Ripple effect of disruptions on performance in supply chains: an empirical study

An Thi Binh Duong (CIRTech Institute, HUTECH University, Ho Chi Minh City, Viet Nam)
Tho Pham (Faculty of Business Administration, Tokyo Keizai University, Tokyo, Japan)
Huy Truong Quang (The Business School, RMIT International University, Ho Chi Minh City, Viet Nam)
Thinh Gia Hoang (The Business School, RMIT International University, Ho Chi Minh City, Viet Nam) (Institute of Business Research, University of Economics Ho Chi Minh City, Ho Chi Minh City, Viet Nam)
Scott McDonald (The Business School, RMIT International University, Ho Chi Minh City, Viet Nam)
Thu-Hang Hoang (School of International Business – Marketing, University of Economics Ho Chi Minh City, Ho Chi Minh City, Viet Nam)
Hai Thanh Pham (Faculty of Business Administration, Van Lang University, Ho Chi Minh City, Viet Nam)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 10 April 2023

2652

Abstract

Purpose

The present study is performed to identify the propagation mechanism of the ripple effect as well as examine the simultaneous impact of risks on supply chain (SC) performance.

Design/methodology/approach

A theoretical framework with many hypotheses regarding the relationships between SC risk types and performance is established. The data are collected from a large-scale survey supported by a project of the Japanese government to promote sustainable socioeconomic development for the Association of Southeast Asian Nations (ASEAN) region, with the participation of 207 firms. Structural equation modeling (SEM) is used to test the hypotheses of the theoretical framework.

Findings

It is indicated that human-made risk causes operational risk, while natural risk causes both supply risk and operational risk. Furthermore, the impacts of human-made risk and natural risk on performance are amplified through operational risk.

Research limitations/implications

This study is one of the first attempts that identifies the propagation mechanism of the ripple effect and examines the simultaneous impact of risks on performance in construction SCs.

Originality/value

Although many studies on risk management in construction SCs have been carried out, they mainly focus on risk identification or quantification of risk impact. It is observed that research on the ripple effect of disruptions has been very scarce.

Keywords

Citation

Duong, A.T.B., Pham, T., Truong Quang, H., Hoang, T.G., McDonald, S., Hoang, T.-H. and Pham, H.T. (2024), "Ripple effect of disruptions on performance in supply chains: an empirical study", Engineering, Construction and Architectural Management, Vol. 31 No. 13, pp. 1-22. https://doi.org/10.1108/ECAM-10-2022-0924

Publisher

:

Emerald Publishing Limited

Copyright © 2023, An Thi Binh Duong, Tho Pham, Huy Truong Quang, Thinh Gia Hoang, Scott McDonald, Thu-Hang Hoang and Hai Thanh Pham

License

Published by Emerald Publishing Limited. This article is published under the Creative Commons Attribution (CC BY 4.0) licence. Anyone may reproduce, distribute, translate and create derivative works of this article (for both commercial and non-commercial purposes), subject to full attribution to the original publication and authors. The full terms of this licence may be seen at http://creativecommons.org/licences/by/4.0/legalcode


1. Introduction

Due to distinctive peculiarities, the construction industry often lags behind other industries in terms of performance, productivity and efficiency (Costa et al., 2019). Construction projects are always characterized by short-term relationships, rapidly changing environments, inherent complexities, time and cost overruns, and interruptions due to unforeseen conditions (Koc and Gurgun, 2021). These characteristics lead to the existence of risks in construction projects (Dikmen et al., 2018). All projects always have a certain degree of uncertainty and risk, and construction projects are also not an exception (Pham et al., 2022). Goh et al. (2013) conclude that risks are unavoidable during the progress of construction projects. Interruptions in any phase of the SC could cause extreme losses (Niu et al., 2017). According to Koushki and Kartam (2004), approximately a quarter of project delays are associated with the late delivery of construction materials. Hence, efficient risk management in construction SCs is essential for increasing work efficiency, reducing environmental impacts and adding values for all partners (Aloini et al., 2012). The development of a SC risk management plan has become more critical for construction firms in complex projects today to increase their presence and competitiveness in this industry (Koc and Gurgun, 2021).

In recent years, many studies on risks in construction SCs have been carried out, for example, Naderpajouh et al. (2015), Rudolf and Spinler (2018), Panova and Hilletofth (2018), Shojaei and Haeri (2019), Zhao (2019), Abas et al. (2022), Obayi and Ebrahimi (2021), Ekanayake et al. (2021a), and Ekanayake et al. (2022). These studies highlight the challenges (e.g. maintaining operations and improving performance) that construction firms have to face regarding the propagation of disruption. However, the above studies have not identified the propagation mechanism of the ripple effect as well as examined the simultaneous impact of all risk types on performance. The occurrence of some risks (e.g. late delivery from suppliers) may lead to shortage of inventory and delay of construction schedule, and then it may seriously impact the operations process of construction firms. In the same vein, Zheng et al. (2021) concluded it is vital to investigate the risk propagation because it may affect the planning, inventory and production schedule which are not directly at risk in some periods. This study is conducted to fill these gaps in the literature. Dolgui and Ivanov (2021) posit that one or more disruptions can propagate throughout the SC and have impacts on performance, hence the emphasis is increasingly placed on the ripple effect. Ripple effect is a specific topic in SCM and a strong stressor to SC resilience. The ripple effect is defined as disruption propagation of an initial disruption toward other SC stages namely supply, production and distribution. In this situation, the occurrence of a disruption risk (e.g. terrorism and war, political instability, epidemics and natural catastrophes) can cause the occurrence of internal risks (e.g. supply risk, operational risk and demand risk). In other words, the ripple effect occurs when a disruption risk, rather than being contained in one SC part, cascades downstream and affects the entire SC performance (Dolgui et al., 2018).

The propagating impacts of a disruption make local disruptions unpredictable, thus it is hard for managing them. Traditional SC risk management begins with risk identification and ends with various strategies to reduce the impacts of identified risks (Craighead et al., 2007). This approach is only effective in dealing with anticipated disruptions, but less effective in dealing with unexpected disruptions. It is vital for firms to develop resilience which allows them quickly respond to and recover from unexpected disruptions (Baghersad and Zobel, 2021). In this case, an understanding of the disruption propagation and how it impacts the whole SC can support various decision-making levels in terms of resilience investment. The whole SC performance is the integrated performance of individual firms inside that SC network, which can be measured by network health (i.e. the number of healthy firms at a specific time) (Li and Zobel, 2020). Thus, investigating how disruptions propagate throughout the SC network and affect the network health allows managers to optimally allocate resources, effectively manage disruption propagation and attain higher SC performance (Li et al., 2021). These arguments from the literature have highlighted the importance of studying the effects of disruption propagation on SC performance. This motivated us to carry out the present study.

In summary, the two specific objectives of the present study include: (1) Identifying the propagation mechanism of the ripple effect in construction SCs and (2) examining the simultaneous impact of SC risks on performance. This study is carried out through two steps. At the first step, SC risks are identified and then, the ripple effect between them is defined. In the second step, an empirical study is conducted with data collected from the construction industry in order to examine the propagation mechanism of the ripple effect.

