Using BIM capabilities to improve existing building energy modelling practices

Tristan Gerrish (Department of Civil and Building Engineering, Loughborough University, Loughborough, UK)
Kirti Ruikar (Department of Civil and Building Engineering, Loughborough University, Loughborough, UK)
Malcolm Cook (Department of Civil and Building Engineering, Loughborough University, Loughborough, UK)
Mark Johnson (BuroHappold Engineering, Leeds, UK)
Mark Phillip (BuroHappold Engineering, Leeds, UK)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 20 March 2017

9553

Abstract

Purpose

The purpose of this paper is to present a review of the implications building information modelling (BIM) is having on the building energy modelling (BEM) and design of buildings. It addresses the issues surrounding exchange of information throughout the design process, and where BIM may be useful in contributing to effective design progression and information availability.

Design/methodology/approach

Through review of current design procedures and examination of the concurrency between architectural and thermophysical design modelling, a procedure for information generation relevant to design stakeholders is created, and applied to a high-performance building project currently under development.

Findings

The extents of information key to the successful design of a buildings energy performance in relation to its architectural objectives are given, with indication of the level of development required at each stage of the design process.

Practical implications

BIM offers an extensible medium for parametric information storage, and its implementation in design development offers the capability to include BEM parameter-integrated construction information. The extent of information required for accurate BEM at stages of a building’s design is key to understanding how best to record performance information in a BIM environment.

Originality/value

This paper contributes to the discussion around the integration of concurrent design procedures and a common data environment. It presents a framework for the creation and dissemination of information during design, exemplifies this on a real building project and evaluates the barriers experienced in successful implementation.

Keywords

Citation

Gerrish, T., Ruikar, K., Cook, M., Johnson, M. and Phillip, M. (2017), "Using BIM capabilities to improve existing building energy modelling practices", Engineering, Construction and Architectural Management, Vol. 24 No. 2, pp. 190-208. https://doi.org/10.1108/ECAM-11-2015-0181

Publisher

:

Emerald Publishing Limited

Copyright © 2017, Tristan Gerrish, Kirti Ruikar, Malcolm Cook, Mark Johnson and Mark Phillip

License

Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial & non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at: http://creativecommons.org/licences/by/4.0/legalcode


1. Introduction

The design of a building is a major determinant in its operational energy performance, with decisions made at this stage contributing to the energy consumed during use (Bordass et al., 2004). Widespread adoption of building information modelling (BIM) to support design provides a platform on which improvement of this performance could be made (Krygiel and Nies, 2008). Through creating a shared knowledge resource for descriptive information, forming a reliable basis for decisions during its life-cycle (BIM Task Group, 2011), BIM could provide the means to transfer information more effectively than the multiple formats and channels previously employed (Chen and Luo, 2014; Redmond et al., 2012; Titus and Bröchner, 2004).

Building energy modelling (BEM) is the analysis of building energy performance through its simulation using predefined criteria describing building composition and utilisation. McGraw Hill Construction (2010) identified the growing benefits of BIM enhanced BEM through numerous case studies and industry feedback, showing how the transfer of information between BEM tools and BIM authoring tools can facilitate the design of more sustainable buildings. Unfortunately, the quantification of improvement is a difficult metric to measure, given each project’s uniqueness. However, increased efficiency in modelling processes (re-use of information from a common data environment (CDE)) enables more time for performance analysis and design optimisation (Arayici et al., 2011).

Understanding the parameters necessary to enable multiple users to complete design activities is essential in the use of BIM, with limitations on accuracy imposed by the extent and detail of modelled data across various modelling platforms (Bordass et al., 2004; Menezes et al., 2012). Information availability also changes throughout the design process – and can only be comprehensive post-construction. Bazjanac and Kiviniemi (2007) demonstrate that data exchange requires translation of datasets to support downstream applications, and that simplification is often used to enable this transfer. Tribelsky and Sacks (2010) action pathway identifies information flows and suggests BIM could assist in identifying the points at which design relies on exchange of key data. However, to implement process efficiency improvements, uncertainty at the points of information redistribution must be mitigated. Collection of information in a structured environment (such as the data drop concept (BIM Task Group, 2012)) allows incremental validation and extraction of descriptive data at these points, for input into BEM environments.

This work aims to identify the current capacity of BIM in the handling of BEM data, how information moves between these two areas, and how procedures must change to enable effective use of these two modelling platforms concurrently where full interoperability is not yet realised. The BEM design process is mapped alongside an engineering design process, indicating the stakeholders involved at each stage of development. The parameters required during these stages are recorded in a BIM environment where a process map including fixed data drop points is defined.

The BIM environment discussed in this research refers to Autodesk Revit and its capabilities as a 3D modelling tool with attached databases. However, it must be stated that the BIM environment is more than data developed in a single software platform and represents the sum total information developed throughout a building’s design.

2. Background

The construction industry is known to be comprised of silos of contributing designers with periodic coordination and information sharing (Gelder, 2012; Merschbrock, 2012). These dis-integrated silos have resulted in the separate development of discipline specific modelling tools for specific design purposes. For example, Autodesk Revit for creation of architectural layouts and drawings, IES-VE for creation of energy performance simulations, and numerous other tools dedicated to one particular aspect of a building’s design or eventual operation. Transfer of information between these tools relies on the ability of each tool interpret the others output, utilise this data and record this in an interpretable format.

Methods of sharing information between BEM and BIM tools have emerged in the form of exchange formats, aiming to provide an open environment in which extensible data can be recorded in a non-proprietary format (Laakso and Kiviniemi, 2012). Proprietary tools then access this information and in most cases write to the same open format for sharing with other tools. However, given the availability of an open format to all potential authoring and reading environment, some loss of functionality is often experienced as these proprietary tools have specific functionality not represented in open exchange format (Figure 1).

Sacks et al. (2005) suggest error reduction could reduce whole project cost by 2.3-4.2 per cent, with reduction of rework constituting a significant proportion of this (Hwang et al., 2009). As the building is developed and occupied, the amount of related information increases, as does the likelihood for inclusion of inaccurate data (which has been superseded or incorrectly recorded). Hicks (2007) expanded upon this problem, stating waste occurring from inaccurate information could result in inappropriate downstream activities, corrective actions or additional verification, with Love et al. (2011) suggesting errors are unavoidable event using BIM.

