Dynamic network analysis of stakeholder-associated social risks of megaprojects: a case study in China

Xin Xia (School of Management Science and Real Estate, Chongqing University, Chongqing, China)
Pengcheng Xiang (School of Management Science and Real Estate, Chongqing University, Chongqing, China) (Research Center for Construction Economics and Management, Chongqing University, Chongqing, China) (International Research Center for Sustainable Built Environment, Chongqing University, Chongqing, China)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 6 July 2022

Issue publication date: 28 November 2023

765

Abstract

Purpose

Managers of megaprojects face social risk management challenges throughout the various design, construction, and operation stages, owing to the various conflicts of interest among stakeholders, public skepticism, and opposition. However, most existing studies have not focused on the dynamic analysis of integrating social risks in these stages. This study developed a dynamic analysis approach to explore the dynamics of critical social risk factors and related stakeholders of megaprojects and built the managerial maps for various stakeholders.

Design/methodology/approach

Based on the social analysis network (SNA), a dynamic network analysis approach for understanding the dynamics of social risk and related stakeholders has been developed by literature and case analysis. The approach comprises the following steps: (1) generating social risk–stakeholder networks in different stages; (2) analysis of the critical stakeholders and social risk factors; (3) dynamic analysis of social risk factors; and (4) developing social risk management maps for various stakeholders. To verify the feasibility and effectiveness of the approach, 40 megaprojects from China were analyzed.

Findings

According to the results, the local government is a critical stakeholder during all stages, inadequate information promotion (IIP) and imperfect communication and coordination mechanism (ICCM) are key social risk sources throughout the megaproject life cycle. Furthermore, the management maps for government organizations, project implementation groups, and external stakeholders were constructed.

Originality/value

This research has three contributions. First, a dynamic analysis approach of stakeholder-associated social risks in megaprojects is developed, which enriches the social risk management theory of megaprojects and provides inspiration for future research focus. Second, the social risk–stakeholder networks and critical social risks in different stages are confirmed to provide a more valid and accurate picture of social risk management in megaprojects. Third, the social risk managerial maps for different stakeholders built in this research will be beneficial for governments, project implementation groups, and external stakeholders to optimize management strategies.

Keywords

Acknowledgements

This research was supported by grants from the Fundamental Research Funds for the Central Universities (No. 2022CDJSKJC18), the Social Science Planning Projects in Chongqing of China (No. 2021ZDSC08), and the Graduate Student Research Innovation Project in Chongqing (CYS17025). The ideas, results, conclusions, or advice expressed in this paper are those of the authors and do not represent the views of the foundations.

Data availability statement: Data generated or analyzed during the study are available from the corresponding author and first author by request.

Citation

Xia, X. and Xiang, P. (2023), "Dynamic network analysis of stakeholder-associated social risks of megaprojects: a case study in China", Engineering, Construction and Architectural Management, Vol. 30 No. 10, pp. 4541-4568. https://doi.org/10.1108/ECAM-02-2022-0161