staley (2021), Hatoum et al. (2021), Kaushal (2021), Pamidimukkala and Kermanshachi (2021)
R3Lack of labourAdhikari and Poudyal (2021), Esa et al. (2020), Gamil and Alhagar (2020), Osuizugbo (2020), Alsharef et al. (2021), Biswas et al. (2021), King et al. (2021), Majumder and Biswas (2021), Zamani et al. (2021)
Health and safety prevention
S1Compulsory body temperature checkingEsa et al. (2020), Shibani (2020), Alsharef et al. (2021), Umar (2021)
S2Practice social distancingEsa et al. (2020), Shibani (2020), Alsharef et al. (2021), Iqbal et al. (2021), Kaushal (2021), Umar (2021)
S3Compulsory COVID-19 test for all workersEsa et al. (2020), Stiles et al. (2021), Umar (2021)
S4Extra management for workers' accommodation and working schedule as well as site sanitationEsa et al. (2020),Shibani (2020), Alsharef et al. (2021), Iqbal et al. (2021), Zamani et al. (2021)
S5Contact tracingAdhikari and Poudyal (2021), Esa et al. (2020), Iqbal et al. (2021), Kaushal (2021), Umar (2021), Zamani et al. (2021)
S6Provide health and safety education for all workersEsa et al. (2020), Alsharef et al. (2021), Iqbal et al. (2021), Umar (2021), Zamani et al. (2021)
Regulatory compliance
RC1Comply with government SOPEsa et al. (2020), King et al. (2021), Stiles et al. (2021)
RC2Regulatory confusionAlsharef et al. (2021), Choi and Staley (2021), King et al. (2021)
Contractual issues
C1Issues and interruptions in contractual termsGamil and Alhagar (2020), Ogunnusi et al. (2020), Alsharef et al. (2021), Biswas et al. (2021), Ebekozien et al. (2021), Hatoum et al. (2021), Kaushal (2021), Salami et al. (2021)
C2Increase in disputes, litigation and claimsAlsharef et al. (2021), Hatoum et al. (2021), Husien et al. (2021), Salami et al. (2021), Umar (2021)
Psychological health of employees
P1Social isolationLingard et al. (2021), Pamidimukkala et al. (2021), Umar (2021)
P2Stress about possibility of exposure to virusHatoum et al. (2021), Pamidimukkala and Kermanshachi (2021), Pamidimukkala et al. (2021), Stiles et al. (2021)
P3Job stress and burnoutHatoum et al. (2021), Lingard et al. (2021), Pamidimukkala et al. (2021), Stiles et al. (2021), Umar (2021)
P4Financial distressHatoum et al. (2021), Lingard et al. (2021), Pamidimukkala and Kermanshachi (2021)
P5Personal needs and family conflictHatoum et al. (2021), Lingard et al. (2021), Pamidimukkala and Kermanshachi (2021), Pamidimukkala et al. (2021), Stiles et al. (2021), Umar (2021)
Others
O1Adoption of new technologyAdhikari and Poudyal (2021), Gamil and Alhagar (2020), Alsharef et al. (2021), Hatoum et al. (2021), Lingard et al. (2021), Pamidimukkala and Kermanshachi (2021), Stiles et al. (2021)
O2Ability to secure loans at low interestAlsharef et al. (2021), Hatoum et al. (2021)
O3Review on improving existing systemAlsharef et al. (2021), Hatoum et al. (2021), Stiles et al. (2021)

Source(s): Table by authors

Demographic profile of respondents

ParameterCategoryRespondents groupTotalFrequency (%)
DeveloperConsultantContractor
DesignationExecutive24246311154.7
Manager143324924.1
Senior manager35142210.8
Director65102110.3
Years of experienceX ≤ 5 years1018396733.0
5 years > X ≤ 10 years185406331.0
10 years > X ≤ 15 years104163014.8
15 years > X ≤ 20 years533115.4
X > 20 years47213215.8
Education levelPostgraduate degree (Ph.D., Master’s degree)1912195024.6
Bachelor’s degree27249214370.4
Diploma, Certificate10783.9
High school01121.0