Given the cumulative amount of data generated in a construction project (Tribelsky and Sacks, 2010) and the number of stakeholders involved (Hughes and Murdoch, 2001), identification of the key data necessary to support concurrent and downstream engineering activities is essential. Research into information transfer has thus far concentrated on whole project aspects such as transfer methods (Tribelsky and Sacks, 2010), operation efficiency (Titus and Bröchner, 2004) and stakeholder interactions (Olander and Landin, 2005), without definition of the types of information required for a singular aspect of design. For the design of a buildings energy performance, creation of an information development and verification framework could reduce the likelihood of inaccurate information being used and recorded at key stages of project development.

2.1 Interoperability between BIM and BEM

Several studies have attempted to incorporate information storage (BIM) and performance analysis (BEM) functionality (Table I), but encounter recurring limitations, most commonly during information transfer between BIM and BEM. Information is currently stored in separate formats before interpretation (Hitchcock and Wong, 2011), with BIM and BEM developed separately, allowing non-concurrent changes to appear, and contributing to the performance disparity between predicted and post-construction building performance. Additionally, transfer of information using a common format is rarely used. For example, storage of heating, ventilation and air-conditioning (HVAC) systems details or spatial geometries is possible in both BEM and BIM tools, however, the method of storing this information is not standardised leading to incompatible transfer of this data.

2.1.1 BEM

During building design, simulation is widely used to inform decisions governing a building’s performance (such as the sizing of plant equipment and provision of specific services). Discretisation of design aspects (e.g. simplification of external climate or factors applied to fixed equipment performance values to account for changes in utilisation over time) are required to simulation performance (Clarke, 2001, p. 64). The various purposes and methodologies of BEM add further complexity to determining a reasonable level of input detail to output valid results.

2.1.2 BIM parametric information storage and utilisation

Autodesks Revit offers a form of simplified energy performance analysis (Green Building Studio), estimating whole building performance. This is useful at early stages of design for comparison between options, but later where calibration of operating schedules and definition of equipment loads is essential, a validated analysis tool is necessary (Ryan and Sanquist, 2012).

Several efforts to integrate BEM within BIM (or using BIM data) have been attempted (Azhar et al., 2009; Bazjanac, 2008; Hitchcock and Wong, 2011), with Aksamija et al. (2011) and Sinha et al. (2013) demonstrating how use of BIM for compliance checking and basic sustainability analysis can be achieved. However, performance analysis integration is still undeveloped and the information from the BIM must be extracted or copied, then evaluated separately.

2.1.3 Interoperability

Information sharing between BIM authoring tools and BEM tools currently relies on open exchange formats of IFC and gbXML. Both provide means of storing geometry with attributed data; however, this information is often not accurately exported by the BIM tool or interpretable by the BEM tool. Figure 2 demonstrates this through creation and transfer of information between Autodesk Revit and IES-VE via the gbXML and IFC formats.

This indicates that a specification for storage of performance impacting parameters is required (building on work by Morrissey et al., 2004) outside attempts to enable this through open exchange formats, enabling accurate information transfer between energy modellers and building designers.

Process mapping of BEM during building design has been investigated previously (Attia et al., 2013; Grinberg and Rendek, 2013). Comprehensive guidance in the implementation of integrated energy design given by Intelligent Energy Europe (2007) did not include reference to implementation within an integrated design/analysis environment (BIM). However, it did define the process of BEM and indicated the problems encountered in attempting to streamline this process. For example, the additional time and resources required during early design, and the need for all stakeholders to appreciate the impacts of theirs and others actions in the overall design process.

3. Methodology

This paper proposes that BIM may be a repository for information storage and accuracy checking during design, to produce an as-built building model, used for BEM interim to the implementation of open exchange formats. The above reasons form the basis for the creation of a procedure followed to enable accurate information storage and transfer between a BIM environment and BEM, using conventional means supported by a defined extent of data being shared.

The methodology used to infer conclusions regarding the potential for implementation of a BIM/BEM information generation and access framework was developed during the design of several key projects, where both BIM and BEM were used concurrently, feeding into the finished design. The procedure used is described in detail in the following section, with an overview of this process, and the means through which conclusions were drawn are given here.

3.1 Building performance design information

Initially, identification of the information pertinent to the development of an energy model at different stages of design is made. The extents of this inform the information extracted from the BIM at progressive stages of the building design development process. The BuildingSMART model view definition for architectural design to building energy analysis (Welle and See, 2011) outlines the key information applicable to building energy analysis, and is used as the basis for this identification. The stages to which information are applied are based on the RIBA (2013) plan of works and split between early stage conceptual analyses, detailed design and system sizing and compliance checking, representing the key stages of BEM development.

In the typical design process of a high-performance non-domestic building, where conceptual designs are evaluated and progressed through to technical design of its configured components, its eventual performance is based primarily on compliance with local regulation, fulfilment of client requirements and response to uncontrollable external factors (such as climate and location).

The information relevant to these criteria, and the optimisation of the buildings form, systems and operation changes based on the extent to which BEM takes place. For example, a small office building would require less careful evaluation than a large art gallery where internal climate is subject to more careful control. Defining a generic information development process aims to outline necessary information without being prescriptive and making this inapplicable to a large range of potential building developments.

Table II shows that the basic definitions of information types necessary to perform an energy performance simulation are limited; however, the details within these categories are extensive (Clarke, 2001). Each category is also recorded in a BIM environment with very little work required to identify where this information could be stored. For example, Autodesk Revit provides an extensible environment where fields for usage, occupancy levels, lighting and equipment data can be used (Tammik, 2011). Constructions defining walls and windows also provide the user the ability to store thermophysical characteristics (although this information is lost upon export; Costa et al., 2013, Figure 2).

3.2 Information exchange requirements

The information development and handover process was defined, specifically for data pertaining to the performance of the building and the involvement of design stakeholders in this process. The requirements of these stakeholders influence the progression of design, where some information is required prior to the specification of certain elements. For example, prior to the creation of a baseline energy performance model around which plant sizing takes place, there must first be a definitive model describing geometry, location and proposed function of the building. The involvement of stakeholders are identified in Figure 3, with the information provided and demanded by each to assist identification of the basic information to be stored and shared via BIM.

3.3 Framework development and application

Following definition of the current BEM and design process, these actions are mapped to existing frameworks for quantification of information at key stages during design. The level of development (LOD) definitions provided by the American Institute of Architects and Associated General Contractors of America (2013) and data drop concept adopted by the UK BIM Task Group (2012) provide the basis for defining information extent and maturity throughout design, to which BEM relevant information is applied. This is then used to map generation of this data to the BIM design process and provide a means with which to specify at key stages of development the type, and extent of information necessary for storage in the BIM, for use in BEM.

