The development of a lean park homes production process using process flow and simulation methods

Jose Arturo Garza‐Reyes (School of Technology, The University of Derby, Derby, UK)
Ilias Oraifige (School of Technology, The University of Derby, Derby, UK)
Horacio Soriano‐Meier (Northampton Business School, The University of Northampton, Northampton, UK)
Paul L. Forrester (Birmingham Business School, The University of Birmingham, Birmingham, UK)
Dani Harmanto (School of Technology, The University of Derby, Derby, UK)

Journal of Manufacturing Technology Management

ISSN: 1741-038X

Article publication date: 3 February 2012

1536

Abstract

Purpose

Continuous process flow is a prerequisite of lean systems as it helps to reduce throughput times, improve quality, minimize operational costs, and shorten delivery times. The purpose of this paper is to empirically demonstrate the application of a methodology that combines a time‐based study, discrete‐event simulation and the trial and error method to enable a leaner process through more efficient line balancing and more effective flow for a park homes production process. This method is replicable across other contexts and industry settings.

Design/methodology/approach

The paper reviews the UK park homes production industry and, specifically, a major factory that builds these homes. It compares the factory method to traditional on‐site construction methods. An empirical study of production times was carried out to collect data in order to analyse the current workload distribution and the process flow performance of the park homes production process. Finally, seven discrete‐event simulation models were developed in order to test different scenarios and define the optimum line balance for every section of the production process.

Findings

By combining time study, discrete‐event simulation and trial and error methods, the workload distribution and process flow performance of the park homes production line were analysed and improved. A reduction of between 1.82 and 36.32 percent in balancing losses in some sections of the process was achieved.

Practical implications

This paper supports current knowledge on process flow improvement and line balancing by exploring and analysing these issues in a real‐life context. It can be used to guide production management practitioners in their selection of methods and demonstrates how they are exploited when seeking to improve process flow, efficiency and line balancing of production operations.

Originality/value

The study uses a real industrial application to demonstrate how the methodological combination and deployment of process flow improvement strategies, such as time study, simulation, and trial and error, can help organisations achieve process flow improvements and, as a consequence, a leaner production process.

Keywords

Citation

Arturo Garza‐Reyes, J., Oraifige, I., Soriano‐Meier, H., Forrester, P.L. and Harmanto, D. (2012), "The development of a lean park homes production process using process flow and simulation methods", Journal of Manufacturing Technology Management, Vol. 23 No. 2, pp. 178-197. https://doi.org/10.1108/17410381211202188