Source(s): Table by authors

Mean scores and ranking of ramifications

RefRamificationsOverall (N = 203)Developer (N = 47)Consultant (N = 37)Contractor (N = 119)KW
MeanSDRankMeanSDRankMeanSDRankMeanSDRankp-value
T3Rescheduling project timeline4.360.90414.360.96524.270.80444.390.91330.306
RC1Comply with government SOP4.350.91324.280.92634.300.81234.400.94210.229
T1Delay in hand over project4.340.98934.360.94214.350.85724.331.05050.891
S3Compulsory COVID-19 test for all workers4.320.99044.151.12264.270.90254.390.95940.260
F2Extra cost incurred to provide COVID-19 tests for workers4.280.96654.060.98794.140.918104.400.96020.008**
R3Lack of labour4.261.00864.191.03554.190.84574.311.04860.278
S4Extra management for workers' accommodation and working schedule as well as site sanitation4.200.99074.021.053114.141.004114.290.95870.199
T2Delay in material supply4.201.03484.151.14274.140.88794.241.03980.480
T4Delay in inspections and securing permits4.150.95594.190.97044.000.882164.180.974110.264
F6Increase in material cost4.151.039103.961.160144.410.76214.151.055120.215
R1Comply with government SOP4.111.030114.061.131104.160.83484.121.051140.943
S6Provide health and safety education for all workers4.091.030123.831.110214.030.928144.211.01690.039*
F7Suspension of projects/reduced number of planned projects4.060.975133.811.056234.190.77664.130.988130.112
F1Additional cost in providing personal protective equipment (PPE)4.060.985143.811.035223.970.866194.190.985100.017*
P4Financial distress4.001.002153.941.030164.110.843123.981.041180.839
S2Practice social distancing3.991.101163.771.127273.970.928204.081.136150.091
S5Contact tracing3.961.031173.701.140314.000.782154.041.045160.135
P2Stress about possibility of exposure of virus3.940.958183.960.908133.970.799183.921.026200.978
H2Low productivity3.931.037193.891.047193.951.026223.941.044190.960
C1Issues and interruptions in contractual terms3.900.975203.811.076243.760.863303.980.965170.231
P3Job stress and burnout3.881.027213.941.009153.921.010243.851.047230.862
P1Social isolation3.870.937223.960.884123.840.898263.840.974250.810
H5Limited access to construction site3.861.072233.941.111174.000.913163.791.104280.546
F5Cash flow problem/late payment3.861.104243.701.061294.050.941133.871.164220.324
C2Increase in disputes, litigation and claims3.851.019253.771.108263.730.871313.921.026200.281
O3Review on improving existing system3.840.974263.830.940203.951.026223.810.977260.588
P5Personal needs and family conflict3.810.992273.890.914183.780.947273.791.040270.852
S1Compulsory body temperature checking3.791.169283.641.206323.781.031283.851.198240.456
O1Adoption of new technology3.781.035293.790.999253.891.100353.751.035290.668
H1Reallocation of human resource3.760.942303.700.907283.970.957213.710.949300.335
RC2Regulatory confusion3.761.013314.090.80383.730.990323.641.071320.058
F4Cost in providing transportation for workers3.651.091323.491.159353.650.789333.711.145310.471
H4Work from home challenges3.631.146333.701.061293.781.031283.551.212330.671
F3Extra cost in appointing COVID-19 health supervisor3.481.114343.401.210373.650.949343.461.126340.625
R2Tools and equipment unavailable3.431.062353.471.231363.570.899373.371.040350.517
O2Ability to secure loan at low interest3.411.039363.621.033333.621.063353.271.110360.068
H3Termination of workers3.361.127373.531.177343.621.163363.211.080370.066

Note(s): SD denotes standard deviation, KW denotes Kruskal–Wallis, * and ** denote the mean is significant at 0.05 and 0.01, respectively

Source(s): Table by authors

Disclosure statement: No potential conflict of interest was reported by the authors.