3.4 Evaluation

The method of sharing information between BIM and BEM environments and their stakeholders is specified, and this process is applied to the development of a detailed design of two multi-purpose university teaching facilities and a mixed-use residential scheme. The means through which information in these projects is created, stored, shared and utilised is followed, noting key issues encountered, and potential improvements to procedures. The issues encountered are characterised as system-, skill- and process-based, and are discussed to contribute knowledge of factors limiting the integration of BIM and BEM in industry adoption of BIM.

4. Development and application of a BIM supported BEM procedure

To assess the barriers encountered in attempting to embed BEM information in a BIM environment, key issues (categorised as (skill) (System) or (Process)) are linked to points for discussion in the “Discussion” section of this paper.

4.1 Information exchange between design stakeholders

Little work has been done to investigate the building energy performance information flow during building design, though several documents provide guidance to integrate low-energy design techniques such as parametric modelling into the process. As part of BuildingSMARTs Information Delivery Manual for Building Energy Analysis (Welle and See, 2011) the method of providing BEM support to design is outlined, indicating several of the processes undertaken therein. This procedure changes for each stage of design, as does modelling purpose, but provides a clear method for the creation of validated, accurate building performance simulations. The American Institute of Architects (2012) best practise guide describing the types of modelling inputs and elements altered during design, as well as identifying key stakeholders involved in the process are incorporated in Figure 3.

Using existing design progression frameworks, including the activities currently being undertaken in the building design processes evaluated here, Figure 3 shows the stakeholders supplying, using and extracting information from the BEM process. The classification of these roles in terms of supply and demand is a simplification not fully representative of these stakeholders in a building’s development, but are reasonable in outlining the process. These roles are adapted from Bakens et al. (2005), linked to the information each stakeholder supplies and demands at each stage of development.

Energy modelling can occur at any time during a buildings’ life-cycle. Incremental models contain varying amounts of information, with data generated by prior models used to inform decisions made at the subsequent stages. However, use of this information post-construction is uncommon (Way et al., 2009), due to the complexity of modelling a building to the necessary level of detail without significant building performance improvement (Prívara et al., 2012), and the costs attributed to this. The impact the building modeller has on design decisions decreases as the design develops (Essig, 2010) meaning the greater amount of accurate information known early on, the more opportunity there is to make improvements to the design. Early stages are also where most performance-related information is generated (Tribelsky and Sacks, 2010). Tupper and Fluhrer (2010) suggest the energy model should inform design; however, this often does not happen due to financial and time constraints (system, process).

As demonstrated by He et al. (2014), in each stage of design development, key information regarding the performance of the building is generated and utilised for design progression. Progression can stop if information pertaining to a certain aspect of the design is unavailable (Aouad et al., 1998). For example, regulatory compliance is necessary before the project can be put to tender, or the tendered project is one which fails to comply with regulation requirements.

4.2 Information development

Quantising the building design stages and points of information handover has been applied to BIM through the “data drop” concept suggested by RIBA (2012) and the UK BIM Task Group (2012). Data drops indicate fixed stages where information should reach a particular level of completion, for verification and use in the next stage of development. Within a data drop, each portion of information describing some part of a model is referenced using an agreed method of classification. For example, BSI (2007) specifies metadata such as project, location, role, classification and revision. These naming conventions are kept throughout design development (Process), allowing those with an understanding of this concept a means of finding the relevant information (skill). While classification of information is useful for reference, its amount and maturity is essential to indicate model development.

Measuring the extent of information at key stages can be achieved through use of the LOD concept. Detailed descriptions of this are given by the AIA and AGC (2013), where an arbitrary scale from 100 to 500 is used to indicate the amount of information subject to further change applied to modelled building objects. Within this scale, 350 is also included, as it represents a stage in the project where clash detection takes place – in particular how systems interact with each other.

This schema for defining the information to be collected at different stages does not explicitly include information applicable to BEM (with the exception of basic geometries, external window characteristics and plumbing, ventilation and electrical systems). Information required for simple energy analysis must often be derived rather than collected directly from the original model/format (System). The minimum required information for BEM is applied to the LOD specification for input into a BIM-integrated BEM data repository Table III. As this develops throughout design, information becomes less likely to change and is therefore more representative of the completed building.

These levels of development applied to the current BEM process map indicate the information extent at each of these points of design development, defining the information required to be stored within the BIM to enable effective extraction of BEM information at each stage (Process).

4.3 Information exchange

The sharing of information between BIM and BEM tools can be problematic, especially when consideration is not made at an early stage in the design process. Without procedures in place for the standard to which a building is modelled, extraction of elements from one environment for use in another can cause errors in data recreation (Process) (Welle et al., 2011), gaps in knowledge where data stored in one format is not available in another (System) (Costa et al., 2013) or inability to access information due to proprietary formats (System) (Sanguinetti et al., 2012). Several of these were experienced in the university teaching facilities projects due to the platforms on which information was initially created not matching those with which that information was then developed.

To avoid these issues and evaluate BIM’s potential for information capture, storage, utilisation and sharing, a conventional means of data exchange is used to eliminate the potential for these issues to affect the testing of the framework created. Conventional information exchange has long used project extranets and document management systems to collate all relevant design information (Yeomans et al., 2005). It is foreseeable that these will integrate with BIM to collate all relevant design documentation for eventual handover to the buildings occupant/operator; however, until then user input is required to share such information.

The procedure followed to create, record and extract information within the BIM and then access this is outlined in Figure 4 (demonstrative of a common process followed to create and share information during design, without use of exchange formats). For each of the projects to which the eventual information development framework was applied, the means of exchange between modelling platforms here was a Room Data Sheet (RDS); a spreadsheet containing characteristics exported from the BIM to be referenced in the creation of a standalone energy performance model. Output from simulations are then transferred to the RDS using an export and Dynamo (Autodesk, 2016) import for reinstating this information in the BIM, for use downstream. Until full interoperability is feasible, exchange methods such as this are the go-to means of information transfer in buildings engineering for the exchange of information between multiple modelling platforms.

4.4 Framework creation

As design progresses, the amount of information available to inform the next stage of design or operations increases. BIM enables the monitoring and management of this information to allow its collection in a CDE.