2. Literature review

2.1 Gaps

Many works on risk management in construction SCs have been performed in recent years. For example, the aim of Naderpajouh et al. (2015) is to study governance of risks related to counterfeit, fraudulent and suspect items in SCs of construction projects, while Rudolf and Spinler (2018) present a prioritized and structured view on the SC risk portfolio in the construction industry. Moreover, the work of Panova and Hilletofth (2018) is aimed at investigating methods and models to manage SC risks and delays in construction projects. Shojaei and Haeri (2019) propose a comprehensive SC risk management approach for construction projects that applies fuzzy cognitive mapping, grounded theory and grey relational analysis. Zhao (2019) defines the risk interconnectivity, propagation density and risk propagation speed; and distinguishes infectious risks from conventional risks in mega project SCs. In addition, the study of Abas et al. (2022) is aimed at identifying critical risk and success factors that have effects on SC performance, whereas the study of Obayi and Ebrahimi (2021) aims to explore the role of external neo-institutional pressures in shaping the risk management strategies implemented to reduce transaction cost risks in construction SCs. It is observed the above studies still mainly focus on the identification and assessment of risks. Two gaps of knowledge emerged from the analysis of these studies. First, they have not identified the propagation mechanism of the ripple effect. Second, they have not assessed the simultaneous impact of all SC risks on performance. In most of real-life situations, firms often face not only a single risk, but also multiple risks (Wu et al., 2017). Various risks in a SC are linked in complex patterns in which the occurrence of one risk can lead to the occurrence of other risks (Song et al., 2017).

In this study, the ripple effect refers that the occurrence of external risks can cause the occurrence of internal risks. The ripple effect is an increase in the degree of impact each and all risks have on performance through the mutual interactions between risks. To the best of our knowledge, evidence for this kind of effect has not yet been found in the literature. As supported by Ho et al. (2015), further investigations on the interrelationships among different risks rather than standalone risks can support the process of SC risk management. Thus, the first contribution of our study is to identify the propagation mechanism of the ripple effect in construction SCs.

Identifying inherent SC risks is one of the main tasks of managers because it allows them to better understand risks and enhance the effectiveness of risk management (Lin and Zhou, 2011). From the perspective of SC managers, it is not easy to justify investments in risk reduction strategies if they are not directly associated with the payoff (Rajagopal et al., 2017). In order to promote best risk mitigation practices, the impacts of risk on performance need to be examined (Colicchia and Strozzi, 2012). Therefore, many studies in various industries have empirically investigated the relationships between SC risks and performance such as Zhao et al. (2013), Mishra et al. (2016), Wiengarten et al. (2016), Brusset and Teller (2017), Chen (2018), and Wang (2018). However, evidence for the simultaneous impact of all risk types on performance in construction SCs is still limited. This is also the second knowledge gap found in the literature; and this study attempts to fill this gap. Kumar et al. (2018) argue that SC risks have been widely explored by individual case studies or standalone models, while research on their simultaneous impacts (i.e. ripple effect of risks on performance) on performance through empirical research has been scarce. The assessment and treatment of a single risk in isolation is ineffective due to the interdependent nature of risks. Risks are propagated and exert a systemic effect on the SC network. The impact of risk propagation is reflected by some performance criteria such as quality, time and cost (Jayasinghe et al., 2022).

Research on the relationships between the ripple effect and performance has gained much attention from researchers in recent years. Ivanov et al. (2016) describe the ripple effect in general and one example of the ripple effect in the dairy SC, present a model for reactive recovery policies under conditions of the ripple effect and exemplify them on a simulation example. Hosseini and Ivanov (2022) theorize a new measure to quantify the resilience of an original equipment manufacturer with a multi-stage assessment of suppliers' proneness to disruptions and the SC exposure to the ripple effect. The contribution of Pavlov et al. (2019) lies in a conceptualization of a new methodical approach to the detection of disruption scenarios, ripple effect dispersal and recovery paths in SCs on the basis of structural genomes. In the study of Birkie and Trucco (2020), resilience capability has direct positive effect in mitigating disruptions when SC complexity is taken into account. Hosseini et al. (2020) construct a new model based on integration of Discrete-Time Markov Chain and a Dynamic Bayesian Network to quantify the ripple effect. Kinra et al. (2020) develop a new model to assess the ripple effect of a supplier disruption, based on possible maximum loss. Özçelik et al. (2021) examines the ripple effect on the system performance of the reverse SC network and introduces a robust optimization model for designing strong reverse SC networks to cope with the uncertainties caused by the ripple effect. Liu et al. (2021) propose a new robust Dynamic Bayesian network approach to analyze the worst-case oriented disruption propagation in the SC. Park et al. (2022) examines the ripple effect in SCs due to circular flows embedded in SC design. Ivanov (2022) performs a simulation analysis using anyLogistix digital SC twin to identify potential impacts of blackouts on SCs for scenarios of different severity. It is found that researchers have paid considerable attention to the optimization and modeling of the ripple effect, while research on the relationship between the ripple effect and performance with survey data is rather limited. Craighead and Meredith (2008) note that the use of empirical data (e.g. survey) can supplement modeling, simulation and mathematics for developing and testing theories. Many researchers (e.g. Scudder and Hill, 1998) have called for this type of empirical research since operations management became an established study field in the management discipline. Thus, our study attempts to empirically examine the impacts of risks on performance in SCs.

2.2 Risks in supply chains

Jüttner (2005) analyzed risks both in processes of a firm and in SC flows (e.g. information and products flows), and basically SC risks can be divided into two categories: internal risk and external risk (or disruption risk). In an empirical study with the participation of 67 German automotive firms, Thun and Hoenig (2011) demonstrated that there are significant differences between internal and external risks with regard to the impact on performance. Previous studies on construction SC risks have also classified risks into disruption and internal risks such as Pham et al. (2022).

Disruption risks (e.g. natural catastrophes, war and terrorism, epidemics, fire accidents, external legal issues, economic downturns, political instability, social and cultural grievances) always have a comprehensive effect on all activities in the SC network. Internal risks include three sub-categories: operational risk, supply risk and demand risk. These risks are daily issues that can directly affect the SC in various ways (Truong Quang and Hara, 2018). The current study conducted a review of the literature to identify all specific risks of sub-categories. Categories, sub-categories and risks are summarized in Table 1.

2.3 Supply chain performance

Kaplan and Norton (1992) argue the performance of a firm should be reflected by both short and long term measures, leading to the development of two indicators: lagging and leading ones. Lagging indicators describe what actually happened in the past such as financial variables while leading indicators give an early warning of what might happen in the future (e.g. human resource-oriented variables, customer-oriented variables). Financial measures always have a crucial role, yet in order to have a comprehensive performance scale, intangible and strategic-oriented measures need to be balanced with financial measures.

This study uses many aspects for measuring performance including finance, customer service, innovation and learning, internal business and supplier performance, as the inheritance from Kaplan and Norton (1992). Developed by Kaplan and Norton (1992), the Balanced Scorecard model recognizes the limitations of traditional firm performance measurement and then, translates the strategy of a firm into performance objectives, particularly focusing on intangible assets such as supplier and customer relationships, skills and knowledge levels of employees, value chain and innovation. This approach shifts the traditional focus on physical assets to emphasize both physical and intangible assets of a firm for long term development. The present study defines a set of performance measures based on the Balanced Scorecard model comprising five main dimensions: finance, customer service, innovation and learning, supplier performance and internal business.

3. Hypotheses development

3.1 The impacts of external risk on internal risk and supply chain performance

Risks such as natural catastrophes, war and terrorism, political and economical issues, social and cultural grievances, and epidemics are known as external risks (or disruption risks). These risks rarely appear but can strongly impact SC performance (Abdel-Basset and Mohamed, 2020; Moktadir et al., 2021; Rostamzadeh et al., 2018; Song et al., 2017; Wu et al., 2017; Xu et al., 2019). For example, Hansen et al. (2013) found that economic downturns changed financial results and market demand as well as created a difficult business environment, even breaking the supplier-buyer relationship. Furthermore, the existence of a large number of procedures causes delays and difficulties in transactions between members in the SC (Truong Quang and Hara, 2018).