References

Adhikari, K. and Poudyal, L. (2021), “Future of construction industry: COVID-19 and its implications on construction projects and risk management -A review”, Preprints, Vol. 2021 April, doi: 10.20944/preprints202104.0383.v1.

Alaloul, W.S., Musarat, M.A., Rabbani, M.B.A., Iqbal, Q., Maqsoom, A. and Farooq, W. (2021), “Construction sector contribution to economic stability: Malaysian gdp distribution”, Sustainability (Switzerland), Vol. 13 No. 9, pp. 1-26, doi: 10.3390/su13095012.

Alfakhri, A.Y.Y., Ismail, A. and Khoiry, M.A. (2018), “The effects of delays in road construction projects in Tripoli, Libya”, International Journal of Technology, Vol. 9 No. 4, pp. 766-774, doi: 10.14716/ijtech.v9i4.2219.

Alkilani, S.Z., Jupp, J. and Sawhney, A. (2013), “Issues of construction health and safety in developing countries: a case of Jordan”, Australasian Journal of Construction Economics and Building, Vol. 13 No. 3, pp. 141-156, doi: 10.5130/ajceb.v13i3.3301.

Alsharef, A., Banerjee, S., Uddin, S.M.J., Albert, A. and Jaselskis, E. (2021), “Early impacts of the COVID-19 pandemic on the United States construction industry”, International Journal of Environmental Research and Public Health, Vol. 18 No. 4, pp. 1-21, doi: 10.3390/ijerph18041559.

Amoah, C. and Simpeh, F. (2021), “Implementation challenges of COVID-19 safety measures at construction sites in South Africa”, Journal of Facilities Management, Vol. 19 No. 1, pp. 111-128, doi: 10.1108/JFM-08-2020-0061.

Amos, D., Au-Yong, C.P. and Musa, Z.N. (2021), “Enhancing the role of facilities management in the fight against the COVID-19 (SARS-CoV-2) pandemic in developing countries' public hospitals”, Journal of Facilities Management, Vol. 19 No. 1, pp. 22-31, doi: 10.1108/JFM-06-2020-0034.

Awwad, R., El Souki, O. and Jabbour, M. (2016), “Construction safety practices and challenges in a Middle Eastern developing country”, Safety Science, Vol. 83, pp. 1-11, doi: 10.1016/j.ssci.2015.10.016.

Bartlett, J.E., Kotrlik, J.W. and Higgins, C.C. (2001), “Organizational Research : Determining Appropriate Sample Size in Survey Research”, Information Technology, Lerning, and Performance Journal, Vol. 19 No. 1, pp. 43-50.

Biswas, A., Ghosh, A., Kar, A., Mondal, T., Ghosh, B. and Bardhan, D.P.K. (2021), “The impact of COVID-19 in the construction sector and its remedial measures”, Journal of Physics: Conference Series, Vol. 1797 No. 1, 012054, doi: 10.1088/1742-6596/1797/1/012054.

Centers for Disease Control and Prevention (2022), “Symptoms of COVID-19 | CDC”, available at: https://www.cdc.gov/coronavirus/2019-ncov/symptoms-testing/symptoms.html (accessed 26 December 2022).

Chan, D. (2020), “Construction sites' Covid-19 cases cause for concern”, available at: https://www.nst.com.my/news/nation/2020/05/595478/construction-sites-covid-19-cases-cause-concern (accessed 16 August 2021).

Choi, S.D. and Staley, J. (2021), “Safety and Health Implications of COVID-19 on the United States Construction Industry”, Industrial and Systems Engineering Review, Vol. 9 No. 1, pp. 56-67, doi: 10.37266/iser.2021v9i1.pp56-67.