The information stored within an BEM is dependent on the type of simulation that tool provides. Methods of determining performance range from simple steady state heat transfer, to dynamic finite difference methods. The more complex the model, the more information required to represent the building being simulated. Transfers between BIM software and BEM tools have often focussed on a single aspect of performance modelling, such as HVAC systems (O’Sullivan and Keane, 2005) or envelope geometry (Verstraeten et al., 2008), with a comprehensive transfer of the sum total of performance impacting information is yet to be realised (System). Direct exchange of data between BIM and BEM design tools remains unattainable (Hitchcock and Wong, 2011; Sanguinetti et al., 2012) (System).

It is therefore justifiable to identify the high-level parameters required for BEM that could be stored in a BIM for use at a later date, but indicating the scope for information storage and re-use in this area. These parameters are outlined in Table III and represent the range of data to be input into the BIM at each LOD before the next stage in design can occur; resulting in a comprehensive model describing a buildings predicted energy performance assembled throughout the design process.

Mapping these information requirements at each developmental stage, a framework for modelling BEM in BIM has been created, linking the LOD to points at which design progress encounters a major exchange between stakeholders. Figure 5 denotes this process, which will be tested in the development of a real project designing a university lecture space and laboratory building.

4.5 Application to real projects

The projects in which the exchange of information between BIM and BEM along the defined framework is applied are a university lecture space and laboratory building, a multi-function university teaching space and a mixed-use residential apartment block (all of which reside in the North of the UK). All buildings had their own unique performance criteria to be targeted; however, the methodology used as described here to apportion the relevant information at each distinct stage of development remained the same. Each project was at the early concept design stage upon application of the framework in Figure 5, where project documentation was at LOD 200. At this stage, preliminary designs had been completed, determining aspects such as required space characteristics, building geometry and the creation of a baseline performance model. The buildings conditioning systems were yet to be defined; however, indicative conditions were specified. Each project had different development teams and external designers, meaning the specification for model development was different throughout. Within this, the method used to exchange information between BEM and BIM was adjusted to adhere to the requirements of that particular project (system, process).

The BIM models developed for each project used generic objects to represent equipment, populated with key performance characteristics to be represented in the BEM. The model built originally by the architects and later used by other disciplines (mechanical engineers for systems coordination) was used as the basis upon which data was attributed. This enabled basic templates to be used that were pre-set with existing components describing performance that could be adjusted by the building physicist for individual building characteristics. At the schematic design stage, information developed by the mechanical engineers was input into RDS (as defined in LOD 300 Table III) and automatically included in the BIM using a Dynamo script reading these sheets and updating fixed parameters within the BIM environment with updated values. In some cases, information was not suitable for attribution using this method, relying instead on reference to locations in the project filing system (skill) separate to the BIM reference model for use by the energy modellers, without a direct method of accessing this data.

One such example of this information is time-series data comprising half-hourly space performance characteristics used to size equipment for detailed design. At most, current BIM tools provide fields for single value descriptors without consideration of change over time (Gerrish et al., 2015) (System). A value range was used in place of the full record of values in the BIM, with reference to external datasets containing all data for investigation by the BEM specialist.

LOD 300 establishes the intended thermal characteristics of the building, including its materials specifications and construction quality. These characteristics are stored as object metadata attached to materials in the BIM. As previous attempts of exchanging data between the BIM and BEM using open exchange formats had failed (Figure 1), on the university teaching facilities project the performance characteristics were extracted to the RDS for manual recreation in the BEM (skill, process). At this point, regulatory compliance is assessed prior to reaching Data Drop 3 (Figure 5). Compliance checking of building performance is currently available in BIM tools, but these do not fully address all aspects required to definitively state whether a building will achieve a specific standard (Greenwood et al., 2010) (System).

The HVAC schematic at the detailed design stage is created by engineers based on the requirements of the building defined by the BEM (and obtained via the RDS link with the BIM environment). From these, a schematic of services is created outside BIM (due to issues modelling such detail, and the familiarity of those designers with BIM as a mechanical services modelling tool) (skill). Modelling stops after checking these servicing layouts for their provision of conditioning capacity; however, this was completed separate from the BIM with data from the RDS informing system interoperation.

Use of BIM as storage for the sum total information describing each projects provided a benefit in the following stages of design development, as an export of all relevant information at each major handover was made available through a simple Dynamo-based export of project information from the BIM, containing all information required at these stages. This was then used during later development and where requests for information came in when a version of the BIM authoring tool may have changed and access to that information was then made more difficult (Process). Following Data Drop 3 (LOD 350), simulated performance data is used to minimise energy consumption during use. At this stage, operational strategies are finalised for input into the operations and maintenance (O&M) manuals (Process) ready for handover to building operators. A potential benefit of keeping descriptive information in a format other than the BIM native format is data accessibility to those without the necessary BIM tools (System), nor the possibility of data being lost through export to an incomplete exchange format (Process).

5. Discussion

The application of the framework for information storage, sharing and access was intended to test whether BIM could be used to improve information accessibility for BEM. The process of determining a building’s theoretical performance using pre-construction information was defined and modified to include its generation within a BIM environment. In the following discussion, the issues encountered during application of this framework, and challenges to be overcome in reaching a more integrated BIM and BEM design process are presented.

5.1 Systems-based issues

5.1.1 Dis-integrated information

Information storage capabilities of BIM tools currently restrict the inclusion of large time-series performance datasets produced by BEM simulations. While summary of this data in a BIM environment is possible, information is derived from simplifications rather than the original data resulting in silos of unlinked information.

Until a whole building-modelling suite including all aspects of performance evaluation exists, methods of sharing information between parallel but non-integrated development platforms will continue to be developed (Bazjanac, 2008; Hitchcock and Wong, 2011; Kim et al., 2012; O’Sullivan and Keane, 2005) prior to open interoperability and widespread adoption by modelling software providers. Changes in processes used and skills held by those using the systems are required to facilitate both the development and adoption of these tools.

5.1.2 Information exchange

In linking data between BIM and non-BIM systems, systemic challenges exist in enabling data exchange through suitable formats. Prior to process change, identification of what information should be available must be addressed (e.g. the key performance descriptors of a piece of mechanical equipment). Attribution of parameters to objects in a BIM enables information to be stored adjacent to a representation of that object and its constituent system. Within the IFC and gbXML schemas there is potential for such information to be stored and exported between modelling platforms; however, this information is not made available by the tools exporting to the open exchange formats. For example, BEM tools typically only manage a single aspect of performance extracted from a BIM environment. Eastman et al. (2011, p. 168) suggest a suite of tools will emerge where information in a BIM can be checked and prepared for extraction into analysis tools without the lengthy and complicated process of manually extracting, checking and re-inputting information for simulation.