In particular, the recent Covid-19 pandemic has gained great attention from practitioners and academics as a fatal health crisis (Contreras et al., 2021). Non-pharmaceutical measures have caused the supply and demand problems for SCs. Indeed, Barichello (2020) notes that social distancing has severely damaged the economic activities and financial instability. Members at the downstream side of the SC have greatly suffered due to demand-side shocks (e.g. panic buying, excessive inventory), even many companies have to stop operations. This pandemic also caused an economic shock with more than 170 countries having negative GDP per capita growth, as well as impacted exchange rates and monetary policies on the market.

H1a,b,c,d.

External risk causes supply risk, operational risk, and demand risk and adversely affects supply chain (SC) performance.

3.2 The impacts of supply risk and demand risk on operational risk and supply chain performance

Supply risk is related to adverse upstream activities in SCs that impact the ability of the focal firm in meeting customer demands (both in quality and quantity), causing threats to the customer's life and safety (Wagner and Bode, 2008). In this situation, the focal firm faces risks associated with the supply side, for example, unstable quantity and quality of inputs, price fluctuations and supplier bankruptcy (Abdel-Basset and Mohamed, 2020; Moktadir et al., 2021; Rostamzadeh et al., 2018). These risks cause failure in providing goods or services to the purchasing company and downstream operations of the SC (Truong and Hara, 2018). Therefore, the following hypotheses are proposed:

H2a,b.

Supply risk causes operational risk and adversely affects SC performance.

Demand risk is associated with adverse downstream events in the SC that affect the fulfillment of customers orders or variance in the volume desired by customers (Ho et al., 2015). This type of risk derives from uncertainties related to the customer side such as customer fragmentation, customer bankruptcy, high market competition and demand variability (Abdel-Basset and Mohamed, 2020; Moktadir et al., 2021; Rostamzadeh et al., 2018; Song et al., 2017; Thun and Hoenig, 2011; Wagner and Bode, 2008; Xu et al., 2019). As a result, the SC network is highly influenced by the customers ability to order with the focal firm and/or differences in the volume and variety that customers expect (Quang and Hara, 2019). Moreover, when these risks arise, businesses will not be able to forecast the actual demand of the market. This leads to product shortages, product obsolescence, inefficient use of capacity, dysfunctional operations and poor customer service (Wagner and Bode, 2008). It is seen that uncertain demand gives rise to backlogs or shortages of orders, errors in planning and the bullwhip effect (George et al., 2004). In addition, rapid changes in customer expectations increase costs of products. On the other hand, fluctuations in customers' demand negatively impact performance of the inventory system.

In construction, the SC process begins with the requirements of services, products and materials by clients, which is always followed by a demand. This step is particularly important because of its unique project-specific requirements (Behera et al., 2015). Additionally, the role of clients is significant in terms of information sharing, trust and collaboration throughout the SC because they are associated with a higher number of risks compared to other stakeholders (Koc and Gurgun, 2021). Pham et al. (2022) imply that demand risk causes operational risk which in turn impacts the performance of construction SCs. Since evidence for such impacts is still limited in construction, the present study proposes that:

H3a,b.

Demand risk causes operational risk and adversely affects SC performance.

3.3 The impact of operational risk on supply chain performance

Operational risk directly affects SC performance and receives resonant effects from other risks, namely supply risk, demand risk and external risk. Operational risk refers to disruptions caused by adverse events within a firm that affect the SC ability in producing goods and services, profitability, timeliness of production and quality. Some examples of operational risk include labor disputes, accidents, or changes in technology and design (Song et al., 2017; Abdel-Basset and Mohamed, 2020; Cunha et al., 2019; Rostamzadeh et al., 2018). These risks lead to the challenge of determining optimal production quantity, optimal order quantity, safety level of inventory and other inventory policies. As a result, they have significant impacts on SC performance both in cost and profit (Truong Quang and Hara, 2018). Kate (2013) states that the majority of work accidents affect the ability of employees to perform their usual duties. Approximately 27 million work days in a year are lost due to occupational disease or personal injury, proving that these incidents can have serious consequences. Although the above studies in various industries have shown the effects of operational risk on performance, empirical evidence for such effects in construction SCs has been scarce. Koc and Gurgun (2021) conclude that operational risks such as lack of skilled workers, safety accidents, technological issues and lack of planning directly affect performance of construction SCs. Therefore, the following hypothesis is proposed Figure 1:

H4.

Operational risk adversely affects SC performance.

4. Data collection

The data used in this study are collected from a large-scale survey supported by a project of the Japanese government to promote sustainable socioeconomic development for the ASEAN (Association of Southeast Asian Nations) region. Through the Vietnam General Statistics Office, a list of construction firms for our survey was firstly compiled. The survey was conducted in Vietnam's construction industry with a total of 3,601 firms. The target respondents are managers of firms who have knowledge and experience in risk management and SC management. Because the scales drawn from the literature were in English, the initial questionnaire was developed in English and subsequently translated into Vietnamese by our research team members. The Vietnamese version of the questionnaire was used for data collection. The content of the survey questionnaire is presented in the Appendix.

An invitation was sent to emails of all firms to ask them to take part in our survey. The invitation presented the purpose and objectives of this study as well as a request for firms to join the survey. Moreover, it is mentioned in the survey that the firm information is confidential and used only for the objectives of the study. After that, questionnaires were sent to firms that agreed to respond to the survey. Respondents were asked to rate the influences of SC risks on their firms in the past 5 years as well as estimate their SC performance. A five-point Likert scale was used in order to capture the different attitudes of the respondents, ranging from one (strongly disagree) to five (strongly agree). An official questionnaire link was sent to all firms via email. 354 responses were subsequently returned, representing a response rate of 9.83%. After excluding 147 incomplete responses, a total of 207 responses were used for the analyses. Characteristics of the sample are described in Table 2.

5. Results

A t-test estimate of non-response bias was undertaken in order to examine the difference in items between early and late responses (Armstrong and Overton, 1977). The results indicated that there were no statistically significant differences in the average scores of all observed items (internal confidence of 99%), hence non-response bias is not a problem in this study.

In addition, each firm's independent and dependent variables were collected from the same respondent. This may result in the emergence of common method variance (CMV). Harman's single-factor test was conducted to examine this emergence (Podsakoff et al., 2003). All observed items were subjected to a non-rotated factor analysis. If just one factor emerges (i.e. a generic factor can explain covariance in all variables), it is reasonable to assume that the CMV is substantial. The findings suggested that eleven factors occurred. However, when there are too many factors, this method of testing is not accurate (Podsakoff et al., 2003). Therefore, items from each independent factor (i.e. risk constructs) were factorically analyzed with items from the scale of the dependent factor (i.e. performance construct). Factor analysis revealed that two or more components appeared, indicating that there is no significant CMV.

Traditional methods are used to assess the validity and reliability of constructs (Hair et al., 1995). This study uses exploratory factor analysis (EFA) for detecting underlying dimensions. After removing measures that did not achieve the threshold value of 0.50, the remaining measures load on the corresponding components with factor loadings greater than 0.734, eigenvalue ≥1.623 and variance extracted ≥63.278. All item – total correlations are above 0.483, the Cronbach's alpha coefficients range from 0.700 to 0.845 (higher than 0.7). Hence, the reliability of the risk constructs is ensured (Table 3). Moreover, the degree of multicollinearity should be examined by calculating the variance inflation factor (VIF). A VIF value of 5.0 indicates potential problems of multicollinearity (Hair et al., 2011). In this study, VIF values calculated are less than the threshold of 5.0, thus the constructs are free from the multicollinearity. Table 4 presents EFA results for performance constructs.