Dao, T.L., Nguyen, T.D. and Hoang, V.T. (2020), “Controlling the COVID-19 pandemic: useful lessons from Vietnam”, Travel Medicine and Infectious Disease, Vol. 37, 101822, doi: 10.1016/J.TMAID.2020.101822.

Dawel, A., Shou, Y., Smithson, M., Cherbuin, N., Banfield, M., Calear, A.L., Farrer, L.M., Gray, D., Gulliver, A., Housen, T., McCallum, S.M., Morse, A.R., Murray, K., Newman, E., Rodney Harris, R.M. and Batterham, P.J. (2020), “The effect of COVID-19 on mental health and wellbeing in a representative sample of Australian adults”, Frontiers in Psychiatry, Vol. 11 October, pp. 1-8, doi: 10.3389/fpsyt.2020.579985.

Deep, S., Bhoola, V., Vidhani, J. and Hampannaver, P.R. (2022), “Evaluating the impact of constraints on project success: empirical study of highway projects”, Built Environment Project and Asset Management, Vol. 12 No. 4, pp. 684-700, doi: 10.1108/BEPAM-05-2021-0074.

Deng, X., Low, S.P., Zhao, X. and Chang, T. (2018), “Identifying micro variables contributing to political risks in international construction projects”, Engineering, Construction and Architectural Management, Vol. 25 No. 3, pp. 317-334, doi: 10.1108/ECAM-02-2017-0042.

Department of Statistics Malaysia (2023), “Gross domestic product (GDP)”, available at: https://open.dosm.gov.my/gdp (accessed 25 July 2023).

Department of Statistics Malaysia Official Portal (2015), “Report on survey of construction industries 2014”, available at: https://www.dosm.gov.my/v1/index.php?r=column/cthemeByCat&cat=321&bul_id=N3AzSEJ3cWhOT2tvOUE5Rmk1blFaQT09&menu_id=OEY5SWtFSVVFVUpmUXEyaHppMVhEdz09 (accessed 8 June 2022).

Dolnicar, S. (2021), “5/7-point ‘Likert scales’ aren't always the best option: their validity is undermined by lack of reliability, response style bias, long completion times and limitations to permissible statistical procedures”, Annals of Tourism Research, Vol. 91, pp. 1-3, doi: 10.1016/j.annals.2021.103297.

Doloi, H. (2009), “Analysis of pre-qualification criteria in contractor selection and their impacts on project success”, Construction Management and Economics, Vol. 27 No. 12, pp. 1245-1263, doi: 10.1080/01446190903394541.

Durdyev, S., Mohamed, S., Lay, M.L. and Ismail, S. (2017), “Key factors affecting construction safety performance in developing countries: evidence from Cambodia”, Construction Economics and Building, Vol. 17 No. 4, pp. 48-65, doi: 10.5130/AJCEB.v17i4.5596.

Ebekozien, A., Aigbavboa, C. and Aigbedion, M. (2021), “Construction industry post-COVID-19 recovery: Stakeholders perspective on achieving sustainable development goals”, International Journal of Construction Management, Taylor & Francis, pp. 111, doi: 10.1080/15623599.2021.1973184.

Esa, M.B., Ibrahim, F.S.B. and Kamal, E.B.M. (2020), “Covid-19 pandemic lockdown: the consequences towards project success in malaysian construction industry”, Advances in Science, Technology and Engineering Systems, Vol. 5 No. 5, pp. 973-983, doi: 10.25046/aj0505119.

Etikan, I. and Bala, K. (2017), “Sampling and sampling methods”, Biometrics and Biostatistics International Journal, Vol. 5 No. 6, pp. 215-217, doi: 10.15406/bbij.2017.05.00149.

Fellow, R. and Liu, A. (2015), Research Methods for Construction, John Wiley & Sons.

Gamil, D.Y. and Alhagar, A. (2020), “The impact of pandemic crisis on the survival of construction industry: a case of COVID-19 Dr. Yaser Gamil Abdulsalam Alhagar”, Mediterranean Journal of Social Sciences, Vol. 11 No. 4, pp. 122-128, doi: 10.36941/mjss-2020-0047.