5.1.3 Information access

Post-construction, the information generated during design must be accessible to provide a rich source of O&M data, assisting the building operators in the ongoing management of the building. If all information is to be stored in a BIM environment, then some means of extracting it upon design completion is necessary. Use of BIM authoring tools to do so is costly for building operators who would need to purchase software and invest in training to extract relevant information. Instead this information is handed over upon completion in some agreed upon format, for input into another system or as simple indexed folders of documents, spreadsheets and drawings, limiting the opportunity for data to be used later in the buildings life-cycle.

5.2 Skills-based issues

5.2.1 Modelling to suit multiple purposes

Creation of a model suitable for the attribution of parametric object data is essential to support use of that model across disciplines, without risk of data loss through incorrect interpretation of the embedded information. Noted during this framework application was the need to partially remodel the supplied architectural models to suit attribution of building services layouts, structural elements and storage of space-related performance data. Commonly, the quality of the supplied model was insufficient to support automation of some design aspects, most likely a result of human error in the original modelling process (Safin et al., 2008) (inaccurate space bounding), and most of these were present as a result of human error.

5.2.2 Querying a CDE

Information stored in a model is used by those accessing that model at a later stage who must have the necessary skills to access this information. Due to the distinct differences between the fields of BIM and BEM (often with different teams working separately from each other), the skills required to model in BIM authoring tools such as Revit or ArchiCAD are significantly different to the skills required for modelling in BEM tools such as EnergyPlus or IES-VE. The BEM specialist must know where to look within the BIM for the information they need, requiring them to be familiar with BIM tools and the location of the data pertinent to their utilisation (Gu et al., 2009).

In the example project, all BEM stakeholders had issues in familiarising themselves with the BIM authoring tools for extraction of relevant embedded data (such as zoned air supply, location and distribution of services and equipment networks and material thermophysical properties); however, through use of the more familiar spreadsheet-based RDS these issues were overcome.

5.3 Process-based issues

5.3.1 Use of incorrect information

Linking the BEM development process to data drops (BIM Task Group, 2012) enabled the amount of information required at these stages to be defined. Through including BEM criteria such as equipment performance requirements within these data drops, this information was more likely to be used and kept up-to-date during design development, reducing the potential for use of inaccurate information. The LOD concept seems to include definitive information more relevant to design progression and performance improvement. While building users are beginning to demand asset registers (Love et al., 2014), it is also beneficial to know about the systems in place and how best to use them to improve energy performance. Through utilising the full parametric information storage capabilities of BIM software, a data trail can be followed to indicate where problems occur in design development (Nassar, 2010), and the decisions made during this process to result in the specification of the system being evaluated. This could allow more effective fault rectification, and feedback into later designs to avoid future issues.

5.3.2 Duplication of effort

Segregation of modelling using different tools and information standards requires some form of open exchange format; however, some tools do not support export of relevant data, nor interpretation of data in an accurate manner. As such, information may be duplicated which adds further intricacy to the already complex process, potentially confusing what information has been generated already, whether the most up-to-date version of information is being used to further overall design, and increasing unnecessary rework (Anumba et al., 2008).

5.3.3 Information accuracy and reference

The term “single source of truth” has been used in reference to BIM, mainly in terms of its use in design (as exemplified in this research); however, there may be benefits in the resolution of disputes and information requests later in the design and building lifetime. A snapshot of a design stage is possible given the capacities of BIM tools to store various versions of the same model at different points in time. Checking the indicative performance against actual performance may become more widespread with the impending implementation of performance-based contracts (Department of Energy and Climate Change, 2015).

6. Conclusions

In this study we presented a process map for exchanging information between building designers and BEM practitioners highlighting the extents of information required at key stages throughout the construction design process. The process of design of a buildings energy performance, and its design using BIM as the method of information storage throughout was followed, identifying the current barriers to integration of these two modelling platforms.

The range of sources available for implementing process planning and information monitoring systems in building design development offer comprehensive instruction in how to manage the building information throughout design and use. Examples include the RIBA (2013) Plan of Works and PAS 1192 (BSI, 2013), but none outline the management of energy performance information, which changes as a buildings design progresses. The framework outlined here evaluated how information pertaining to the evolution of a buildings energy performance design is stored, exchanged and accessed to ascertain the issues currently preventing effective use of BIM as a means to achieve coordination across disciplines in this process.

The specific data stored within a BIM environment required by BEM for the purposes of informing building design at particular stages of that design progression has been defined with the following recommendations made for future efforts moving towards an integrated cross-discipline design environment:

  • Open exchange formats are not currently viable for a large proportion of information exchange purposes. As a result, proprietary formats are specified for exchange in real projects to avoid potential errors.

  • Use of conventional methods of data transfer (spreadsheets) remain due to user familiarity with these processes. Training is required by all those utilising information stored within a BIM environment, if only to provide knowledge of how information is accessed to support their activities downstream.

  • Up-to-date information describing a building design creates a more accurate representation of that building. This information can be stored in a BIM environment, but responsibility for the update of this information is essential to ensure it is accurate and usable.

  • BIM execution plans fail to account for those working outside the current BIM environment. Information generated here is not commonly specified for inclusion in the BIM, and until it is the model remains a mere 3D representation of 2D geometry with no metadata usable in later versions of that model.

  • Processes used to access and update information in a CDE should be supported by both the tools being used to achieve this, and user skill in interacting with these tools. Without both, using BIM to support any “non-BIM” design tool will not be feasible.

Industry practitioners managing the design development of building require an understanding of how that design progresses, and the means of sharing information in an efficient and accurate manner. Use of a framework such as that suggested here could assist designers to include information in their models that can then be used to understand a buildings operational performance, and provide a definitive source of information that can be referenced by all members of the design team.

Future research in the attribution of in-use building performance data into the CDE for the management of a buildings performance in both design and use can use these findings to focus work in the areas requiring most development.