In the next step, SEM is employed for estimating the relationships among the constructs. Our study uses a two-step model building approach in which the measurement model is examined before testing the structural model (Anderson and Gerbing, 1988). Confirmatory factor analysis (CFA) is used to test the constructs validity including convergent and discriminant validity. CFA results from Table 5 show that composite reliability (CR) and average variance extracted (AVE) of all constructs are higher than 0.7 and 50% respectively, thus confirming the convergent validity.

Table 6 shows the evaluation of discriminant validity. It is seen that the square root of AVE for each construct located in the diagonal is greater than correlations between any two constructs. This result indicates that the discriminant validity of the constructs was satisfactory (Fornell and Larcker, 1981).

The results of the SEM model are schematically depicted in Figure 2, with χ2/df = 1.726, CFI = 0.902, RMSEA = 0.059, indicating that the model suits the data. In addition, the coefficient of R2 is 0.54, meaning that our model can explain 54% variance of SC performance. Table 7 summarizes the results of hypotheses testing.

6. Discussion

The literature has given little attention to the combined impacts of disruptions and internal risks (e.g. supply, demand and operational risks). During the COVID-19 pandemic, firms have experienced severe supply–demand disruptions, causing shortages in production capacity (Xu et al., 2020). Thus, they are unable to meet customer needs for essential products during lockdowns. Because of supply and demand disruptions, many firms have suffered from financial losses (Gholami-Zanjani et al., 2021). As a result, such risks and disruptions have caused the ripple effect in SCs. Many previous studies have been done on risk management in construction SCs such as Naderpajouh et al. (2015), Rudolf and Spinler (2018), Panova and Hilletofth (2018), Shojaei and Haeri (2019), Zhao (2019), Abas et al. (2022), Obayi and Ebrahimi (2021), Ekanayake et al. (2021a), and Ekanayake et al. (2022). However, the findings of this study differ from those of these studies in some ways. First, some studies such as Shojaei and Haeri (2019), Zhao (2019), and Ekanayake et al. (2021a) have not provided evidence for the impact of all risks on performance. Second, other studies (e.g. Naderpajouh et al., 2015; Panova and Hilletofth, 2018; Rudolf and Spinler, 2018; Abas et al., 2022; Obayi and Ebrahimi, 2021; Ekanayake et al., 2022) partially identify the types of risks while the propagation mechanism of risks has not been established.

The present study has two important contributions to the literature. The first contribution of this study is to identify the mechanism of the ripple effect in construction SCs. A good SC risk management strategy needs to evaluate the severity of risks. Ho et al. (2015) conclude that the majority of studies only consider the impact of each risk on various performance outputs. For this reason, the overall picture of the impacts of all risks in the SC is still lacking. However, the literature (e.g. Wagner and Bode, 2008; Truong Quang and Hara, 2018) indicates that risks do not independently occur, but simultaneously occur. This can explain why hedging solutions do not achieve the desired results because plans for mitigating and controlling risks only focus on a single risk. Worse, in an adverse situation, many risks that simultaneously occur without appropriate contingency plans inevitably have devastating consequences for SC operations. It is proven that a risk, when it occurs, can create a ripple effect. Indeed, using empirical data from 760 firms in Germany, Wagner and Bode (2008) conclude the occurrence of financial and information risks leads to the occurrence of supply, manufacturing and demand risks. This view is also supported by Klüppelberg et al. (2014) that firms should understand how to model and describe the dependency structure of risks. Obviously, if all risks are interrelated, they tend to occur together and increase the severity of the overall risk impact.

Our results indicate that human-made risk causes operational risk. Moreover, natural risk causes both supply risk and operational risk. It is remarkable to see that operational risk is the main risk that amplifies the impacts of human-made risk and natural risk on performance. Operational risk which is referred to uncertainties inherent in SCs (e.g. uncertain demand/supply/cost) is mostly ignored by the literature on the ripple effect. However, operational risk can create the ripple effect because firms often engage in the creation of customized products with suppliers. Hence, firms are highly dependent on single suppliers, causing delays in operations (Xu, 2020). In addition, due to high costs related to inventory holding, many firms adopt lean practices for keeping minimum inventory. This renders firms more susceptible to operational risk and the ripple effect along the SC (Papadakis, 2006). Although it is hypothesized that human-made risk leads to supply risk and demand risk, natural risk leads to demand risk, and supply risk and demand risk cause operational risk; the results do not support these hypotheses. A possible explanation for these unsupported hypotheses is that the data of this study are only obtained from construction firms in Vietnam. Because the construction industry in each country has specific characteristics that differ from those in other countries, such differences may be one reason that some hypotheses in our theoretical framework have not been supported.

The second contribution of this study is to demonstrate the ripple effect of risk on performance. As observed in Figure 2, human-made risk, supply risk and operational risk have direct impacts on SC performance, yet natural risk and demand risk have no such direct impacts. However, it is found that the impacts of human-made risk and natural risk on performance are amplified through operational risk. It means that human-made risk and natural risk lead to the occurrence of operational risk which in turn has negative effect on performance. Hence, the findings demonstrated the ripple effects of both human-made risk and natural risk on performance. In addition, the ripple effect of natural risk on performance is also confirmed by this study. Specifically, natural risk causes the occurrence of supply risk which then adversely affects performance. In this case, it is concluded that the impacts of natural risk on performance are propagated through supply risk and operational risk.

Recently, there is a growing interest from both practitioners and academics in managing disruptions through the development of SC resilience (Ambulkar et al., 2015; Ekanayake et al., 2020, 2021b). Resilience is an adaptive capability of a SC for preparing for unexpected events, responding to disruptions and recovering from them by maintaining the operations continuity (Yu et al., 2019). It is claimed that resilience enables firms to better manage disruptions and maintain high performance through the continuance of products deliveries to customers (Brusset and Teller, 2017). In uncertain and turbulent environments, it is more crucial for firms to develop resilient SCs for managing unforeseen (Ali et al., 2017). Although many previous studies on risk management in construction SCs have been conducted such as Naderpajouh et al. (2015), Rudolf and Spinler (2018), Panova and Hilletofth (2018), Shojaei and Haeri (2019), Zhao (2019), Abas et al. (2022), and Obayi and Ebrahimi (2021), their aims mainly focus on the risk identification and quantification of risk impact. It is concluded that research on resilience is still very limited. It is pivotal to nurture and embed resilience at appropriate levels in construction SCs because the performance targets and planned sustainability cannot be achieved without successfully overcoming disruptions and their ripple effect through the enhanced resilience (Ekanayake et al., 2021c).

Whenever a SC is impacted by disruptions, resilience becomes important (Golan et al., 2020). The comprehensive development of a SC resilience strategy consists of three stages: preparedness, response and recovery aimed at mitigating disruptions. Hence, in responding to severe impacts of disruptions, it is seen that the extant literature is increasingly focusing on the topic of resilience. For this reason, our study suggests that further studies should pay more attention in studying resilience in construction SCs since it helps firms effectively manage disruptions, thus operations can be restored to the previous or even improved performance level (Scholten et al., 2014). Vertical collaborative strategies (e.g. inter-firm collaboration) and horizontal collaborative strategies (e.g. intra-firm collaboration) can help firms articulate rapid actions in responding to global disruptions, for example, the Covid-19 pandemic (Rahman et al., 2022). In this situation, our study suggests that firms need to develop collaboration and operational flexibility along their SC when dealing with disruptions. Further investigation is needed to understand how and to what extent collaborative strategies can help firms reduce the impacts of large-scale disruptions.