Hallin, H. (2020), “Home-based Telework during the covid-19 pandemic”, p. 5.

Harari, Y.N. (2020), “The world after coronavirus”, Financial Times, available at: https://www.ft.com/content/19d90308-6858-11ea-a3c9-1fe6fedcca75 (accessed 28 September 2021).

Hatoum, M.B., Faisal, A., Nassereddine, H. and Sarvari, H. (2021), “Analysis of COVID-19 concerns raised by the construction workforce and development of mitigation practices”, Frontiers in Built Environment, Vol. 7 May, pp. 1-15, doi: 10.3389/fbuil.2021.688495.

Husien, I.A., Borisovich, Z. and Naji, A.A. (2021), “COVID-19: key global impacts on the construction industry and proposed coping strategies”, E3S Web of Conferences, Vol. 263, 05056, doi: 10.1051/e3sconf/202126305056.

Iqbal, M., Ahmad, N., Waqas, M. and Abrar, M. (2021), “COVID-19 pandemic and construction industry: impacts, emerging construction safety practices, and proposed crisis management framework”, Brazilian Journal of Operations and Production Management, Vol. 18 No. 2, pp. 1-17, doi: 10.14488/BJOPM.2021.034.

Kaklauskas, A., Zavadskas, E.K., Lepkova, N., Raslanas, S., Dauksys, K., Vetloviene, I. and Ubarte, I. (2021), “Sustainable construction investment, real estate development, and covid-19: a review of literature in the field”, Sustainability (Switzerland), Vol. 13 No. 13, pp. 1-42, doi: 10.3390/su13137420.

Kaushal, V. (2021), “Strategies to Mitigate COVID-19 Pandemic Impacts on Health and Safety of Workers in Construction Projects”, Civil Engineering Beyond Limits, Vol. 2 No. 2, pp. 1-8, doi: 10.36937/cebel.2021.002.001.

King, S.S., Rahman, R.A., Fauzi, M.A. and Haron, A.T. (2021), “Mechanisms for addressing the impact of COVID-19 on infrastructure projects”, IOP Conference Series: Earth and Environmental Science, Vol. 682 No. 1, 012047, doi: 10.1088/1755-1315/682/1/012047.

Kumar, R. (2011), Research Methodology: A Step-vy-step Guide for Beginners, 3rd ed., SAGE Publications, London, Vol. 148.

Lingard, H., Peihua Zhang, R., Räisänen, C., Miang Goh, Y., Bowen, P. and Bhandari, S. (2021), “Special issue: what have we learnt from the COVID-19 global pandemic: improving the construction industry's abilities to foresee, respond to and recover from future endemic catastrophes”, Construction Management and Economics, Vol. 39 No. 2, pp. 192-197, doi: 10.1080/01446193.2020.1869480.

Loayza, N. and Pennings, S. (2020), “Macroeconomic policy in the time of COVID-19: a primer for developing countries”, Research and Policy Briefs, No. 28, pp. 1-9.

Majumder, S. and Biswas, D. (2021), COVID-19 Impacts Construction Industry: Now, Then and Future, Springer Nature Singapore Pte Ltd., Vol. 60.

Malaysiakini (2020), “Covid-19 (Dec 15): 1,772 new cases, large construction cluster in KL”, available at: https://www.malaysiakini.com/news/555340 (accessed 13 August 2021).

Naoum, S.G. (2019), Dissertation Research and Writing for Built Environment Students, 4th ed, Routledge, London and NewYork.

New Straits Times (2021), “Construction sector allowed to operate under strict SOP”, available at: https://www.nst.com.my/news/nation/2021/07/711307/construction-sector-allowed-operate-under-strict-sop (accessed 10 June 2022).