Figures

Loss of data integrity/accuracy through export via open exchange formats

Figure 1

Loss of data integrity/accuracy through export via open exchange formats

Data loss from file creation and interpretation

Figure 2

Data loss from file creation and interpretation

Energy performance modelling stakeholder information exchange and development process

Figure 3

Energy performance modelling stakeholder information exchange and development process

BIM/BEM information exchange process without open exchange formats

Figure 4

BIM/BEM information exchange process without open exchange formats

High-level process map showing decision gates and stages for information extents assessment

Figure 5

High-level process map showing decision gates and stages for information extents assessment

BIM-integrated energy assessment/design studies

Author/s Technical barriers
Leicht and Messner (2007) User error
Information extent not defined
Work duplication in transition between traditional and BIM systems
Azhar et al. (2009) Value/cost prioritised over building performance
Energy assessment not completed between detailed specification and build completion
Schlueter and Thesseling (2009) External parameter storage easier than use of a BIM environment
Hjelseth (2010) Information not considered an asset and therefore not requested
Little guidance available for information relevance
Input information only benefits the receiver, not the producer
Aksamija et al. (2011) Significant software customisation required
Multi-stepped processes susceptible to user error
Corry et al. (2011) Design intent lost post-completion and commissioning
Welle et al. (2011) Long model preparation times
Inaccurate and inconsistent data conversion
Missing data
Inconsistent analysis results (metrics, coordination)
Sanguinetti et al. (2012) Separation of building models and analysis model during design
Data access restricted by storage format
Aziz et al. (2012) Changes in design resulting in incorrect representative models
Sinha et al. (2013) Current energy analysis plug-ins within BIM software based on simplified consumption estimation
No current definition of embedded BEM parameters within a BIM environment
Costa et al. (2013) IFC exchange format is the “lowest common denominator” limiting functionality

Basic information typologies supporting BEM and simulation

Relevant data Description
Location The climate in which the building is located
Spatial geometry The form of the building (including orientation)
Space definitions Layout of the usable spaces within the building
Materials properties Properties describing thermal performance of fabric (including doors, windows, floors, ceiling, roofs and walls)
Space utilisation Function of space (describing the likely internal occupant, lighting and equipment gains with operating schedules)
Servicing characteristics Operating methodology (heating, cooling and ventilation systems)

Level of development for BEM parameters during building design

Design stage Level of development Key parameters
Early concept design LOD100 – elements represented in model symbolically (no geometric information) Location (climate, surroundings)
Basic thermal zones
Generic fabric type
Generic thermal profile (occupancy, lighting, equipment)
Generic conditions (temperature)
Late concept design LOD200 – elements in model represented graphically as generic system with geometries indicated Spatial geometry (subject to change)
Fabric composition
Occupancy, lighting and equipment levels
Method of servicing (heating/cooling/ventilation)
Early detailed design LOD300 – elements represent specific systems with defined location with parametric information included Fixed spatial geometry
Detailed fabric composition (thermophysical characteristics, thermal bridging, infiltration rates)
Detailed internal gains schedules
Servicing schedules
Late detailed design LOD350 – element interfaces with other systems included Local servicing optimisation
Change in-use provision
Whole building system optimisation
Construction LOD400 – fabrication and operation information stored within/alongside element As-built specifications (geometry, fabric, equipment)
Operation and maintenance methods
In-use LOD500 – all information regarding installed elements is included ready for use by Facilities Manager External environment records
Operations and maintenance records

References

Aksamija, A., Guttman, M., Rangarajan, H.P. and Meador, T. (2011), “Parametric control of BIM elements for sustainable design in Revit”, Perkins+Will Research Journal, Vol. 3 No. 1, pp. 32-45.

American Institute of Architects (2012), “An architect’s guide to integrating energy modeling in the design process”, available at: www.aia.org/resources/8056-architects-guide-to-integrating-energy-modeli (accessed 14 June 2013).

American Institute of Architects (AIA) and Associated General Contractors (AGC) of America (2013), “Level of development specification”, BIMForum, available at: http://bimforum.org/lod/ (accessed 21 February 2017).

Anumba, C.J., Pan, J., Issa, R.R.A. and Mutis, I. (2008), “Collaborative project information management in a semantic web environment”, Engineering, Construction and Architectural Management, Vol. 15 No. 1, pp. 78-94, doi: 10.1108/09699980810842089.

Aouad, G., Hinks, J., Cooper, R., Sheat, D., Kagioglou, M. and Sexton, M. (1998), “An IT map for a generic design and construction process protocol”, Journal of Construction Procurement, Vol. 4 No. 1, pp. 132-151.

Arayici, Y., Coates, P., Koskela, L., Kagioglou, M., Usher, C. and O’Reilly, K. (2011), “Technology adoption in the BIM implementation for lean architectural practice”, Automation in Construction, Vol. 20 No. 2, pp. 189-195, doi: 10.1016/j.autcon.2010.09.016.

Attia, S., Anders, M. and Walter, E. (2013), “Identifying and modeling the integrated design process of Net Zero Energy Buildings”, presented at the High Performance Buildings: Design and Evaluation Methodologies, European Commission: Joint Research Centre, Brussels, 24-26 June.

Autodesk (2016), “Dynamo (online document), DynamoBIM”, available at: http://dynamobim.org/ (accessed 19 January 2016).

Azhar, S., Brown, J. and Farooqui, R. (2009), “BIM-based sustainability analysis: an evaluation of building performance analysis software”, presented at the 45th ASC Annual Conference, Associated Schools of Construction, Gainesville, FL, 4-7 November.

Aziz, Z., Arayici, Y. and Shivachev, D. (2012), “Building energy performance analysis of an academic building using IFC BIM-based methodology”, presented at the International Conference for Enhanced Building Operations, Manchester, 23-26 October.

Bakens, W., Foliente, G. and Jasuja, M. (2005), “Engaging stakeholders in performance-based building: lessons from the performance-based building (PeBBu) network”, Building Research and Information, Vol. 33 No. 2, pp. 149-158, doi: 10.1080/0961321042000322609.

Bazjanac, V. (2008), “IFC BIM-based methodology for semi-automated building energy performance simulation”, presented at the CIB W78, Santiago, 15-17 July.

Bazjanac, V. and Kiviniemi, A. (2007), “Reduction, simplification, translation and interpretation in the exchange of model data”, presented at the CIB W78, Maribor, 26-29 June, pp. 163-168.

BIM Task Group (2011), “A report for the government construction client group building information modelling (BIM) working party strategy paper”, Department of Business, Innovation and Skills, London.

