Determining and assessing the significant barriers of transferring unfinished construction projects from the public sector to the private sector in Iran

Hadi Sarvari (Department of Civil Engineering, Isfahan (Khorasgan) Branch, Islamic Azad University, Isfahan, Iran)
Hala Nassereddine (Department of Civil Engineering, University of Kentucky, Lexington, Kentucky, USA)
Daniel W.M. Chan (Department of Building and Real Estate, The Hong Kong Polytechnic University, Hung Hom, Kowloon, Hong Kong SAR, China)
Mohsen Amirkhani (Department of Civil Engineering, Isfahan (Khorasgan) Branch, Islamic Azad University, Isfahan, Iran)
Norhazilan Md Noor (Construction Research Centre, School of Civil Engineering, Universiti Teknologi Malaysia, Johor, Malaysia)

Construction Innovation

ISSN: 1471-4175

Article publication date: 31 December 2020

Issue publication date: 21 October 2021

279

Abstract

Purpose

The government sometimes lacks sufficient financial, management and technical capabilities to deliver construction projects. As a result, it has recognized the need to introduce private sector capital and expertise to complete unfinished construction projects. This outsourcing paradigm is known as a public-private partnership, a form of privatization. This study aims to identify the barriers associated with the transfer of unfinished construction projects to the private sector in Iran and grouped them into areas that were ranked to shed light on where the risk lies.

Design/methodology/approach

After a thorough and comprehensive literature review, a questionnaire was developed and distributed to 67 experts in the public and private sectors in Iran. The survey included 37 barriers grouped into seven areas and measured on a five-point Likert scale. Face validity, content validity and structural validity of the collected data were confirmed. The reliability of the questionnaire was also tested and validated using Cronbach’s alpha coefficient.

Findings

The survey findings indicated that private company laws, national constitution, government policies, lack of sufficient regulations, one-sided regulations and lack of balance, the regulations of other organizations and taxation laws were perceived as the major barriers to the transfer of unfinished public sector construction projects to the private sector in Iran. The ranking of the seven areas produced the following top three ranked barriers areas: taxation laws, government policies and one-sided regulations and lack of balance of importance.

Originality/value

The elicitation of this study can be useful to both private and public sectors for the development of infrastructure construction projects.

Keywords

Citation

Sarvari, H., Nassereddine, H., Chan, D.W.M., Amirkhani, M. and Md Noor, N. (2021), "Determining and assessing the significant barriers of transferring unfinished construction projects from the public sector to the private sector in Iran", Construction Innovation, Vol. 21 No. 4, pp. 592-607. https://doi.org/10.1108/CI-07-2020-0112