Newby, J.M., Moore, K.O., Id, S.T., Christensen, H. and Faasse, K. (2020), “Acute mental health responses during the COVID-19 pandemic in Australia”, pp. 1-21, doi: 10.1371/journal.pone.0236562.

Niroshana, N., Siriwardana, C. and Jayasekara, R. (2022), The Impact of COVID-19 on the Construction Industry and Lessons Learned: A Case of Sri Lanka, Taylor & Francis, doi: 10.1080/15623599.2022.2076016.

Ogunnusi, M., Hamma-adama, M., Salman, H. and Kouider, T. (2020), “COVID-19 pandemic: the effects and prospects in the construction industry”, International Journal of Real Estate Studies, available at: https://www.utm.my/intrest/files/2020/11/2_Final_MS_CRES-Covid-025

Osuizugbo, I.C. (2020), “Disruptions and Responses within Nigeria Construction Industry amid COVID-19 Threat”, Covenant Journal of Research in the Built Environment, Vol. 8 No. 2, pp. 37-48, available at: http://journals.covenantuniversity.edu.ng/index.php/cjrbe/article/view/2457.

Pamidimukkala, A. and Kermanshachi, S. (2021), “Impact of COVID-19 on field and office workforce in construction industry”, Project Leadership and Society, Vol. 2, doi: 10.1016/j.plas.2021.100018.

Pamidimukkala, A., Kermanshachi, S. and Jahan Nipa, T. (2021), “Impacts of COVID-19 on health and safety of workforce in construction industry”, International Conference on Transportation and Development 2021: Transportation Planning and Development - Selected Papers from the International Conference on Transportation and Development 2021, Vol. 19, pp. 418-430, doi: 10.1061/9780784483541.040.

PropertyGuru (2021), “188 construction sites ordered to close for breaching COVID-19 SOP | market news | PropertyGuru.com.my”, available at: https://www.propertyguru.com.my/property-news/2021/7/199713/188-construction-sites-ordered-to-close-for-breaching-covid-19-sop (accessed 24 September 2021).

Salami, B.A., Ajayi, S.O. and Oyegoke, A.S. (2021), “Tackling the impacts of Covid-19 on construction projects: an exploration of contractual dispute avoidance measures adopted by construction firms”, International Journal of Construction Management, Vol. 23 No. 7, pp. 1-9, doi: 10.1080/15623599.2021.1963561.

Shafiq, M.T. and Afzal, M. (2020), “Potential of virtual design construction technologies to improve job-site safety in gulf corporation council”, Sustainability (Switzerland), Vol. 12 No. 9, p. 3826, doi: 10.3390/su12093826.

Shibani, A. (2020), “Evaluate the UK Construction Project Impact and Response Strategies during the Epidemic through Malaysia and China”, Journal of Advanced Research in Civil and Environmental Engineering, Vol. 7 Nos. 3-4, pp. 17-26, doi: 10.24321/2393.8307.202005.

Simpeh, F. and Amoah, C. (2021), “Assessment of measures instituted to curb the spread of COVID-19 on construction site”, International Journal of Construction Management, Vol. 23 No. 3, pp. 1-19, doi: 10.1080/15623599.2021.1874678.

Simpeh, F., Bamfo-Agyei, E. and Amoah, C. (2021), “Barriers to the implementation of COVID-19 safety regulations: insight from Ghanaian construction sites”, Journal of Engineering, Design and Technology, Vol. 20 No. 1, pp. 47-65, doi: 10.1108/JEDT-03-2021-0153.

Sospeter, N.G., Rwelamila, P.D. and Gimbi, J.J. (2022), “A conceptual framework for managing post-disaster reconstruction projects in emerging economies: the case of Angola”, Built Environment Project and Asset Management, Vol. 12 No. 2, pp. 205-222, doi: 10.1108/BEPAM-03-2021-0040.

Star Property (2020), “Rehda proposes that the government bear the cost of covid-19 testing”, available at: https://www.starproperty.my/news/property-news/rehda-proposes-that-the-government-bear-the-cost-of-covid-19-testing/117883 (accessed 10 June 2022).

