Increasing production efficiency through the reduction of transportation activities and time using 4D BIM simulations

Cristina Toca Pérez (Department of Structural and Construction, Universidade Federal da Bahia, Salvador, Brazil)
Dayana Bastos Costa (Structural and Cosntruction Engineering, Universidade Federal da Bahia Escola Politecnica, Salvador, Brazil)

Engineering, Construction and Architectural Management

ISSN: 0969-9988

Article publication date: 6 January 2021

Issue publication date: 26 October 2021

871

Abstract

Purpose

This paper proposes to apply the lean philosophy principle of minimizing or eliminating non-value adding activities combined with 4D building information modeling (BIM) simulations to reduce transportation waste in construction production processes.

Design/methodology/approach

This study adopts design science research (DSR) because of its prescriptive character to produce innovative constructions (artifacts) to solve real-world problems. The artifact proposed is a set of constructs for evaluating the utility of 4D BIM simulations for transportation waste reduction. The authors performed two learning cycles using empirical studies in projects A, B and C. The construction process of cast-in-place (CIP) reinforcement concrete (RC) was selected to demonstrate and evaluate 4D BIM's utility. The empirical studies focused on understanding the current transportation waste, collecting actual performance data during job site visits and demonstrating the usage of 4D BIM.

Findings

In the first cycle, 4D BIM successfully allowed users to understand the CIP-RC process's transportation activities, which were modeled. In the second cycle, 4D BIM enabled better decision-making processes concerning the definitions of strategies for placing reusable formworks for CIP concrete walls by planning transportation activities.

Practical implications

In Cycle 2, three different scenarios were simulated to identify the most suitable formwork assembly planning, and the results were compared to the real situations identified during the job site visits. The scenario chosen demonstrated that the 4D BIM simulation yielded an 18.75% cycle time reduction. In addition, the simulation contributed to a decrease in transportation waste that was previously identified.

Originality/value

The original contribution of this paper is the use of 4D BIM simulation for managing non-value adding activities to reduce transportation waste. The utility of 4D BIM for the reduction of those conflicts considered three constructs: (1) the capacity to improve transportation activity efficiency, (2) the capacity to improve construction production efficiency and (3) the capacity to reduce transportation waste consequences.

Keywords

Acknowledgements

This work was supported by the Ministry of Education of Brazil through the Agency for Support and Evaluation of Graduate Education (CAPES) with Grant PROCAD 071/2013-CAPES (Number 2954/2014) and with student scholarship support.

Citation

Pérez, C.T. and Bastos Costa, D. (2021), "Increasing production efficiency through the reduction of transportation activities and time using 4D BIM simulations", Engineering, Construction and Architectural Management, Vol. 28 No. 8, pp. 2222-2247. https://doi.org/10.1108/ECAM-02-2020-0132