BIM Task Group (2012), “COBie data drops”, BIM Task Group, available at: www.bimtaskgroup.org/wp-content/uploads/2012/03/COBie-data-drops-29.03.12.pdf (accessed 4 April 2013).

Bordass, B., Cohen, R. and Field, J. (2004), “Energy performance of non-domestic buildings – closing the credibility gap”, presented at the Building Performance Congress, IBPSA, Frankfurt, 19-22 April.

BSI (2007), BS 1192-2007: collaborative production of architectural, engineering and construction information. Code of practice, British Standards Institution.

BSI (2013), PAS 1192-2:2016 specification for information management for the capital/delivery phase of construction projects using building information modelling, British Standards Institution.

Chen, L. and Luo, H. (2014), “A BIM-based construction quality management model and its applications”, Automation in Construction, Vol. 46, pp. 64-73, doi: 10.1016/j.autcon.2014.05.009.

Clarke, J.A. (2001), Energy Simulation in Building Design, 2nd ed., Butterworth-Heinemann, Oxford.

Corry, E., Keane, M., O’Donnell, J. and Costa, A. (2011), “Systematic development of an operational BIM utilising simulation and performance data in building operation”, presented at the Building Simulation, IBPSA, Sydney, pp. 1422-1429.

Costa, A., Keane, M.M., Torrens, J.I. and Corry, E. (2013), “Building operation and energy performance: monitoring, analysis and optimisation toolkit”, Applied Energy, Vol. 101, pp. 310-316, doi: 10.1016/j.apenergy.2011.10.037.

Department of Energy and Climate Change (2015), “Guide to energy performance contracting best practices”, Department of Energy & Climate Change, available at: www.gov.uk/government/uploads/system/uploads/attachment_data/file/395076/guide_to_energy_performance_contracting_best_practices.pdf (accessed 21 February 2017).

Eastman, C., Teicholz, P., Sacks, R. and Liston, K. (2011), BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors, 2nd ed., John Wiley and Sons, Hoboken, NJ.

Essig, N. (2010), “Open house – instrument for assessing the sustainability performance of buildings in Europe”, presented at the Central Europe towards Sustainable Building (CESB10), Faculty of Civil Engineering CTU, Prague.

Gelder, J. (2012), “Integrated. Dis-integrated. Coordinated. Re-integrated”, Architectural Research Quarterly, Vol. 16 No. 3, pp. 253-260, doi: 10.1017/S1359135513000109.

Gerrish, T., Ruikar, K., Cook, M.J., Johnson, M. and Phillip, M. (2015), “Attributing in-use building performance data to an as-built building information model for lifecycle building performance management”, presented at the CIB W78, CIB, Eindhoven, 27-29 October.

Greenwood, D., Lockley, S., Malsane, S. and Matthews, J. (2010), “Automated compliance checking using building information models”, presented at the RICS COBRA 2010, RICS, Paris, 2-3 September.

Grinberg, M.R. and Rendek, A. (2013), “Architecture, cartography and energy: mapping the way we share information to build better buildings”, ASHRAE Transactions, Vol. 119 No. 2, pp. 1-8.

Gu, N. et al. (2009), “Handbook of research on building information modeling and construction informatics: concepts and technologies”, in Underwood, J. and Iskidag, U. (Eds), BIM Aadoption: Expectations across Disciplines, ISI Global, pp. 501-520.

He, B., Ye, M., Yang, L., Fu, X.-P., Mou, B. and Griffy-Brown, C. (2014), “The combination of digital technology and architectural design to develop a process for enhancing energy-saving: the case of Maanshan China”, Technology in Society, Vol. 39 No. 4, pp. 77-87, doi: 10.1016/j.techsoc.2014.10.002.

Hicks, B.J. (2007), “Lean information management: understanding and eliminating waste”, International Journal of Information Management, Vol. 27, pp. 233-249, doi: 10.1016/j.ijinfomgt.2006.12.001.

Hitchcock, R.J. and Wong, J. (2011), “Transforming IFC architectural view BIMs for energy simulation: 2011”, Presented at the 12th Conference of International Building Performance Simulation Association, Sydney, pp. 1089-1095.

Hjelseth, E. (2010), “Exchange of relevant information in BIM objects defined by the role- and life-cycle information model”, Architectural Engineering and Design Management, Vol. 6 No. 4, pp. 279-287, doi: 10.3763/aedm.2010.IDDS5.

Hughes, W. and Murdoch, J.R. (2001), Roles in Construction Projects: Analysis and Terminology, Construction Industry Publications Limited, Birmingham.

Hwang, B.-G., Thomas, S.R., Haas, C.T. and Caldas, C.H. (2009), “Measuring the impact of rework on construction cost performance”, Journal of Construction Engineering and Management, Vol. 135 No. 3, pp. 187-198.

Intelligent Energy Europe (2007), “Mapping of previous integrated energy approaches: description of previous integrated energy approaches from around the world EIE-06-021-INTEND”, Intelligent Energy Europe, available at: www.intendesign.com/oslo/Intend.nsf//FA3C2A500C743202C12573F0005467B7/$FILE/Mapping+Existing+Tools.pdf (accessed 14 August 2013).

Kim, I., Kim, J. and Seo, J. (2012), “Development of an IFC-based IDF converter for supporting energy performance assessment in the early design phase”, Journal of Asian Architecture and Building Engineering, Vol. 11 No. 2, pp. 313-320.

Krygiel, E. and Nies, B. (2008), Green BIM: Successful Sustainable Design with Building Information Modeling, Wiley Publishing, Indianapolis, IN.

Laakso, M. and Kiviniemi, A. (2012), “The IFC standard – a review of history, development, and standardization”, Journal of Information Technology in Construction, Vol. 17, pp. 134-161.

Leicht, R.M. and Messner, J.I. (2007), “Comparing traditional schematic design documentation to a schematic building information model”, presented at the CIB W78, CIB, Maribor, 26-29 June, pp. 39-46.

Love, P.E.D., Edwards, D.J., Han, S. and Goh, Y.M. (2011), “A benefits realization management building information modeling framework for asset owners”, Automation in Construction, Vol. 37, pp. 1-10, doi: 10.1016/j.autcon.2013.09.007.

Love, P.E.D., Matthews, J., Simpson, I., Hill, A. and Olatunji, O.A. (2014), “Design error reduction: toward the effective utilization of building information modeling”, Research in Engineering Design, Vol. 22 No. 3, pp. 173-187, doi: 10.1007/s00163-011-0105-x.

