TY - JOUR AB - Purpose– This paper aims to develop a fuzzy risk assessment model for construction projects procured with target cost contracts and guaranteed maximum price contracts (TCC/GMP) using the fuzzy synthetic evaluation method, based on an empirical questionnaire survey with relevant industrial practitioners in South Australia. Design/methodology/approach– A total of 34 major risk factors inherent with TCC/GMP contracts were identified through an extensive literature review and a series of structured interviews. A questionnaire survey was then launched to solicit the opinions of industrial practitioners on risk assessment of such risk factors. Findings– The most important 14 key risk factors after the computation of normalised values were selected for undertaking fuzzy evaluation analysis. Five key risk groups (KRGs) were then generated in descending order of importance as: physical risks, lack of experience of contracting parties throughout TCC/GMP procurement process, design risks, contractual risks and delayed payment on contracts. These survey findings also revealed that physical risks may be the major hurdle to the success of TCC/GMP projects in South Australia. Practical implications– Although the fuzzy risk assessment model was developed for those new-build construction projects procured by TCC/GMP contracts in this paper, the same research methodology may be applied to other contracts within the wide spectrum of facilities management or building maintenance services under the target cost-based model. Therefore, the contribution from this paper could be extended to the discipline of facilities management as well. Originality/value– An overall risk index associated with TCC/GMP construction projects and the risk indices of individual KRGs can be generated from the model for reference. An objective and a holistic assessment can be achieved. The model has provided a solid platform to measure, evaluate and reduce the risk levels of TCC/GMP projects based on objective evidence instead of subjective judgements. The research methodology could be replicated in other countries or regions to produce similar models for international comparisons, and the assessment of risk levels for different types of TCC/GMP projects (including new-build or maintenance) worldwide. VL - 32 IS - 11/12 SN - 0263-2772 DO - 10.1108/F-08-2012-0063 UR - https://doi.org/10.1108/F-08-2012-0063 AU - Chan Daniel W.M. AU - Chan Joseph H.L. AU - Ma Tony PY - 2014 Y1 - 2014/01/01 TI - Developing a fuzzy risk assessment model for guaranteed maximum price and target cost contracts in South Australia T2 - Facilities PB - Emerald Group Publishing Limited SP - 624 EP - 646 Y2 - 2024/04/19 ER -