7. Implications and limitations

With regard to theoretical implications, this study broadens the understanding of relationships between SC risks and performance with efforts to define, develop and examine the ripple effect. This is a new approach in the SC risk management literature, which simultaneously considers risks in an interactive system. Therefore, if firms are able to manage the mechanism of the ripple effect, they can significantly reduce the impact of risks on performance. Efforts should start with operational risks because they receive ripple effects from other risks namely human-made risk and natural risk. Then, the attention should be focused on supply risk which is also pushed by natural risk. In this situation, the severity of external risks would be significantly reduced if supply risk and operational risk are controlled.

It is really important to develop resilience in construction SCs since performance results can only be achieved if the effect of disruptions and their ripple effect are controlled through better resilience (Ekanayake et al., 2021c). In this regard, this study has some practical implications. In order to maintain high performance, managers should implement various mitigation strategies namely SC resilience to enhance the ability of their firm in absorbing disruptions and rapidly returning to the stable condition (Yu et al., 2019). Indeed, it is posited that in a highly changing environment, firms that strongly develop resilience are able to quickly recover from unforeseeable disruptions and still maintain the high level of performance (Hohenstein et al., 2015). In an uncertain environment, firms in the SC always face many disruptions. Nevertheless, being exposed to disruptions is not necessarily a threat but potentially an opportunity for firms to develop resilient SC. Developing robust SC initiatives such as resilience can provide managers with an effective strategy to cope with risks and recover from disruptions.

Despite its own contributions, the present study still has several limitations that should be considered by further studies. The first limitation concerns the unsupported hypotheses in our theoretical model. Future research in Vietnam should apply other research methods such as case study and focus groups to examine why these hypotheses have not been supported. In this way, future studies can enhance the generalization of our model and establish more clearly the ripple effect of SC risks. Second, the data of the present study are cross-sectional in nature. This did not allow us to evaluate the long-term impacts of risks on performance. Hence, it is more interesting to conduct a longitudinal study to better understand the long-term impacts of risks. Third, toward a broader perspective, it is essential to examine the overall validity of the results in nations with different characteristics (developing countries/developed countries). Thus, an international survey may provide interesting insights into risk attitudes in other countries and may identify cultural differences in SC risk management.

Figures

Theoretical framework

Figure 1

Theoretical framework

SEM results

Figure 2

SEM results

Supply chain risks

CategoriesSub-categoriesRisksReferences
Internal riskSupply risk
  • Supplier opportunism

  • Unstable quality of inputs

  • Price fluctuations

  • Inflexibility of suppliers

  • Supplier bankruptcy

  • Suppliers' dependency

  • Unstable quantity of inputs

  • Delays in supply activities

Abdel-Basset and Mohamed (2020), Moktadir et al. (2021), Rostamzadeh et al. (2018), Truong and Hara (2018), Wagner and Bode (2008)
Operational risk
  • Design changes

  • Poor planning and scheduling

  • Technological changes

  • Dissatisfaction with work

  • Accidents

  • Inflexibility in layout for free flow of materials

  • Labor disputes/strikes

  • Lack of experience or training

Abdel-Basset and Mohamed (2020), Cunha et al. (2019), Rostamzadeh et al. (2018), Song et al. (2017), Truong Quang and Hara (2018)
Demand risk
  • Demand variability

  • Deficient or missing customer relation management function

  • Customer bankruptcy

  • Customer dependency

  • High competition in the market

  • Customer fragmentation

Abdel-Basset and Mohamed (2020), George et al. (2004), Ho et al. (2015), Moktadir et al. (2021), Quang and Hara (2019), Rostamzadeh et al. (2018), Song et al. (2017), Thun and Hoenig (2011), Wagner and Bode (2008), Xu et al. (2019)
Disruption riskHuman-made risk
  • Economic downturns

  • Social and cultural grievances

  • External legal issues

  • War and terrorism

  • Political instability

Abdel-Basset and Mohamed (2020), Contreras et al. (2021), Hansen et al. (2013), Manuj and Mentzer (2008), Moktadir et al. (2021), Rostamzadeh et al. (2018), Song et al. (2017), Truong Quang and Hara (2018), Wu et al. (2017), Xu et al. (2019)
Natural risk
  • Epidemics

  • Earthquakes

  • Natural catastrophes

  • Tsunami

Source(s): Compiled by the authors

Survey sample characteristics

Percent
Business field
Building material manufacturing (sand, stone, additive)15.5
Building material distribution23.2
Concrete production19.3
Construction executive34.8
Design (architecture and construction)7.2
Authorized capital
Less than 1 million dollars5.3
From 1 to 5 million dollars16.4
Above 5 million dollars78.3
Job title
Top-level manager7.7
Middle-level manager22.7
First-level manager51.2
Coordinator10.6
Others7.7

Source(s): Compiled by the authors

EFA results for risk constructs

Supply riskOperational riskDemand riskExternal riskItem – total correlation
ConstructsObserved itemsHuman-made riskNatural risk
Supply riskSupplier bankruptcy0.870 0.727
Price fluctuations0.797 0.608
Unstable quality of inputs0.744 0.555
Unstable quantity of inputs0.767 0.586
Operational riskDesign changes 0.928 0.731
Technological changes 0.932 0.731
Accidents 0.921 0.697
Labor disputes/strikes 0.920 0.697
Demand riskDemand variability 0.793 0.618
High competition in the market 0.734 0.550
Customer bankruptcy 0.819 0.656
Customer fragmentation 0.832 0.669
External riskEconomic downturns 0.808 0.540
External legal issues 0.794 0.521
War and terrorism 0.770 0.483
Epidemics 0.9090.682
Natural catastrophes 0.9200.682
Cronbach's alpha0.8010.8450.8050.7000.81
Eigenvalue2.5331.6512.5311.623
Variance extracted63.32586.14163.27871.441

Source(s): Calculated by the authors

EFA results for performance constructs

Observed items1234Item – total correlation
Supplier performanceReliability 0.8910.623
Response time 0.7000.623
Internal businessAmount of waste 0.517 0.551
Costs of inventory management 0.765 0.635
Workforce productivity 0.806 0.58
Innovation and learningNumber of new products developed per year 0.778 0.635
Workforce flexibility 0.871 0.635
Customer serviceDelivery timelinessDeleted
Percentage of “perfect orders” deliveredDeleted
Product value perceived by customers0.658 0.552
Product quality0.939 0.673
Response time to customers queries0.473 0.481
FinanceMarket share growthDeleted
Return on Investments (ROI)Deleted
Cronbach's alpha0.7380.7570.7460.767
Eigenvalue1.131
Variance extracted74.661