McGraw Hill Construction (2010), “Green BIM: how building information modeling is contributing to green design and construction (SmartMarket report)”, Bedford, MA.

Menezes, A.C., Cripps, A., Bouchlaghem, D. and Buswell, R. (2012), “Predicted vs actual energy performance of non-domestic buildings: using post-occupancy evaluation data to reduce the performance gap”, Applied Energy, Vol. 97, pp. 355-364, doi: 10.1016/j.apenergy.2011.11.075.

Merschbrock, C. (2012), “Experiences of EDM usage in construction projects”, Journal of Information Technology in Construction, Vol. 17, pp. 333-350.

Morrissey, E., Keane, M. and Bazjanac, V. (2004), “Specification and implementation of an IFC based performance metrics to support building life cycle assessment of hybrid energy systems”, presented at the SimBuild, IBPSA, Boulder, pp. 4-6.

Nassar, K. (2010), “The effect of building information modeling on the accuracy of estimates”, presented at the Associated Schools of Construction 46th Annual Conference, Boston, MA, 7-10 April.

O’Sullivan, B. and Keane, M. (2005), “Specification of an IFC based intelligent graphical user interface to support building energy simulation”, Proceedings of the Ninth International IBPSA Conference, pp. 15-18.

Olander, S. and Landin, A. (2005), “Evaluation of stakeholder influence in the implementation of construction projects”, International Journal of Project Management, Vol. 23 No. 4, pp. 321-328, doi: 10.1016/j.ijproman.2005.02.002.

Prívara, S., Váňa, Z., Žáčeková, E. and Cigler, J. (2012), “Building modeling: selection of the most appropriate model for predictive control”, Energy and Buildings, Vol. 55, pp. 341-350, doi: 10.1016/j.enbuild.2012.08.040.

Redmond, A., Hore, A., Alshawi, M. and West, R. (2012), “Exploring how information exchanges can be enhanced through Cloud BIM”, Automation in Construction, Vol. 24, pp. 175-183, doi: 10.1016/j.autcon.2012.02.003.

RIBA (2012), BIM Overlay to the RIBA Outline Plan of Work, RIBA Publishing, London, available at: www.ribabookshops.com/uploads/b1e09aa7-c021-e684-a548-b3091db16d03.pdf (accessed 2 August 2013).

RIBA (2013), RIBA Plan of Work 2013 Overview, RIBA, London.

Ryan, E.M. and Sanquist, T.F. (2012), “Validation of building energy modeling tools under idealized and realistic conditions”, Energy and Buildings, Vol. 47, pp. 375-382, doi: 10.1016/j.enbuild.2011.12.020.

Sacks, R., Eastman, C., Lee, G. and Orndorff, D. (2005), “A target benchmark of the impact of three-dimensional parametric modeling in precast construction”, PCI Journal, July-August, pp. 126-139.

Safin, S., Leclercq, P. and Blavier, A. (2008), “Errors in architectural design process: towards a cognitive model”, Presented at the Design: 10th International Design Conference, University of Zagreb, Dubrovnik, pp. 1057-1067.

Sanguinetti, P., Abdelmohsen, S., Lee, J., Lee, J., Sheward, H. and Eastman, C. (2012), “General system architecture for BIM: an integrated approach for design and analysis”, Advanced Engineering Informatics, Vol. 26 No. 2, pp. 317-333, doi: 10.1016/j.aei.2011.12.001.

Schlueter, A. and Thesseling, F. (2009), “Building information model based energy/exergy performance assessment in early design stages”, Automation in Construction, Vol. 18 No. 2, pp. 153-163, doi: 10.1016/j.autcon.2008.07.003.

Sinha, S., Sawhney, A., Borrmann, A. and Ritter, F. (2013), “Extracting information from building information models for energy code compliance of building envelope”, presented at the RICS COBRA, RICS, New Delhi.

Tammik, J. (2011), “CP4451: extensible storage in the Revit 2012 API”, Autodesk University, available at: www.aucache.autodesk.com/au2011/sessions/4451/.../v1_CP4451_tammik_estorage.pptx (accessed 3 December 2014).

Titus, S. and Bröchner, J. (2004), “Managing information flow in construction supply chains”, Construction Innovation: Information, Process, Management, Vol. 5 No. 2, pp. 71-82.

Tribelsky, E. and Sacks, R. (2010), “Measuring information flow in the detailed design of construction projects”, Research in Engineering Design, Vol. 21 No. 3, pp. 189-206, doi: 10.1007/s00163-009-0084-3.

Tupper, K. and Fluhrer, C. (2010), “Energy modeling at each design phase: strategies to minimize design energy use”, presented at SimBuild, IBPSA, New York, NY.

Verstraeten, R., Pauwels, P., De Meyer, R., Meeus, W., Van Campenhout, J. and Lateur, G. (2008), “IFC-based calculation of the flemish energy performance standard”, presented at the 7th European Conference on Product and Process Modelling, CRC Press, Sophia-Antipolis, pp. 437-443.

Way, M., Bordass, B., Leaman, A. and Bunn, R. (2009), “The soft landings framework: for better briefing, design, handover and building performance in-use. Framework BG 4/2009”, BSRIA.

Welle, B. and See, R. (2011), “Information Delivery Manual (IDM) for design to building energy analysis, version 1”, BLIS Project, available at: www.blis-project.org/IAI-MVD/IDM/GSA-001/PM_GSA-001.pdf (accessed 21 September 2013).

Welle, B., Haymaker, J. and Rogers, Z. (2011), “ThermalOpt: a methodology for automated bim-based multidisciplinary thermal simulation for use in optimization environments”, CIFE Technical Report TR200, Center for Integrated Facility Engineering, Stanford, CA.

Yeomans, S., Bouchlaghem, D. and El-Hamalawi, A. (2005), “Collaborative extranet working via multiple construction project extranets”, Presented at the 3rd International Conference on Innovation in Architecture, Engineering and Construction, Nottingham Trent University, Rotterdam, pp. 211-222.

Acknowledgements

This research was funded by the EPSRC and sponsors BuroHappold Engineering. Materials used may be subject to non-disclosure agreements and can be requested by contacting the corresponding author.

Corresponding author

Tristan Gerrish can be contacted at: t.gerrish@lboro.ac.uk

Related articles