Stiles, S., Golightly, D. and Ryan, B. (2021), “Impact of COVID-19 on health and safety in the construction sector”, Human Factors and Ergonomics In Manufacturing, Vol. 31 No. 4, pp. 425-437, doi: 10.1002/hfm.20882.

The World Bank (2020), “COVID-19 to plunge global economy into worst recession since world war II”, available at: https://www.worldbank.org/en/news/press-release/2020/06/08/covid-19-to-plunge-global-economy-into-worst-recession-since-world-war-ii (accessed 24 May 2022).

Umar, T. (2021), “The impact of COVID-19 on the GCC construction industry”, International Journal of Service Science, Management, Engineering, and Technology, Vol. 13 No. 2, pp. 1-17, doi: 10.4018/ijssmet.20220301.oa1.

WHO (2023), “Advice for the public”, available at: https://www.who.int/emergencies/diseases/novel-coronavirus-2019/advice-for-public (accessed 25 March 2023).

Yap, J.B.H. and Cheah, S.Y. (2020), “Key challenges faced by Chinese contractors in Malaysian construction industry: empirical study”, Journal of Engineering, Design and Technology, Vol. 18 No. 3, pp. 705-726, doi: 10.1108/JEDT-05-2019-0124.

Yap, J.B.H. and Lee, W.K. (2019), “Analysing the underlying factors affecting safety performance in building construction”, Production Planning and Control, Vol. 31 No. 13, pp. 1061-1076, doi: 10.1080/09537287.2019.1695292.

Yap, J.B.H., Chow, I.N. and Shavarebi, K. (2019), “Criticality of construction industry problems in developing countries: analyzing Malaysian projects”, Journal of Management in Engineering, Vol. 35 No. 5, 04019020, doi: 10.1061/(asce)me.1943-5479.0000709.

Yap, J.B.H., Lee, K.Y. and Skitmore, M. (2020), “Analysing the causes of corruption in the Malaysian construction industry”, Journal of Engineering, Design and Technology, Vol. 18 No. 6, pp. 1823-1847, doi: 10.1108/JEDT-02-2020-0037.

Yap, J.B.H., Lam, C.G.Y., Skitmore, M. and Talebian, N. (2022), “Barriers to the adoption of new safety technologies in construction: a developing country context”, Journal of Civil Engineering and Management, Vol. 28 No. 2, pp. 120-133, doi: 10.3846/jcem.2022.16014.

Yap, B.W. and Sim, C.H. (2011), “Comparisons of various types of normality tests”, Journal of Statistical Computation and Simulation, Vol. 81 No. 12, pp. 2141-2155, doi: 10.1080/00949655.2010.520163.

Zakia and Febrianti, D. (2021), “The critical path method in construction project rescheduling”, IOP Conference Series: Earth and Environmental Science, Vol. 832 No. 1, 012009, doi: 10.1088/1755-1315/832/1/012009.

Zamani, S.H., Rahman, R.A., Fauzi, M.A. and Yusof, L.M. (2021), “Effect of COVID-19 on building construction projects: impact and response mechanisms”, IOP Conference Series: Earth and Environmental Science, Vol. 682 No. 1, 012049, doi: 10.1088/1755-1315/682/1/012049.

Acknowledgements

The authors would like to acknowledge the Ministry of Education Malaysia (MOE) for financial support under Fundamental Research Grant Scheme (FRGS) Project Number: FRGS/1/2022/SS02/UTAR/02/1 for the project entitled “Technology Readiness Index (TRI) for the adoption of innovative technologies in construction safety science and management in Malaysia” and UTAR Research Fund (UTARRF) Project Number: IPSR/RMC/UTARRF/2021-C1/J01. The authors express their sincere thanks to all the industry practitioners who have participated in the data collection process.

Corresponding author

Yi Tong Kum can be contacted at: yitong6015@gmail.com

Related articles