Source(s): Calculated by the authors

CFA results

ConstructsObserved itemsStandardized regression weightsStandard errorsR2Composite reliabilityVariance extracted
Supply riskSupplier bankruptcy0.9200.0520.8460.8000.510
Price fluctuations0.7330.0610.538
Unstable quality of inputs0.5730.0590.329
Unstable quantity of inputs0.5720.0740.327
Operational riskDesign changes0.8630.0580.7460.9180.737
Technological changes0.9010.0540.812
Accidents0.8480.0550.720
Labor disputes/strikes0.8200.0590.672
Demand riskDemand variability0.6410.0450.4100.8040.513
High competition in the market0.5490.0340.301
Customer bankruptcy0.7860.0350.618
Customer fragmentation0.8500.0420.723
External riskEconomic downturns0.7130.0450.5090.8890.543
External legal issues0.6720.0530.451
Corruption0.6860.0640.470
Epidemics0.8620.0460.743
Natural catastrophes0.8840.0440.782
Threshold valuesStandardized Regression Coefficients >0.5
Standardized Regression Coefficient >2 × standard error
R2 > 0.3
Composite reliability >0.7
Variance Extracted >50%

Source(s): Calculated by the authors

Discriminant validity results

Supply riskOperational riskDemand riskExternal risk
Supply risk0.796
Operational risk−0.201**0.928
Demand risk0.181**−0.0790.795
External risk0.186**−0.0540.0430.845

Source(s): Calculated by the authors

Hypotheses testing results

HypothesesStatementsStandardized regression weights
H1aHuman-made riskSupply riskUnsupported
H1bHuman-made riskDemand riskUnsupported
H1cHuman-made riskOperational risk0.211**
H1dHuman-made riskSupply chain performance0.325**
H1eNatural riskSupply risk0.225**
H1fNatural riskDemand riskUnsupported
H1gNatural riskOperational risk0.811***
H1hNatural riskSupply chain performanceUnsupported
H2aSupply riskOperational riskUnsupported
H2bSupply riskSupply chain performance0.232*
H3aDemand riskOperational riskUnsupported
H3bDemand riskSupply chain performanceUnsupported
H4Operational riskSupply chain performance0.417**

Source(s): Calculated by the authors

Appendix Survey questionnaire

References

Abas, M., Khattak, S.B., Habib, T. and Nadir, U. (2022), “Assessment of critical risk and success factors in construction supply chain: a case of Pakistan”, International Journal of Construction Management, Vol. 22 No. 12, pp. 2258-2266.

Abdel-Basset, M. and Mohamed, R. (2020), “A novel plithogenic TOPSIS-CRITIC model for sustainable supply chain risk management”, Journal of Cleaner Production, Vol. 247, 119586.

Ali, A., Mahfouz, A. and Arisha, A. (2017), “Analysing supply chain resilience: integrating the constructs in a concept mapping framework via a systematic literature review”, Supply Chain Management: An International Journal, Vol. 22 No. 1, pp. 16-39.

Aloini, D., Dulmin, R., Mininno, V. and Ponticelli, S. (2012), “Supply chain management: a review of implementation risks in the construction industry”, Business Process Management Journal, Vol. 18 No. 5, pp. 735-761.

Ambulkar, S., Blackhurst, J. and Grawe, S. (2015), “Firm's resilience to supply chain disruptions: scale development and empirical examination”, Journal of Operations Management, Vol. 33, pp. 111-122.

Anderson, J.C. and Gerbing, D.W. (1988), “Structural equation modeling in practice: a review and recommended two-step approach”, Psychological Bulletin, Vol. 103 No. 3, p. 411.

Armstrong, J.S. and Overton, T.S. (1977), “Estimating nonresponse bias in mail surveys”, Journal of marketing research, Vol. 14 No. 3, pp. 396-402.

Baghersad, M. and Zobel, C.W. (2021), “Assessing the extended impacts of supply chain disruptions on firms: an empirical study”, International Journal of Production Economics, Vol. 231, 107862.

Barichello, R. (2020), “The COVID‐19 pandemic: anticipating its effects on Canada’s agricultural trade”, Canadian Journal of Agricultural Economics/Revue canadienne d’agroeconomie, Vol. 68 No. 2, pp. 219-224.

Behera, P., Mohanty, R. and Prakash, A. (2015), “Understanding construction supply chain management”, Production Planning and Control, Vol. 26 No. 16, pp. 1332-1350.

Birkie, S.E. and Trucco, P. (2020), “Do not expect others do what you should! Supply chain complexity and mitigation of the ripple effect of disruptions”, International Journal of Logistics Management, Vol. 31 No. 1, pp. 123-144.

Brusset, X. and Teller, C. (2017), “Supply chain capabilities, risks, and resilience”, International Journal of Production Economics, Vol. 184, pp. 59-68.

Chen, H.L. (2018), “Supply chain risk’s impact on corporate financial performance”, International Journal of Operations and Production Management, Vol. 38 No. 3, pp. 713-731.

Colicchia, C. and Strozzi, F. (2012), “Supply chain risk management: a new methodology for a systematic literature review”, Supply Chain Management: An International Journal, Vol. 17 No. 4, pp. 403-418.

Contreras, L.E.V., Perkins, K.M., Ellenbecker, M., Moure-Eraso, R. and Velazquez, L. (2021), “COVID-19 pandemic lessons to facilitate future engagement in the global climate crisis”, Journal of Cleaner Production, Vol. 290, 125178.

Costa, F., Denis Granja, A., Fregola, A., Picchi, F. and Portioli Staudacher, A. (2019), “Understanding relative importance of barriers to improving the customer–supplier relationship within construction supply chains using DEMATEL technique”, Journal of Management in Engineering, Vol. 35 No. 3, 04019002.

Craighead, C.W. and Meredith, J. (2008), “Operations management research: evolution and alternative future paths”, International Journal of Operations and Production Management, Vol. 28 No. 8, pp. 710-726.

Craighead, C.W., Blackhurst, J., Rungtusanatham, M.J. and Handfield, R.B. (2007), “The severity of supply chain disruptions: design characteristics and mitigation capabilities”, Decision Sciences, Vol. 38 No. 1, pp. 131-156.

Cunha, L., Ceryno, P. and Leiras, A. (2019), “Social supply chain risk management: a taxonomy, a framework and a research agenda”, Journal of Cleaner Production, Vol. 220, pp. 1101-1110.

Dikmen, I., Budayan, C., Talat Birgonul, M. and Hayat, E. (2018), “Effects of risk attitude and controllability assumption on risk ratings: observational study on international construction project risk assessment”, Journal of Management in Engineering, Vol. 34 No. 6, 04018037.

Dolgui, A. and Ivanov, D. (2021), “Ripple effect and supply chain disruption management: new trends and research directions”, International Journal of Production Research, Vol. 59 No. 1, pp. 102-109.

Dolgui, A., Ivanov, D. and Sokolov, B. (2018), “Ripple effect in the supply chain: an analysis and recent literature”, International Journal of Production Research, Vol. 56 Nos 1-2, pp. 414-430.

Ekanayake, E.M.A.C., Shen, G.Q., Kumaraswamy, M. and Owusu, E.K. (2021b), “Critical supply chain vulnerabilities affecting supply chain resilience of industrialized construction in Hong Kong”, Engineering, Construction and Architectural Management, Vol. 28 No. 10, pp. 3041-3059.

Ekanayake, E.M.A.C., Shen, G., Kumaraswamy, M. and Owusu, E.K. (2022b), “A fuzzy synthetic evaluation of vulnerabilities affecting supply chain resilience of industrialized construction in Hong Kong”, Engineering, Construction and Architectural Management, Vol. 29 No. 6, pp. 2358-2381.

Ekanayake, E.M.A.C., Shen, G.Q. and Kumaraswamy, M.M. (2021a), “Identifying supply chain capabilities of construction firms in industrialized construction”, Production Planning and Control, Vol. 32 No. 4, pp. 303-321.

