Short‐line railroad management system for bridge prioritization

Robert C. Guyer (NTM Engineering, Inc, Dillsburg, Pennsylvania, USA)
Jeffrey A. Laman (Department of Civil and Environmental Engineering, The Pennsylvania State University, University Park, Pennsylvania, USA)

Built Environment Project and Asset Management

ISSN: 2044-124X

Publication date: 6 July 2012

Abstract

Purpose

–

Limited funding to maintain and preserve short‐line railroad (SLRR) bridge infrastructure requires that important priority decisions be made on an annual basis. The compartmentalized, dispersed, and diverse nature of many SLRR owners and operators is such that there is a need for a coordinated and centralized effort to evaluate the state‐wide system as a whole, to ensure the most effective overall resource allocation and also identify assets that either outperform predictions or consume disproportionate levels of resources for maintenance and operation, allowing for review of design and construction practices. The purpose of this paper is to examine the state of the art for railroad bridge population management and resource allocation decisions and to develop a state‐wide SLRR bridge prioritization methodology, to be used as a tool by a state agency to assist in allocating limited public funding for bridge maintenance, rehabilitation and replacement activities.

Design/methodology/approach

–

A literature review examining the state of the art of railroad bridge population management and resource allocation decisions was conducted, which provided the foundation for the development of a bridge prioritization algorithm. A state‐wide survey was conducted to develop a bridge database. A detailed evaluation of a statistically significant sample of bridges was conducted, to determine the structural and maintenance needs and preservation status of sub‐populations. The research team developed methodologies, applicable to the entire population, to develop a ranking of bridge preservation candidates.

Findings

–

A risk‐based prioritization algorithm is proposed to assign a relative risk score to each bridge in the population. The algorithm provides a management tool for making more effective maintenance and preservation decisions. Additionally, the bridge database allows managers to examine sub‐populations according to structural parameters to evaluate performance.

Originality/value

–

The revisable, modular framework of the prioritization algorithm provides a simple, effective and versatile tool for asset management and evaluation. The present proposal of this new prioritization methodology for SLRR bridges is a valuable tool for agencies faced with making rational decisions with limited information. Such a methodology does not currently exist in the literature and is of significant interest to short‐line owners/operators and state transportation agencies.

Keywords

  • United States of America
  • Rail bridges
  • Railways
  • Maintenance programmes
  • Decision support systems
  • Database management
  • Asset management
  • Risk assessment

Citation

Guyer, R.C. and Laman, J.A. (2012), "Short‐line railroad management system for bridge prioritization", Built Environment Project and Asset Management, Vol. 2 No. 1, pp. 25-40. https://doi.org/10.1108/20441241211235035

Download as .RIS

Publisher

:

Emerald Group Publishing Limited

Copyright © 2012, Emerald Group Publishing Limited

Please note you do not have access to teaching notes

You may be able to access teaching notes by logging in via Shibboleth, Open Athens or with your Emerald account.
Login
If you think you should have access to this content, click the button to contact our support team.
Contact us

To read the full version of this content please select one of the options below

You may be able to access this content by logging in via Shibboleth, Open Athens or with your Emerald account.
Login
To rent this content from Deepdyve, please click the button.
Rent from Deepdyve
If you think you should have access to this content, click the button to contact our support team.
Contact us
Emerald Publishing
  • Opens in new window
  • Opens in new window
  • Opens in new window
  • Opens in new window
© 2021 Emerald Publishing Limited

Services

  • Authors Opens in new window
  • Editors Opens in new window
  • Librarians Opens in new window
  • Researchers Opens in new window
  • Reviewers Opens in new window

About

  • About Emerald Opens in new window
  • Working for Emerald Opens in new window
  • Contact us Opens in new window
  • Publication sitemap

Policies and information

  • Privacy notice
  • Site policies
  • Modern Slavery Act Opens in new window
  • Chair of Trustees governance statement Opens in new window
  • COVID-19 policy Opens in new window
Manage cookies

We’re listening — tell us what you think

  • Something didn’t work…

    Report bugs here

  • All feedback is valuable

    Please share your general feedback

  • Member of Emerald Engage?

    You can join in the discussion by joining the community or logging in here.
    You can also find out more about Emerald Engage.

Join us on our journey

  • Platform update page

    Visit emeraldpublishing.com/platformupdate to discover the latest news and updates

  • Questions & More Information

    Answers to the most commonly asked questions here