Ekanayake, E.M.A.C., Shen, G., Kumaraswamy, M., Owusu, E.K. and Xue, J. (2022c), Capabilities to withstand vulnerabilities and boost resilience in industrialized construction supply chains: a Hong Kong study. Engineering, Construction and Architectural Management, Vol. 29 No. 10, pp. 3809-3829.

Ekanayake, E.M.A.C., Shen, G.Q., Kumaraswamy, M.M. and Owusu, E.K. (2022a), “Identifying supply chain vulnerabilities in industrialized construction: an overview”, International Journal of Construction Management, Vol. 22 No. 8, pp. 1464-1477.

Fornell, C. and Larcker, D.F. (1981), “Evaluating structural equation models with unobservable variables and measurement error”, Journal of Marketing Research, pp. 39-50.

George, A.Z., Lisa, M.E., Joseph, R.C. and Joseph, L.C. (2004), “An analysis of supply risk assessment techniquesnull”, International Journal of Physical Distribution and Logistics Management, Vol. 34 No. 5, pp. 397-413.

Gholami-Zanjani, S.M., Jabalameli, M.S., Klibi, W. and Pishvaee, M.S. (2021), “A robust location-inventory model for food supply chains operating under disruptions with ripple effects”, International Journal of Production Research, Vol. 59 No. 1, pp. 301-324.

Goh, C.S., Abdul-Rahman, H. and Abdul Samad, Z. (2013), “Applying risk management workshop for a public construction project: case study”, Journal of Construction Engineering and Management, Vol. 139 No. 5, pp. 572-580.

Golan, M.S., Jernegan, L.H. and Linkov, I. (2020), “Trends and applications of resilience analytics in supply chain modeling: systematic literature review in the context of the COVID-19 pandemic”, Environment Systems and Decisions, Vol. 40 No. 2, pp. 222-243.

Hair, J.F., Anderson, R.E., Tatham, R.L. and Black, W.C. (1995), Multivariate Data Analysis with Readings, 4th ed., Prentice Hall, New Jersy.

Hair, J.F., Ringle, C.M. and Sarstedt, M. (2011), “PLS-SEM: indeed a silver bullet”, Journal of Marketing Theory and Practice, Vol. 19 No. 2, pp. 139-152.

Hansen, E., Nybakk, E. and Panwar, R. (2013), “Firm performance, business environment, and outlook for social and environmental responsibility during the economic downturn: findings and implications from the forest sector”, Canadian Journal of Forest Research, Vol. 43 No. 12, pp. 1137-1144.

Ho, W., Zheng, T., Yildiz, H. and Talluri, S. (2015), “Supply chain risk management: a literature review”, International Journal of Production Research, Vol. 53 No. 16, pp. 5031-5069.

Hohenstein, N.O., Feisel, E., Hartmann, E. and Giunipero, L. (2015), “Research on the phenomenon of supply chain resilience: a systematic review and paths for further investigation”, International Journal of Physical Distribution and Logistics Management, Vol. 45 Nos 1/2, pp. 90-117.

Hosseini, S. and Ivanov, D. (2022), “A new resilience measure for supply networks with the ripple effect considerations: a Bayesian network approach”, Annals of Operations Research, Vol. 319 No. 1, pp. 581-607.

Hosseini, S., Ivanov, D. and Dolgui, A. (2020), “Ripple effect modelling of supplier disruption: integrated Markov chain and dynamic Bayesian network approach”, International Journal of Production Research, Vol. 58 No. 11, pp. 3284-3303.

Ivanov, D., Sokolov, B., Solovyeva, I., Dolgui, A. and Jie, F. (2016), “Dynamic recovery policies for time-critical supply chains under conditions of ripple effect”, International Journal of Production Research, Vol. 54 No. 23, pp. 7245-7258.

Ivanov, D. (2022), “Blackout and supply chains: cross-structural ripple effect, performance, resilience and viability impact analysis”, Annals of Operations Research, Vol. ahead-of-print No. ahead-of-print.

Jayasinghe, R.S., Rameezdeen, R. and Chileshe, N. (2022), “Modelling the cause and effect relationship risks in reverse logistics supply chains for demolition waste”, Engineering, Construction and Architectural Management, Vol. ahead-of-print No. ahead-of-print.

Jüttner, U. (2005), “Supply chain risk management: understanding the business requirements from a practitioner perspective”, The International Journal of Logistics Management, Vol. 16 No. 1, pp. 120-141.

Kaplan, R.S. and Norton, D. (1992), “The balanced scorecard: measures that drive performance”, Harvard Business Review, Vol. 70 No. 1, pp. 71-79.

Kate, S. (2013), “Health and safety executive - annual statistics report for Great Britain 2012/13”.

Kinra, A., Ivanov, D., Das, A. and Dolgui, A. (2020), “Ripple effect quantification by supplier risk exposure assessment”, International Journal of Production Research, Vol. 58 No. 18, pp. 5559-5578.

Klüppelberg, C., Straub, D. and Welpe, I.M. (2014), Risk - A Multidisciplinary Introduction, Springer Cham, Springer International Publishing Switzerland 2014.

Koc, K. and Gurgun, A.P. (2021), “Stakeholder-associated life cycle risks in construction supply chain”, Journal of Management in Engineering, Vol. 37 No. 1, 04020107.

Koushki, P.A. and Kartam, N. (2004), “Impact of construction materials on project time and cost in Kuwait”, Engineering, Construction and Architectural Management, Vol. 11 No. 2, pp. 126-132.

Kumar, V., Bak, O., Guo, R., Shaw, S.L., Colicchia, C., Garza-Reyes, J.A. and Kumari, A. (2018), “An empirical analysis of supply and manufacturing risk and business performance: a Chinese manufacturing supply chain perspective”, Supply Chain Management: An International Journal, Vol. 23 No. 6, pp. 461-479.

Li, Y. and Zobel, C.W. (2020), “Exploring supply chain network resilience in the presence of the ripple effect”, International Journal of Production Economics, Vol. 228, 107693.

Li, Y., Chen, K., Collignon, S. and Ivanov, D. (2021), “Ripple effect in the supply chain network: forward and backward disruption propagation, network health and firm vulnerability”, European Journal of Operational Research, Vol. 291 No. 3, pp. 1117-1131.

Lin, Y. and Zhou, L. (2011), “The impacts of product design changes on supply chain risk: a case study”, International Journal of Physical Distribution and Logistics Management, Vol. 41 No. 2, pp. 162-186.

Liu, M., Liu, Z., Chu, F., Zheng, F. and Chu, C. (2021), “A new robust dynamic Bayesian network approach for disruption risk assessment under the supply chain ripple effect”, International Journal of Production Research, Vol. 59 No. 1, pp. 265-285.

Manuj, I. and Mentzer, J.T. (2008), “Global supply chain risk management strategies”, International Journal of Physical Distribution and Logistics Management, Vol. 38 No. 3, pp. 192-223.

Mishra, D., Sharma, R.R.K., Kumar, S. and Dubey, R. (2016), “Bridging and buffering: strategies for mitigating supply risk and improving supply chain performance”, International Journal of Production Economics, Vol. 180, pp. 183-197.

Moktadir, M.A., Dwivedi, A., Khan, N.S., Paul, S.K., Khan, S.A., Ahmed, S. and Sultana, R. (2021), “Analysis of risk factors in sustainable supply chain management in an emerging economy of leather industry”, Journal of Cleaner Production, Vol. 283, 124641.

Naderpajouh, N., Hastak, M., Gokhale, S., Bayraktar, M.E., Iyer, A. and Arif, F. (2015), “Counterfeiting risk governance in the capital projects supply chain”, Journal of Construction Engineering and Management, Vol. 141 No. 3, 04014084.

Niu, Y., Lu, W., Liu, D., Chen, K., Anumba, C. and Huang, G.G. (2017), “An SCO-enabled logistics and supply chain–management system in construction”, Journal of Construction Engineering and Management, Vol. 143 No. 3, 04016103.

Obayi, R. and Ebrahimi, S.N. (2021), “A neo-institutional view of the transaction cost drivers of construction supply chain risk management”, Supply Chain Management: An International Journal, Vol. 26 No. 5, pp. 592-609.

Özçelik, G., Faruk Yılmaz, Ö. and Betül Yeni, F. (2021), “Robust optimisation for ripple effect on reverse supply chain: an industrial case study”, International Journal of Production Research, Vol. 59 No. 1, pp. 245-264.

Panova, Y. and Hilletofth, P. (2018), “Managing supply chain risks and delays in construction project”, Industrial Management and Data Systems, Vol. 118 No. 7, pp. 1413-1431.

Papadakis, I.S. (2006), “Financial performance of supply chains after disruptions: an event study”, Supply Chain Management: An International Journal, Vol. 11 No. 1, pp. 25-33.

Park, Y.W., Blackhurst, J., Paul, C. and Scheibe, K.P. (2022), “An analysis of the ripple effect for disruptions occurring in circular flows of a supply chain network”, International Journal of Production Research, Vol. 60 No. 15, pp. 4693-4711.

Pavlov, A., Ivanov, D., Werner, F., Dolgui, A. and Sokolov, B. (2019), “Integrated detection of disruption scenarios, the ripple effect dispersal and recovery paths in supply chains”, Annals of Operations Research, Vol. 319 No. 1, pp. 609-631.

Pham, H.T., Pham, T., Truong Quang, H. and Dang, C.N. (2022), “Supply chain risk management research in construction: a systematic review”, International Journal of Construction Management, Vol. ahead-of-print No. ahead-of-print.

Podsakoff, P.M., MacKenzie, S.B., Lee, J.Y. and Podsakoff, N.P. (2003), “Common method biases in behavioral research: a critical review of the literature and recommended remedies”, Journal of Applied Psychology, Vol. 88 No. 5, p. 879.

Quang, H.T. and Hara, Y. (2019), “The push effect of risks on supply chain performance: service-oriented firms”, Business Process Management Journal, Vol. 25 No. 7, pp. 1734-1758.

Rahman, T., Paul, S.K., Shukla, N., Agarwal, R. and Taghikhah, F. (2022), “Supply chain resilience initiatives and strategies: a systematic review”, Computers and Industrial Engineering, Vol. 170, 108317.

Rajagopal, V., Venkatesan, S.P. and Goh, M. (2017), “Decision-making models for supply chain risk mitigation: a review”, Computers and Industrial Engineering, Vol. 113, pp. 646-682.

Rostamzadeh, R., Ghorabaee, M.K., Govindan, K., Esmaeili, A. and Nobar, H.B.K. (2018), “Evaluation of sustainable supply chain risk management using an integrated fuzzy TOPSIS-CRITIC approach”, Journal of Cleaner Production, Vol. 175, pp. 651-669.

Rudolf, C.A. and Spinler, S. (2018), “Key risks in the supply chain of large scale engineering and construction projects”, Supply Chain Management: An International Journal, Vol. 23 No. 4, pp. 336-350.

Scholten, K., Scott, P.S. and Fynes, B. (2014), “Mitigation processes–antecedents for building supply chain resilience”, Supply Chain Management: An International Journal, Vol. 19 No. 2, pp. 211-228.

Scudder, G.D. and Hill, C.A. (1998), “A review and classification of empirical research in operations management”, Journal of Operations Management, Vol. 16 No. 1, pp. 91-101.

Shojaei, P. and Haeri, S.A.S. (2019), “Development of supply chain risk management approaches for construction projects: a grounded theory approach”, Computers and Industrial Engineering, Vol. 128, pp. 837-850.

Song, W., Ming, X. and Liu, H.-C. (2017), “Identifying critical risk factors of sustainable supply chain management: a rough strength-relation analysis method”, Journal of Cleaner Production, Vol. 143, pp. 100-115.

Thun, J.-H. and Hoenig, D. (2011), “An empirical analysis of supply chain risk management in the German automotive industry”, International Journal of Production Economics, Vol. 131 No. 1, pp. 242-249.

Truong, H.Q. and Hara, Y. (2018), “Supply chain risk management: manufacturing-and service-oriented firms”, Journal of Manufacturing Technology Management, Vol. 29 No. 2, pp. 218-239.

Truong Quang, H. and Hara, Y. (2018), “Risks and performance in supply chain: the push effect”, International Journal of Production Research, Vol. 56 No. 4, pp. 1369-1388.

Wagner, S.M. and Bode, C. (2008), “An empirical examination of supply chain performance along several dimensions of risk”, Journal of Business Logistics, Vol. 29 No. 1, pp. 307-325.

Wang, M. (2018), “Impacts of supply chain uncertainty and risk on the logistics performance”, Asia Pacific Journal of Marketing and Logistics, Vol. 30 No. 3, pp. 689-704.

Wiengarten, F., Humphreys, P., Gimenez, C. and McIvor, R. (2016), “Risk, risk management practices, and the success of supply chain integration”, International Journal of Production Economics, Vol. 171, pp. 361-370.

Wu, K.-J., Liao, C.-J., Tseng, M.-L., Lim, M.K., Hu, J. and Tan, K. (2017), “Toward sustainability: using big data to explore the decisive attributes of supply chain risks and uncertainties”, Journal of Cleaner Production, Vol. 142, pp. 663-676.

Xu, M., Cui, Y., Hu, M., Xu, X., Zhang, Z., Liang, S. and Qu, S. (2019), “Supply chain sustainability risk and assessment”, Journal of Cleaner Production, Vol. 225, pp. 857-867.

Xu, Z., Elomri, A., Kerbache, L. and El Omri, A. (2020), “Impacts of COVID-19 on global supply chains: facts and perspectives”, IEEE Engineering Management Review, Vol. 48 No. 3, pp. 153-166.

Xu, H. (2020), “Minimizing the ripple effect caused by operational risks in a make-to-order supply chain”, International Journal of Physical Distribution and Logistics Management, Vol. 50 No. 4, pp. 381-402.

Yu, W., Jacobs, M.A., Chavez, R. and Yang, J. (2019), “Dynamism, disruption orientation, and resilience in the supply chain and the impacts on financial performance: a dynamic capabilities perspective”, International Journal of Production Economics, Vol. 218, pp. 352-362.

Zhao, L., Huo, B., Sun, L. and Zhao, X. (2013), “The impact of supply chain risk on supply chain integration and company performance: a global investigation”, Supply Chain Management: An International Journal, Vol. 18 No. 2, pp. 115-131.

Zhao, N. (2019), “Managing interactive collaborative mega project supply chains under infectious risks”, International Journal of Production Economics, Vol. 218, pp. 275-286.

Zheng, Y., Ke, J. and Wang, H. (2021), “Risk propagation of concentralized distribution logistics plan change in cruise construction”, Processes, Vol. 9 No. 8, p. 1398.

Acknowledgements

Funding: The authors would like to thank Van Lang University, Ho Chi Minh City, Vietnam for funding this research. This research is funded by the University of Economics Ho Chi Minh City, Vietnam.

Corresponding author

Hai Thanh Pham can be contacted at: hai.pt@vlu.edu.vn

Related articles